The defendant, through counsel, has moved to continue the February 5, 2008 trial in the above case, citing the need for additional time to complete discovery review, engage in plea negotiations or prepare for trial. The government does not object to a continuance of the trial date.

Accordingly, for the above reasons and to allow the parties additional time to properly prepare for trial, the court will continue the trial from February 5, 2008 to May 6, 2008. In agreeing to continue the trial, the court finds pursuant to 18 U.S.C.A. § 3161(h)(8)(A) that for the above-stated reasons, the ends of justice served in granting a continuance outweigh the best interests of the public and the defendant in a speedy trial.

The January 31, 2008 final pretrial conference is continued to April 22, 2008 at 4:30 p.m.

SO ORDERED.


Summaries of

U.S. v. Berg

United States District Court, D. New Hampshire
Jan 22, 2008
Case No. 07-cr-236-PB (D.N.H. Jan. 22, 2008)
Case details for

U.S. v. Berg

Case Details

Full title:United States of America v. Joshua Berg

Court:United States District Court, D. New Hampshire

Date published: Jan 22, 2008

Citations

Case No. 07-cr-236-PB (D.N.H. Jan. 22, 2008)