U.S., ex Rel. Glumac v. Don Todd Associates, Inc.

United States District Court, N.D. California
Feb 23, 2010
No. C 09-01442 WHA (N.D. Cal. Feb. 23, 2010)

Opinion

No. C 09-01442 WHA.

February 23, 2010


ORDER GRANTING COSTS AND DENYING INTEREST


In this action involving claims for violation of the False Claims Act and breach of contract, default judgment was entered in favor of relator and qui tam plaintiff Glumac against defendant Don Todd Associates, Inc. in the amount of $62,512.00. Plaintiff's request for costs was denied without prejudice because plaintiff did not properly document the costs it incurred or why they were reasonable. Plaintiff was invited to submit documentation in support of its request for costs. Plaintiff has now submitted a sworn declaration and detailed explanation of its request for an award of costs of $2,943.48. Accordingly, plaintiff's request for an award of $2,943.48 for costs is GRANTED.

Plaintiff also now requests that the Court award interest on its monetary damages arising out of its breach of contract claim. Section 3302 of the California Civil Code allows for an award of interest but no interest was previously awarded because plaintiff did not seek interest in its motion for default judgment. Because plaintiff did not previously move for interest, its request now is DENIED as untimely.

IT IS SO ORDERED.


Summaries of

U.S., ex Rel. Glumac v. Don Todd Associates, Inc.

United States District Court, N.D. California
Feb 23, 2010
No. C 09-01442 WHA (N.D. Cal. Feb. 23, 2010)
Case details for

U.S., ex Rel. Glumac v. Don Todd Associates, Inc.

Case Details

Full title:UNITED STATES OF AMERICA, ex rel. GLUMAC, a California corporation…

Court:United States District Court, N.D. California

Date published: Feb 23, 2010

Citations

No. C 09-01442 WHA (N.D. Cal. Feb. 23, 2010)