From Casetext: Smarter Legal Research

U.S. v. Lord

United States District Court, D. New Hampshire
May 26, 2009
Case No. 09-cr-83-PB (D.N.H. May. 26, 2009)

Opinion

Case No. 09-cr-83-PB.

May 26, 2009


ORDER


The defendant, through counsel, has moved to continue the trial scheduled for June 2, 2009, citing the need for additional time to finalize a plea agreement. The government does not object to a continuance of the trial date.

Accordingly, for the above reasons and to allow the parties additional time to properly prepare for trial, the court will continue the trial from June 2, 2009 to August 18, 2009. In agreeing to continue the trial, the court finds pursuant to 18 U.S.C.A. § 3161(h)(8)(A) that for the above-stated reasons, the ends of justice served in granting a continuance outweigh the best interests of the public and the defendant in a speedy trial.

The May 27, 2009 final pretrial conference is continued to July 21, 2009 at 3:00 p.m.

SO ORDERED.


Summaries of

U.S. v. Lord

United States District Court, D. New Hampshire
May 26, 2009
Case No. 09-cr-83-PB (D.N.H. May. 26, 2009)
Case details for

U.S. v. Lord

Case Details

Full title:United States of America v. Marion Lord

Court:United States District Court, D. New Hampshire

Date published: May 26, 2009

Citations

Case No. 09-cr-83-PB (D.N.H. May. 26, 2009)