From Casetext: Smarter Legal Research

Thorson v. Pfeifer

Supreme Court of South Dakota
Oct 13, 1966
145 N.W.2d 438 (S.D. 1966)

Summary

In Thorson v. Pfeifer, 82 S.D. 313, 145 N.W.2d 438 (1966), where a heating subcontractor returned voluntarily over three months after installation to inspect and winterize the unit, this court held that the 120-day filing period ran from installation and not the voluntary service call.

Summary of this case from Bachman Mech. v. Wal-Mart Real Estate Business Trust

Opinion

File No. 10295.

Opinion filed October 13, 1966

1. Mechanics' Liens.

In action to foreclose mechanic's lien based on subcontract for heating, air-conditioning and gutter work, evidence sustained finding that installation of heating and air-conditioning unit had been completed, within statute limiting time for filing lien statement, 243 days before lien statement was filed after house had been sold, though subcontractor, 119 days before filing lien statement but without request by either general contractor or owner, checked air conditioner, added freon gas and set blower to prevent unit from freezing. SDC 39.0708.

2. Mechanics' Liens.

One who furnishes or installs a fixture for another cannot unreasonably or indefinitely postpone time for filing lien statement by making periodic tests and service calls. SDC 39.0708.

3. Mechanics' Liens.

Generally, services, such as examination, regulation or repairs, performed by seller or party who made installation after installation of fixtures, machinery or attachments in a building, are not regarded as part of act of sale or installation and do not make time within which to file mechanic's lien based on original sale run from time of performance of such additional services. SDC 39.0708.

4. Mechanics' Liens.

Lien law should be construed favorably to laborer, but rights of owner and subsequent grantees should also be respected. SDC 39.0708.

5. Mechanics' Liens.

On appeal from judgment refusing to foreclose and cancelling mechanic's lien based on subcontract for heating, air-conditioning and gutter work, finding that materials and equipment installed by subcontractor could not be severed and removed from property without material injury thereto would not be disturbed in absence of any evidence to the contrary.

Appeal from Circuit Court, Minnehaha County; Hon. Roy D. Burns, Judge.

Action against owner and others to foreclose a mechanic's lien based on subcontract for heating, air conditioning and gutter work. From the entry of judgment cancelling his lien, plaintiff appeals.

Affirmed.

Dana, Golden, Moore Rasmussen, and Peder K. Ecker, Sioux Falls, for plaintiff and appellant.

May, Boe Johnson, and Paul V. Van Buren, Sioux Falls, for defendants and respondents.


In this action to foreclose a mechanic's lien the question is whether or not plaintiff timely filed a lien statement within 120 days after doing the last work or furnishing the last item of material in accordance with SDC 39.0708 as amended by Chapter 200, Laws of 1961. The question is presented by plaintiff's appeal from an adverse judgment canceling his lien.

It appears that defendant Pfeifer, Drake Dodge Company, a partnership, contracted with Duane Mahlstedt to construct a house on its property located at 2001 Allen Drive in Sioux Falls. Mahlstedt was a general contractor and commenced work on the house shortly after Christmas in 1963. He subcontracted the heating, air conditioning and gutter work to plaintiff Thorson for the sum of $1,133.

According to his lien statement plaintiff performed work and furnished materials on the house valued at $1,142.93 between January 21 and April 17, 1964. On April 30, 1964 he submitted a statement to Mahlstedt for the entire contractual amount of $1,133. Mahlstedt then considered plaintiff's work completed.

The house was open for public inspection for approximately a week during June 1965. The air conditioner was operated during this period. It was also operated and functioned properly throughout the summer when the house was shown to prospective buyers.

On August 19, 1964 which was one hundred and twenty-four days after April 17, 1964 plaintiff claims he performed work on defendants' property described in the lien statement as "check out furnace air conditioner, check out job complete $11.00". Plaintiff testified this item represented his final work on the job which consisted of checking the air conditioner, adding freon gas and setting the blower to prevent the unit from freezing. This work was not requested by either Mahlstedt or the defendant Pfeifer, Drake Dodge Company.

In November 1964 the house was sold to defendants, R.W. Jolley and Patsy L. Jolley on a Contract for Deed. On December 16, 1964 plaintiff filed his mechanic's lien. This was one hundred and nineteen days after August 19th and two hundred and forty-three days after April 17th. Therefore, the lien was timely filed if August 19, 1964 is considered to be the last day plaintiff furnished skill, labor, services, or materials on defendants' property or it was not timely filed, as the trial court found, if April 17, 1964 is considered to be the last day under our Mechanics' Lien Law.

[1-4] The trial court did not err. The heating and air conditioner unit was completely installed by plaintiff on or before April 17, 1964. Shortly after its installation a statement was submitted by plaintiff for the entire contractual amount due. The unit functioned properly. No request was made by the general contractor or the owners to have it corrected, tested, or serviced. One who wishes or installs a fixture for another cannot unreasonably or indefinitely postpone the time for filing a lien statement by simply making periodic tests and service calls. General Air Conditioning Corp. v. Stuewe, 156 Kan. 182, 131 P.2d 638, 143 A.L.R. 1184. The general rule is stated in the annotation appearing in 143 A.L.R. 1190: "With but few exceptions, it has been held, in the cases considering the question, that after the installation of fixtures, machinery, or attachments in a building, services in the form of examination or regulation of, or repairs to, such fixtures, machinery, or attachments, performed by the seller or the one making the installation, should not be regarded as a part of the act of sale or installation, so as to make the time within which to file a mechanic's lien based on such original act run from the time of performance of such additional services." The underlying principle is aptly stated in Hartley v. Richardson, 91 Me. 424, 40 A. 336, in the following language: "While the lien law should be construed favorably to the laborer, the rights of the owner and subsequent grantees should also be respected. The laborer ought not to be encouraged to leave some trifling matter incomplete, and wait to see if his payment is made, and if that fails, complete the trifling work left, and be allowed to revive and continue his lien, to the detriment of parties, who in good faith, relying upon the records, and the apparent completion of the work of the laborer, pay the contractor, or take a conveyance of the property. Protection to the laborer should not operate a fraud upon other innocent parties."

In the absence of any evidence to the contrary the trial court's finding that the materials and equipment installed by plaintiff cannot be severed and removed from the property without material injury thereto will not be disturbed on appeal.

Affirmed.

All the Judges concur.


Summaries of

Thorson v. Pfeifer

Supreme Court of South Dakota
Oct 13, 1966
145 N.W.2d 438 (S.D. 1966)

In Thorson v. Pfeifer, 82 S.D. 313, 145 N.W.2d 438 (1966), where a heating subcontractor returned voluntarily over three months after installation to inspect and winterize the unit, this court held that the 120-day filing period ran from installation and not the voluntary service call.

Summary of this case from Bachman Mech. v. Wal-Mart Real Estate Business Trust

In Thorson v. Pfeifer, 82 S.D. 313, 145 N.W.2d 438 (1966), where a heating subcontractor returned voluntarily over three months after installation to inspect and winterize the unit, this court held that the 120-day filing period ran from installation and not the voluntary service call.

Summary of this case from Wefel v. Harold J. Westin Associates, Inc.
Case details for

Thorson v. Pfeifer

Case Details

Full title:THORSON, Appellant v. PFEIFER et al., Respondents

Court:Supreme Court of South Dakota

Date published: Oct 13, 1966

Citations

145 N.W.2d 438 (S.D. 1966)
145 N.W.2d 438

Citing Cases

Bachman Mech. v. Wal-Mart Real Estate Business Trust

Par Golf contends that its filing was extended because it returned to the project on September 23-24, 2005,…

Wefel v. Harold J. Westin Associates, Inc.

In several of these cases, we have held that the 120-day period cannot be extended by a return to the…