From Casetext: Smarter Legal Research

Town of Mexico v. Cnty. of Oswego

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
Aug 22, 2019
175 A.D.3d 876 (N.Y. App. Div. 2019)

Summary

finding that the plaintiff's submission of invoices within thirty days of performing work was a condition precedent to its right to payment

Summary of this case from Gramercy Holdings I, LLC v. Matec S.R.L.

Opinion

243 CA 18–01946

08-22-2019

TOWN OF MEXICO, Plaintiff–Appellant, v. COUNTY OF OSWEGO and County of Oswego Highway Department, Defendants–Respondents.

BOND, SCHOENECK & KING, PLLC, SYRACUSE (DANIEL J. PAUTZ OF COUNSEL), FOR PLAINTIFF–APPELLANT. RICHARD C. MITCHELL, COUNTY ATTORNEY, OSWEGO (RICHARD C. MITCHELL OF COUNSEL), FOR DEFENDANTS–RESPONDENTS.


BOND, SCHOENECK & KING, PLLC, SYRACUSE (DANIEL J. PAUTZ OF COUNSEL), FOR PLAINTIFF–APPELLANT.

RICHARD C. MITCHELL, COUNTY ATTORNEY, OSWEGO (RICHARD C. MITCHELL OF COUNSEL), FOR DEFENDANTS–RESPONDENTS.

PRESENT: WHALEN, P.J., SMITH, CARNI, NEMOYER, AND CURRAN, JJ.

MEMORANDUM AND ORDER It is hereby ORDERED that the judgment so appealed from is unanimously modified on the law by denying the motion in part and reinstating the breach of contract cause of action insofar as it alleges that defendants waived the 30–day billing deadline, and as modified the judgment is affirmed without costs.

Memorandum: In this action to recover damages for, inter alia, breach of contract, plaintiff appeals from a judgment granting defendants' pre-answer motion to dismiss the complaint. In November 2016, plaintiff entered into a contract with defendant County of Oswego Highway Department pursuant to which plaintiff agreed to provide snow and ice removal services on certain county roads. Article 4 of the contract included a billing deadline clause that required plaintiff to submit to defendant County of Oswego (County) all invoices within 30 days of the work and services performed. It further provided that: "Any compensation for the work and services performed and submitted after the [30–day] billing deadline shall be deemed to be forfeited by [plaintiff]." Plaintiff performed approximately $26,000 worth of snow and ice removal services during the month of December 2016, but did not submit the invoices for that month until February 9, 2017. The County refused to reimburse plaintiff on the ground that the invoices were not submitted within the requisite 30 days. Plaintiff commenced this action against defendants, asserting causes of action for breach of contract and unjust enrichment. With respect to the breach of contract cause of action, plaintiff alleged in its complaint that defendants had waived the 30–day billing deadline clause by previously accepting late invoices under the current contract and prior agreements with identical provisions and that the billing deadline clause constituted an unenforceable penalty. Before answering, defendants moved to dismiss the complaint based on, inter alia, documentary evidence (see CPLR 3211[a][1] ). Supreme Court granted the motion on that basis, and plaintiff appeals.

"When a court rules on a CPLR 3211 motion to dismiss, it ‘must accept as true the facts as alleged in the complaint and submissions in opposition to the motion, accord [the] plaintiff[ ] the benefit of every possible favorable inference and determine only whether the facts as alleged fit within any cognizable legal theory’ " ( Whitebox Concentrated Convertible Arbitrage Partners, L.P. v. Superior Well Servs., Inc., 20 N.Y.3d 59, 63, 956 N.Y.S.2d 439, 980 N.E.2d 487 [2012] ; see Leon v. Martinez, 84 N.Y.2d 83, 87–88, 614 N.Y.S.2d 972, 638 N.E.2d 511 [1994] ). "A motion to dismiss pursuant to CPLR 3211(a)(1) will be granted if the documentary evidence resolves all factual issues as a matter of law, and conclusively disposes of the [plaintiff's] claim[s]" ( Lots 4 Less Stores, Inc. v. Integrated Props., Inc., 152 A.D.3d 1181, 1182, 59 N.Y.S.3d 628 [4th Dept. 2017] [internal quotation marks omitted] ).

Contrary to plaintiff's contention, the court properly granted the motion with respect to the unjust enrichment cause of action inasmuch as the documentary evidence established as a matter of law that a valid and enforceable contract exists between the parties (see Goldman v. Metropolitan Life Ins. Co., 5 N.Y.3d 561, 572, 807 N.Y.S.2d 583, 841 N.E.2d 742 [2005] ; see also Auble v. Doyle, 38 A.D.3d 1264, 1266, 832 N.Y.S.2d 715 [4th Dept. 2007] ).

With respect to the breach of contract cause of action, we reject plaintiff's contention that the billing deadline clause is an unenforceable penalty and conclude that the clause is instead an enforceable condition precedent to plaintiff's right to payment (see Tops Mkts. v. S & R Co. of W. Seneca, 275 A.D.2d 988, 988–989, 713 N.Y.S.2d 796 [4th Dept. 2000] ; see generally 1029 Sixth v. Riniv Corp., 9 A.D.3d 142, 149–150, 777 N.Y.S.2d 122 [1st Dept. 2004], lv dismissed 4 N.Y.3d 795, 795 N.Y.S.2d 170, 828 N.E.2d 86 [2005] ; Weisblatt v. Schwimmer, 249 A.D.2d 297, 298, 670 N.Y.S.2d 891 [2d Dept. 1998] ). We agree with plaintiff, however, that the court erred in granting defendants' motion with respect to that cause of action insofar as it alleges that defendants waived the 30–day billing deadline, and we therefore modify the judgment accordingly. Although the contract unambiguously provided a 30–day billing deadline, the complaint alleged that the County had previously accepted invoices submitted past the 30–day deadline and thus that defendants had waived the 30–day provision. It is well settled that the abandonment of a contractual right " ‘may be established by affirmative conduct or by failure to act so as to evince an intent not to claim a purported advantage’ " ( Fundamental Portfolio Advisors, Inc. v. Tocqueville Asset Mgt., L.P., 7 N.Y.3d 96, 104, 817 N.Y.S.2d 606, 850 N.E.2d 653 [2006] ). Whether a party intended to waive a contractual right is a question of fact (see id. ) and, in our view, the documentary evidence submitted in support of defendants' motion failed to "utterly refute ... plaintiff's factual allegations [that defendants waived the 30–day billing deadline clause] or conclusively establish a defense as a matter of law" ( Vassenelli v. City of Syracuse, 138 A.D.3d 1471, 1473, 31 N.Y.S.3d 320 [4th Dept. 2016] [internal quotation marks omitted] ). Additionally, contrary to defendants' contention, the fact that the 30–day billing deadline clause is unambiguous does not change this result. In its complaint, plaintiff does not challenge the plain meaning of the billing deadline clause, but rather asserts that defendants, through their conduct, waived a contractual right that "but for the waiver, would have been enforceable" ( Nassau Trust Co. v. Montrose Concrete Prods. Corp., 56 N.Y.2d 175, 184, 451 N.Y.S.2d 663, 436 N.E.2d 1265 [1982], rearg. denied 57 N.Y.2d 674, 454 N.Y.S.2d 1032, 439 N.E.2d 1247 [1982] ).


Summaries of

Town of Mexico v. Cnty. of Oswego

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
Aug 22, 2019
175 A.D.3d 876 (N.Y. App. Div. 2019)

finding that the plaintiff's submission of invoices within thirty days of performing work was a condition precedent to its right to payment

Summary of this case from Gramercy Holdings I, LLC v. Matec S.R.L.
Case details for

Town of Mexico v. Cnty. of Oswego

Case Details

Full title:TOWN OF MEXICO, PLAINTIFF-APPELLANT, v. COUNTY OF OSWEGO AND COUNTY OF…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department

Date published: Aug 22, 2019

Citations

175 A.D.3d 876 (N.Y. App. Div. 2019)
107 N.Y.S.3d 221
2019 N.Y. Slip Op. 6242

Citing Cases

Bisimwa v. St. John Fisher Coll.

Thus, contrary to defendants’ assertion, even if an "applicable law" permitted disclosure such that there…

Gramercy Holdings I, LLC v. Matec S.R.L.

The issuance of appropriate invoices could conceivably be a condition precedent to Noranda's obligation to…