From Casetext: Smarter Legal Research

Providence Washington Insurance v. Beck

Supreme Judicial Court of Massachusetts
Jan 30, 1970
255 N.E.2d 600 (Mass. 1970)

Summary

holding that contractor's failure to comply with seven-day notice provision before termination was substantial breach

Summary of this case from Enterprise Capital, Inc. v. San-Gra Corp.

Opinion

January 30, 1970.

Joseph M. Cohen for I. Fred DiCenso.

Lyman C. Sprague George A. Goldstein, for J. Howard Beck, submitted a brief.


This is a bill for a declaratory decree by a bonding company against I. Fred DiCenso and J. Howard Beck, to determine the duties and liabilities of the parties under DiCenso's agreement to construct a building for Beck and under a surety bond covering the construction agreement. Each of the defendants filed a counterclaim. The case was referred to a master. The trial judge entered an interlocutory decree confirming the master's report. A final decree was entered from which DiCenso appeals. The construction agreement contained a provision that in the event of a breach by the owner, the agreement could be terminated by the contractor giving the owner seven days written notice of the contractor's intention to terminate the agreement. On October 20, 1958, DiCenso notified Beck that Beck was in breach of the agreement and "that he considers himself to be free of any further obligation to continue with or complete the construction of the . . . building." DiCenso contends that Beck's failure to comply with the schedule of payments was a "substantial breach of contract [and therefore] he is not entitled to damages." The record, however, discloses that except for the breach of the payment on October 17, 1958, each time Beck was delinquent in making progress payments DiCenso not only accepted the payments, but continued to perform the construction agreement. Therefore, although Beck had not made the payments on schedule prior to October 17, DiCenso's actions constituted a waiver of those breaches. See Carrig v. Gilbert-Varker Corp. 314 Mass. 351, 355; Wenzel Henoch Constr. Co. v. Metropolitan Water Dist. 115 F.2d 25 (9th Cir.); United States v. Americo Constr. Co. Inc. 168 F. Supp. 760 (D. Mass.); Corbin, Contracts, revised, § 756. DiCenso also argues that if his failure to give seven days notice of termination (as required by the agreement) on October 20, 1958, is a breach, "it is not prejudicial because . . . Beck did nothing to cure his own breaches during the seven days." We believe this argument to be untenable. DiCenso, by failing to comply with the requirement of giving seven days notice of termination, committed a substantial breach of the contract and thus there was no further obligation on Beck to tender payment. Finally, we discern no basis for DiCenso's contention that the amount of damages assessed by the master "bears no relationship" to DiCenso's breach of the termination provision. The master awarded Beck an amount equal to the difference between the contract price and the total cost of completing the building. Ficara v. Belleau, 331 Mass. 80. There was no error.

Decree affirmed.


Summaries of

Providence Washington Insurance v. Beck

Supreme Judicial Court of Massachusetts
Jan 30, 1970
255 N.E.2d 600 (Mass. 1970)

holding that contractor's failure to comply with seven-day notice provision before termination was substantial breach

Summary of this case from Enterprise Capital, Inc. v. San-Gra Corp.

holding contractor's failure to comply with seven-day notice provision under contract before termination was substantial breach

Summary of this case from Joseph Schott, LLC v. Medrea

holding contractor's failure to comply with seven-day notice provision under contract before termination was substantial breach

Summary of this case from Bouchard v. Boyer
Case details for

Providence Washington Insurance v. Beck

Case Details

Full title:THE PROVIDENCE WASHINGTON INSURANCE COMPANY vs. J. HOWARD BECK another

Court:Supreme Judicial Court of Massachusetts

Date published: Jan 30, 1970

Citations

255 N.E.2d 600 (Mass. 1970)
255 N.E.2d 600

Citing Cases

Stokes v. Clark

Under appropriate circumstances, a case could easily arise wherein a stop-payment order on a buyer's deposit…

Midland Hot. v. Pref. Mot. Inns

Even assuming that Preferred's purported August 17 termination was a material breach of the Agreement, there…