From Casetext: Smarter Legal Research

Tompkins Fin. Corp. v. John M. Floyd & Assocs., Inc.

Supreme Court, Appellate Division, Third Department, New York.
Nov 3, 2016
144 A.D.3d 1252 (N.Y. App. Div. 2016)

Opinion

11-03-2016

TOMPKINS FINANCIAL CORPORATION, Respondent, v. JOHN M. FLOYD & ASSOCIATES, INC., Appellant.

Menter, Rudin & Trivelpiece, PC, Syracuse (Mitchell J. Katz of counsel), for appellant. Harris Beach, PLLC, Syracuse (David M. Capriotti of counsel), for respondent.


Menter, Rudin & Trivelpiece, PC, Syracuse (Mitchell J. Katz of counsel), for appellant.

Harris Beach, PLLC, Syracuse (David M. Capriotti of counsel), for respondent.

Before: PETERS, P.J., McCARTHY, LYNCH, ROSE and CLARK, JJ.

LYNCH, J. Appeal from an order of the Supreme Court (Mulvey, J.), entered October 2, 2015 in Tompkins County, which granted plaintiff's motion for, among other things, summary judgment.

Plaintiff is the parent company of a number of banks. In August 2011, plaintiff and defendant entered into an agreement wherein defendant agreed to provide consulting services to help plaintiff maximize the income earned through, among other things, its overdraft program. Pursuant to the agreement, the parties agreed that defendant would provide its services on a contingency basis and that its fee would be based on the amount of income earned above a baseline amount that was to be established by defendant. Plaintiff paid a retainer fee and, in October 2011, plaintiff agreed to defendant's preliminary baseline amount, subject to certain adjustments. Thereafter, defendant engaged in its contractually requisite analysis and recommended that plaintiff make certain changes to its overdraft program. In February 2012, defendant proposed and plaintiff accepted a baseline that was calculated based on plaintiff's response to defendant's recommendations. Indisputably, plaintiff never experienced the anticipated income increase.

In June 2012, defendant advised that the February 2012 baseline was incorrect and proposed that it be decreased. After the parties were unable to agree to a revised baseline, plaintiff commenced this action seeking rescission of the agreement and a return of the $25,000 retainer payment. Defendant asserted counterclaims for, among other things, breach of contract, unjust enrichment and reformation. Following joinder of issue and some discovery, Supreme Court granted plaintiff's motion for summary judgment on its claim for a declaratory judgment and for dismissal of the counterclaims. Defendant now appeals.

The general, well-settled rule with regard to contract interpretation is that an agreement “is to be construed in accordance with the parties' intent, which is generally discerned from the four corners of the document itself. Consequently, a written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (IDT Corp. v. Tyco Group, S.A.R.L., 13 N.Y.3d 209, 214, 890 N.Y.S.2d 401, 918 N.E.2d 913 [2009] [internal quotation marks and citations omitted] ). Unless we find that a term of the agreement is ambiguous, extrinsic evidence is not admissible to aid its interpretation (see Schron v. Troutman Sanders LLP, 20 N.Y.3d 430, 436, 963 N.Y.S.2d 613, 986 N.E.2d 430 [2013] ). Further, while “a mere agreement to agree, in which a material term is left for future negotiations, is unenforceable” (Joseph Martin, Jr., Delicatessen v. Schumacher, 52 N.Y.2d 105, 109, 436 N.Y.S.2d 247, 417 N.E.2d 541 [1981] ), “it is also plain that all the terms contemplated by the agreement need not be fixed with complete and perfect certainty for a contract to have legal efficacy” (Kolchins v. Evolution Mkts., Inc., 128 A.D.3d 47, 61, 8 N.Y.S.3d 1 [2015] ).

Here, the agreement obligated defendant to install an overdraft program that conformed to all applicable laws and regulations. Further, defendant agreed to analyze plaintiff's accounts and make recommendations that would, ideally, maximize plaintiff's overdraft income. Payment for defendant's services was agreed to be on a contingency basis—that is, defendant would bill plaintiff a percentage of the “monthly quantified net increase in non-interest income and expenses related to [insufficient funds] and overdraft income” (hereinafter lift). The increases were calculated against a “baseline,” established by calculating the “net average existing [insufficient funds] and [overdraft] revenue” earned from eligible checking accounts during a “base period” using historical data. The agreement provided that, once the baseline was established, the program would run for 60 days before plaintiff would be billed for any increased revenue.

Indisputably, no lift was realized during the 60 days following the proposed February 2012 baseline. The issue between the parties appears to stem from the data used to develop the February 2012 baseline, an error not discovered until September 2012. The parties agree that during the baseline period, plaintiff's banks were not compliant with certain regulations regarding the order that payments should be posted to account balances. When defendant attempted to replicate compliance using the historical data provided by plaintiff, it posted the debits to incorrect account balances. Defendant now claims that the September 2012 baseline was the correct baseline and that, if it were applied, it would be evident that plaintiff actually realized an approximately $3,000,000 lift. Plaintiff did not agree to the revised baseline amounts proposed in June or September 2012 and, by its motion, sought a declaration that the contract was terminated, that it owed no money to defendant and that it was entitled to a refund of the retainer.

Plaintiff provided a report generated after the close of business showing amounts for both the “current balance” and “avail[able] bal[ance] for [payment]” for each listed account. Defendant, which was trying to analyze and reapply the historical data as if plaintiff had been compliant, asked which amount was the beginning balance used for posting payments. Plaintiff advised that it was the latter. Defendant interpreted that to mean that the “available balance for payment” was the beginning balance on the day of the report, while, in reality, because the report was generated after the close of business, it was the beginning balance available for the next day. Consequently, the baseline amount was based on a flawed application of the data.


Supreme Court determined that, because the baseline was an indefinite material term, the agreement was unenforceable as a “mere agreement to agree” (Joseph Martin, Jr., Delicatessan v. Schumacher, 52 N.Y.2d at 109, 436 N.Y.S.2d 247, 417 N.E.2d 541 ). We do not agree. “[W]here it is clear from the language of an agreement that the parties intended to be bound and there exists an objective method for supplying a missing term, the court should endeavor to hold the parties to their bargain. Striking down a contract as indefinite and in essence meaningless is at best a last resort” (Matter of 166 Mamaroneck Ave. Corp. v. 151 E. Post Rd. Corp., 78 N.Y.2d 88, 91, 571 N.Y.S.2d 686, 575 N.E.2d 104 [1991] [internal quotation marks and citations omitted]; see Cobble Hill Nursing Home v. Henry & Warren Corp., 74 N.Y.2d 475, 483, 548 N.Y.S.2d 920, 548 N.E.2d 203 [1989], cert. denied 498 U.S. 816, 111 S.Ct. 58, 112 L.Ed.2d 33 [1990] ). If, “at the time of agreement the parties have manifested their intent to be bound, a price term may be sufficiently definite if the amount can be determined objectively without the need for new expressions by the parties; ... for example, [the price term might] be ... ascertained by reference to an extrinsic event” (Cobble Hill Nursing Home v. Henry & Warren Corp., 74 N.Y.2d at 483, 548 N.Y.S.2d 920, 548 N.E.2d 203 ; see Seton Health at Schuyler Ridge Residential

Health Care v. Dziuba, 127 A.D.3d 1297, 1298–1299, 6 N.Y.S.3d 750 [2015] ). Here, the parties' conduct evinced that they intended to be bound by the agreement and, in our view, the baseline could be ascertained with reference to an extrinsic event, that is, defendant's calculation derived from the existing historical data (see Village of Lansing v. Triphammer Dev. Co., 193 A.D.2d 919, 920–921, 597 N.Y.S.2d 766 [1993] ). Accordingly, we find that the agreement was enforceable.

Turning to plaintiff's motion for summary judgment, the clear and unambiguous language of the contract provides that, “[i]n any event, if the baseline is not mutually agreed upon by both [plaintiff and defendant], [the agreement would] be considered terminated and no longer in full force and effect, subject to [plaintiff] paying travel and reasonable out of pocket expanses incurred by [defendant], and [defendant] shall promptly return the $25,000 retainer payment.” While the evidence demonstrates that the October 2011 baseline was agreed to, the agreement was subject to further adjustment. Plaintiff claims that it agreed to the February 2012 adjusted baseline, but defendant rescinded that baseline and proposed two more, neither of which were agreed to by plaintiff. Frank Fetsko, plaintiff's executive vice-president, submitted an affidavit confirming that if the September 2012 baseline had been proposed earlier, plaintiff would not have accepted it. Indisputably, there was never an agreement with regard to the baseline. Accordingly, the plain and unambiguous language of the agreement is prima facie proof of plaintiff's entitlement to summary judgment (see Heritage Springs Sewer Works, Inc. v. Boghosian, 61 A.D.3d 1038, 1041, 875 N.Y.S.2d 635 [2009] ).

Defendant now argues that once plaintiff agreed to the October 2011 baseline, plaintiff waived its right to terminate the agreement. As stated, however, the parties never agreed to a defined baseline. Moreover, because defendant did not plead the affirmative defense of waiver, defendant is precluded from raising this defense (see CPLR 3018 ; McIntosh v. Niederhoffer, Cross & Zeckhauser, 106 A.D.2d 774, 775, 483 N.Y.S.2d 807 [1984], lv. denied 64 N.Y.2d 608, 488 N.Y.S.2d 1023, 477 N.E.2d 1107 [1985] ).

We further find that Supreme Court properly dismissed defendant's first and second counterclaims for reformation and damages. In order to support a claim for reformation based on a mistake, defendant has the burden of establishing, “by clear and convincing evidence, that the writing in question was executed under mutual mistake or unilateral mistake coupled with fraud” (Timber Rattlesnake, LLC v. Devine, 117 A.D.3d 1291, 1292, 986 N.Y.S.2d 278 [2014] [internal quotation marks and citation omitted], lv.

denied 24 N.Y.3d 904, 2014 WL 4548528 [2014] ). Defendant must “show in no uncertain terms, not only that mistake or fraud exists, but exactly what was really agreed upon between the parties” (George Backer Mgt. Corp. v. Acme Quilting Co., 46 N.Y.2d 211, 219, 413 N.Y.S.2d 135, 385 N.E.2d 1062 [1978] ; see Rosen Auto Leasing, Inc. v. Jacobs, 9 A.D.3d 798, 800, 780 N.Y.S.2d 438 [2004] ).

Here, the parties did not make a mistake with regard to the meaning or interpretation of their agreement. Rather, defendant contends that the parties mistakenly agreed to the October 2011 baseline calculation. As stated, however, the record confirms that the October 2011 agreement was a preliminary one, made with the knowledge that it was subject to adjustment. Indisputably, it was defendant's contractual obligation to complete the calculation and, as set forth above, plaintiff was under no contractual obligation to accept the calculation. In our view, it is immaterial whether the adjusted February 2012 calculations were based upon a mistake because defendant rejected them and recalculated the baseline. The parties then never agreed to the readjusted calculations. To hold otherwise would require us to rewrite the agreement as obligating plaintiff to accept the proposed baseline—an interpretation in contravention of the express terms of the agreement. Because defendant raises no material factual questions warranting a trial and because we must enforce the plain and unambiguous terms of the agreement as written (see Maines Paper & Food Serv., Inc. v. Pike Co., Inc., 137 A.D.3d 1366, 1368, 26 N.Y.S.3d 646 [2016] ), we find that Supreme Court properly granted plaintiff's motion for summary judgment on its cause of action for a declaratory judgment and for dismissal of defendant's counterclaims for reformation, damages upon such reformation and breach of contract.

Supreme Court also properly dismissed defendant's third counterclaim seeking damages based on unjust enrichment. A successful claim for unjust enrichment exists where a party is “enriched at [the claiming party's] expense and ... it is against equity and good conscience to permit the [enriched party] to retain what is sought to be recovered” (Silipo v. Wiley, 138 A.D.3d 1178, 1180, 30 N.Y.S.3d 716 [2016] [internal quotation marks and citation omitted] ). “A ‘quasi contract’ only applies in the absence of an express agreement, and is not really a contract at all, but rather a legal obligation imposed in order to prevent a party's unjust enrichment” (Clark–Fitzpatrick, Inc. v. Long Is. R.R. Co., 70 N.Y.2d 382, 388, 521 N.Y.S.2d 653, 516 N.E.2d 190 [1987] [citations omitted] ). Accordingly, a party cannot recover damages for unjust enrichment based on conduct or events governed by a written agreement (see Simkin

v. Blank, 19 N.Y.3d 46, 55, 945 N.Y.S.2d 222, 968 N.E.2d 459 [2012] ). Here, we have determined that the agreement was valid and enforceable and defendant seeks to change the terms of the agreement to allow it to unilaterally impose a baseline calculation and to recover sums ostensibly due upon such baseline. This remedy would contradict the express terms of the agreement, and the existence of the valid, enforceable agreement precludes any such recovery based on quasi contract and unjust enrichment (see Clark–Fitzpatrick, Inc. v. Long Is. R.R. Co., 70 N.Y.2d at 388, 521 N.Y.S.2d 653, 516 N.E.2d 190 ; Mascorp, Inc. v. United States Fid. & Guar. Co., 122 A.D.3d 1195, 1196–1197, 997 N.Y.S.2d 537 [2014] ; State of New York v. Industrial Site Servs., Inc., 52 A.D.3d 1153, 1161, 862 N.Y.S.2d 118 [2008] ).

Supreme Court also properly dismissed defendant's counterclaim for breach of the covenant of good faith and fair dealing. This covenant, implied in all contracts in this state, “embraces a pledge that neither party shall do anything which will have the effect of destroying or injuring the right of the other party to receive the fruits of the contract” (511 W. 232nd Owners Corp. v. Jennifer Realty Co., 98 N.Y.2d 144, 153, 746 N.Y.S.2d 131, 773 N.E.2d 496 [2002] [internal quotation marks and citations omitted] ). “[T]he implied obligation is only in aid and furtherance of other terms of the agreement of the parties” (Trump on the Ocean, LLC v. State of New York, 79 A.D.3d 1325, 1326, 913 N.Y.S.2d 792 [2010] [internal quotation marks and citation omitted], lv. dismissed and denied 17 N.Y.3d 770, 929 N.Y.S.2d 74, 952 N.E.2d 1067 [2011] ; see Fahs Constr. Group, Inc. v. State of New York, 123 A.D.3d 1311, 1312, 999 N.Y.S.2d 244 [2014], lv. denied 25 N.Y.3d 902, 2015 WL 1471636 [2015] ). Defendant does not cite any applicable, supporting provision of the agreement and, in contrast, we have concluded that plaintiff was expressly permitted to reject the baseline. Accordingly, there is no basis to claim that plaintiff breached the covenant of good faith and fair dealing (see Fahs Constr. Group, Inc. v. State of New York, 123 A.D.3d at 1312, 999 N.Y.S.2d 244 ; Rooney v. Slomowitz, 11 A.D.3d 864, 867, 784 N.Y.S.2d 189 [2004] ). Finally, since Supreme Court did not make a declaration, we must modify the order accordingly.

We have considered the parties' remaining contentions and, in light of the foregoing, find them to be either moot or without merit.

ORDERED that the order is modified, on the law, with costs to plaintiff, by declaring that the agreement between the parties is terminated and defendant shall refund the retainer amount to plaintiff, less defendant's travel expenses and reasonable out-of-pocket expenses, and, as so modified, affirmed.

PETERS, P.J., McCARTHY, ROSE and CLARK, JJ., concur.


Summaries of

Tompkins Fin. Corp. v. John M. Floyd & Assocs., Inc.

Supreme Court, Appellate Division, Third Department, New York.
Nov 3, 2016
144 A.D.3d 1252 (N.Y. App. Div. 2016)
Case details for

Tompkins Fin. Corp. v. John M. Floyd & Assocs., Inc.

Case Details

Full title:TOMPKINS FINANCIAL CORPORATION, Respondent, v. JOHN M. FLOYD & ASSOCIATES…

Court:Supreme Court, Appellate Division, Third Department, New York.

Date published: Nov 3, 2016

Citations

144 A.D.3d 1252 (N.Y. App. Div. 2016)
41 N.Y.S.3d 577
2016 N.Y. Slip Op. 7252

Citing Cases

Downstate at Lich Holding Co. v. Fortis Prop. Grp.

And NYUHC's decision not to lease the New Medical Site or hire Fortis to construct the New Medical Building…

Catlyn & Derzee, Inc. v. Amedore Land Developers, LLC

"[T]he theory of unjust enrichment lies as a quasi-contract claim and contemplates an obligation imposed by…