Where an agreement was to do three things of different degrees of importance and value, or pay twenty-five hundred dollars as stipulated damages, and the breach assigned is the not doing one of the things which was readily ascertainable in value, and was clearly less than the sum specified as damages, the stipulation was held to be a penalty.
ACTION of COVENANT, tried before his Honor Judge DICK, at the Fall Term, 1854, of Tyrrel Superior Court.
Gilliam and Winston, Jr., for plaintiff.
Heath and Smith, for defendant.
The plaintiff declared upon the following obligation, viz: "Know all men by these presents, that I, W. W. Walker, of the county and State aforesaid, for the sale of one half the schooner named James F. Davenport, of Edenton, made to me this day by John Thoroughgood, do promise, covenant and agree to pay for the said, John Thoroughgood, one half of the debt due from said Thoroughgood, to Doyle, Durvin Rudder, which is about six hundred and seventy-five dollars: and I, the said W. W. Walker, do further covenant and agree for the same consideration, to pay the note of seven hundred and twenty dollars, which was given by the said Thoroughgood, to Casey Davis, and to which W. B. Etheridge and myself are sureties, as on reference to the said note will more fully appear. Now, if the said John Thoroughgood shall pay back to me, within three years from the date of this agreement, the sum of $675, together with the further sum of $720, and the interest on both amounts up to the time of the payment, then and in that case, I do promise, covenant and agree, to reconvey to the said John Thoroughgood, a title for one half of the schooner, named J. F. Davenport. And I, the said W. W. Walker, do further covenant and agree, to pay unto the said John Thoroughgood, the sum of twenty-five hundred dollars, as liquidated damages, in case of a failure on my part to comply with the terms of the above agreement. This 17th April, 1852."
The breach assigned was the non-conveyance of the schooner to plaintiff, at the end of the three years. The proof was, that before the expiration of the three years, the defendant sold the vessel to one Simmons, who repaired her and made her more valuable, but that at the time defendant parted with her, the half was not worth more than the amount plaintiff was to pay for the repurchase of her.
The plaintiff insisted, 1st, that the measure of his damages was the sum of twenty-five hundred dollars stipulated in the written contract.
2nd. That he was at least entitled to the difference between the value of half the schooner at the end of three years, (i.e. after the improvements were made upon her) and the amount of the redemption money, and called upon the Court so to charge, but his Honor declined giving such instruction and told the jury that the measure of damages was the difference between the value of one half of the schooner at the time of Walker's sale to Simmons, and the redemption money then to be paid with interest on that difference. Exception by plaintiff.
Under this instruction, the jury found a verdict for six pence damages.
Motion for a venire de novo for error in the instruction excepted to. Rule discharged. Judgment and appeal.
The bill of exceptions presents an interesting question of damages which has not hitherto been decided in this State. It has, however, been much discussed in England, and, after some conflict of judicial opinions, seems to be settled there upon just and equitable principles.
For the better elucidation of the subject, it may be proper to give a brief history of the manner in which the question came to be entertained in a Court of law: and to do this, we need only abridge the clear and accurate account contained in Mr. Sedgewick's Work on damages. (See chap. 16 of the 2nd edition.)
The obligation or bond of the English law is either a single one, in the form of a simple promise to pay money, under seal, or it has a clause appended declaring that the previous obligation shall be void on the payment of some lesser sum of money, or the performance of some particular act. The latter part or condition of the bond is that which discloses the real nature of the contract, and contains its essence. The former part is the penalty. Formerly, if the condition was not strictly complied with, as in regard to the payment of money on a certain day, the moment the day was passed, the penalty became the debt, and at law recoverable: and neither payment, nor tender after the day, would avail; because a condition once broken was gone forever. If the condition were to do any other thing than pay money and were not fulfilled, the penalty again became the debt, and was recoverable without any reference whatever to the actual damages incurred. In an action of debt upon the bond for a condition broken, the plaintiff recovered the penalty, and the action would not be relieved against either by payment or tender: no defense would avail but a release under seal. Hence the party was driven for relief to the Courts of Chancery, which interposed and would not allow the plaintiff to take more than, in conscience he ought: holding that the condition of the bond expressed the agreement of the parties, and that therefore, the defaulter should not be compelled to pay the penalty. This practice was followed by the common law Courts, which ordered the proceedings to be stayed upon the defendant's bringing into Court the principal, interest and cost. Finally, this discretionary power was confirmed by the Statute 4th Anne, ch. 16, sec. 12 and 13, which provided that in actions on bonds, with penalties, the defendant might plead payment after the day, or bring in the principal, interest and costs, and be discharged. This Statute has been enacted in this State, and forms the 106th and 107th sections of the 31st chapter of our Revised Statutes. By the Statute 8 and 9, Will. 3, ch. 2, sec. 8, (which forms the 63rd section of the same chapter of the Revised Statutes,) it had been declared not long before, "that in all actions, c., upon any bond or bonds, or on any penal sum for non-performance of any covenants or agreements in any indenture, deed or writing certain, the plaintiff or plaintiffs may assign as many breaches as he or they shall think fit, and the jury upon the trial of such action or actions, shall and may assess, not only such damages and costs of suit as have heretofore been usually done in such cases, but also damages for such of the said breaches so to be assigned, as the plaintiff, on the trial of the same, shall prove to have been broken." The words " may assign breaches," have been held to be imperative, and that a judgment obtained under the former practice would be erroneous, Rose v. Rosewell, 5 Term, Rep. 538.
These two Statutes have produced this result, that in the case of an agreement to do, or to refrain from doing, any particular act secured by a penalty, the amount of the penalty is in no sense the measure of compensation: and the plaintiff must show the particular injury of which he complains, and have his damages assessed by the jury.
But there is a class of cases, in which upon entering into an agreement, the parties, to avoid all future enquiries, as to the amount of damages which may result from the violation of the contract, may settle upon a definite sum, as that which shall be paid to the party who alleges and establishes the violation of the contract. In these cases, the damages so fixed upon, are termed liquidated, stipulated or stated damages. But even when this course has been adopted, the Courts both of Law and Equity will not always hold the definite sum named, as liquidated damages; but if from the words used, and the nature of the contract, they can infer that such was the intention of the parties, they will hold it to be a penalty. If from the nature of the agreement, it is clear that any attempt to get at the actual damages would be difficult, if not impossible, the Court will incline to give the stipulated damages which the parties have agreed on. But if, on the other hand, the contract is such, that the strict construction of the phraseology would work absurdity or oppression, the use of the term "liquidated damages," will not prevent the Courts from inquiring into the actual injury sustained, and doing justice between the parties. In the earlier cases on the subject, we may not perhaps be able to deduce any definite rule, but the later decisions will be found to establish the one, which we have stated, and which is extracted from Mr. Sedgewick's treatise. Without examining all the cases on the subject, we will refer to those cited by the defendant's counsel, which we think are decisive in the case before us. In Ashley v. Weldon, 2 Bos. and Pul. 346, an agreement was entered into by the defendant, to perform for the plaintiff, at his Theatre, and attend all rehearsals, or pay the established fines for all forfeitures of any kind whatsoever, with a clause that either of the parties, neglecting to perform the agreement, should pay the other 200 pounds; the declaration averred a refusal to perform, and the defendant pleaded non assumpsit. On the trial a verdict was taken for 20 pounds, with leave to the plaintiff to enter a verdict for 200 pounds, if the Court should consider the agreement one in the nature of liquidated damages. LORD ELDON, then Lord Chief Justice of the Common Pleas, in delivering the judgment of the Court, said, that he had felt much embarrassment in ascertaining the principle of the decisions, and that "this appeared to him the clearest principle; that where a doubt is stated, whether the sum inserted be a penalty or not, if a certain damages less than that sum is made payable upon the face of the same instrument, in case the act intended to be prohibited be done, that sum shall be construed to be a penalty; though the mere fact of the sums being apparently onerous and excessive, would not prevent it from being considered as liquidated damages." It was held to be a penalty. Kemble v. Farren, 6 Bing. Rep. 141, was a case very similar to the last, differing from it, however, in the use of the terms "liquidated and ascertained damages, and not a penalty or a penal sum, or in the nature thereof." The defendant had agreed with the plaintiff to act as principal comedian at Covent Garden, and to conform to its rules; the plaintiff was to pay 3 pounds, 6 shillings and 8 pence, every night that the theatre should be open; and the agreement contained a clause that if either a party failed to fulfil his agreement, or any part thereof, or any stipulation therein contained, such party should pay the other the sum of 1000 pounds, to which sum it was agreed that the damages should amount, and which sum was declared by the parties to be liquidated damages, and not a penalty or penal sum, or in the nature thereof: The breach alleged was a refusal to act during the second season, and the jury gave a verdict for 750 pounds. A motion was made to increase the verdict to 1000 pounds, on the ground that sum was the amount liquidated by the parties. The motion was denied, and the reasons for it were clearly and explicitly stated by the Chief Justice TINDAL. This case was distinctly recognized by the court of Exchequer, in Hamer v. Flintoff, 9 Mees. and Wels. 678, where the sum named was held to be a penalty: PARKE, Baron, saying "the rule laid down in Kemble v. Farren was, that when an agreement contained several stipulations of various degrees of importance and value, the sum agreed to be paid by the way of damages for the breach of any of them, shall be construed as a penalty, and not as liquidated damages, even though the parties, in express terms stated the contrary. When parties say that the same ascertained sum shall be paid for the breach of any article of the agreement, however minute and unimportant, they must be considered as not meaning exactly what they say, and a contrary intention may be collected from the other parts of the agreement." The same rule was again sanctioned in the subsequent case of Green v. Price, 13 Mees. and Wels. 695, though for the reasons therein stated, it was held not to govern that case. The defendant there had contracted not to practice as a performer within a certain district, and to insure the performance of his agreement, had bond himself to the plaintiff, in the sum of 5,000 pounds, "as and by way of liquidated damages, and not of penalty." Kemble v. Farren was cited for the defendant, but the Court said, "where the deed contains several stipulations of various degrees of importance, as to some of which, the damages might be considered liquidated, whilst for others, they may be deemed unliquidated, and a sum of money is made payable on a breach of any of them, the Courts have held it to be a penalty and not liquidated damages. But when the damages is altogether uncertain, and yet a definite sum of money is expressly made payable in respect of it, by way of liquidated damages, those words must be read in the ordinary sense, and cannot be construed to import a penalty." This cause was affirmed on a writ of error to the Exchequer chamber, when TINDAL, C. J., who had decided Kemble v. Farren was present. See Price v. Green, 16 Mees. and Wels. Rep. 346.
The principle of the rule has been recognized in the Supreme Court of the United States, and in the Courts of many of the States. See Tayloe v. Sandiford 7, Wheat. 13; Dakin v. Williams 17, Wend. Rep. 447; S.C. in Error 22, Wend. 201, and the cases in other States in a note to 419 page of Sedgewick on Damages, (2nd Ed.)
Let us now apply the rule, which we have thus deduced from the cases, to the one before us. The defendant in consideration of his purchase from the plaintiff of one half of the schooner, John F. Davenport, covenanted to do three things: 1st, to pay one half of the debt due by the plaintiff, to Doyle, Durvin Rudder, such half amounting to $675: 2ndly, to pay off a note due from plaintiff to Casey Davis for $720: and 3rdly, to permit the plaintiff to redeem the half of the vessel, by repaying these sums with interest, at any time within three years from the sale: and if he failed to comply with these terms, he agreed to pay the plaintiff $2,500 as liquidated damages. It is manifest that if the defendant had failed to pay both, or either of the sums which he agreed to do, he would have broken the covenant as effectually, as he did by failing to reconvey. If the sum agreed on by the parties, is to be construed liquidated damages, as the terms import, then the defendant will be bound to pay a greater sum for a less; which cannot be, as that, according to all the cases, is a penalty. The sum, too, agreed to be paid by the way of damages, is for the breach of any of the stipulations which are of different degrees of importance and value, and so comes directly within the rule laid down in the cases to which we have referred. Nor is the damage for the breach assigned, to wit, the non-reconveyance of a half of the schooner in question, so entirely uncertain as to bring the case within the rule of stipulated damages. We have not learnt that the half of the schooner was of such peculiar value to the plaintiff, as to make altogether uncertain his damage for the defendant's failure to reconvey it to him. The charge of his Honor in relation to the damage was right, and the judgment must be affirmed.
PER CURIAM. Judgment affirmed.