In the Matter of Shamima N. SUMI, appellant, v. VILLAGE OF STEWART MANOR, respondent.

Sacco & Fillas, LLP, Astoria, NY (Albert R. Matuza, Jr., of counsel), for appellant. Keith J. Conway, Melville, NY (Shannon Davis of counsel), for respondent.


Sacco & Fillas, LLP, Astoria, NY (Albert R. Matuza, Jr., of counsel), for appellant.

Keith J. Conway, Melville, NY (Shannon Davis of counsel), for respondent.

ANGELA G. IANNACCI, J.P., CHERYL E. CHAMBERS, DEBORAH A. DOWLING, HELEN VOUTSINAS, JJ.

DECISION & ORDER In a proceeding pursuant to General Municipal Law § 50–e(5) for leave to serve a late notice of claim or to deem a late notice of claim timely served nunc pro tunc, the petitioner appeals from an order of the Supreme Court, Nassau County (Denise L. Sher, J.), dated April 28, 2022. The order denied the petition and dismissed the proceeding. ORDERED that the order is affirmed, with costs.

Pursuant to General Municipal Law § 50–e(1)(a), a party seeking to sue a public corporation must serve a notice of claim on the prospective defendant within 90 days after the claim arises (see Matter of Newcomb v. Middle Country Cent. Sch. Dist., 28 N.Y.3d 455, 460, 45 N.Y.S.3d 895, 68 N.E.3d 714 ). "In determining whether to grant a petition for leave to serve a late notice of claim or to deem a late notice of claim timely served nunc pro tunc, the court must consider all relevant circumstances, including whether (1) the public corporation acquired actual knowledge of the essential facts constituting the claim within 90 days after the claim arose or a reasonable time thereafter, (2) the claimant demonstrated a reasonable excuse for the failure to serve a timely notice of claim, and (3) the delay would substantially prejudice the public corporation in its defense on the merits" ( Matter of Brown v. City of New York, 202 A.D.3d 783, 783, 158 N.Y.S.3d 864 [internal quotation marks omitted]; see General Municipal Law § 50–e[5] ; Matter of Reddick v. New York City Hous. Auth., 188 A.D.3d 890, 890, 132 N.Y.S.3d 317 ). The presence or absence of any factor is not determinative (see Matter of Newcomb v. Middle Country Cent. Sch. Dist., 28 N.Y.3d at 460, 45 N.Y.S.3d 895, 68 N.E.3d 714 ; Etienne v. City of New York, 189 A.D.3d 1400, 1402, 134 N.Y.S.3d 738 ).

Here, the Supreme Court providently exercised its discretion in denying the petition pursuant to General Municipal Law § 50–e(5) for leave to serve a late notice of claim or to deem a late notice of claim timely served nunc pro tunc and in dismissing the proceeding. The petitioner failed to demonstrate a reasonable excuse for service of the late notice of claim, which was a nullity, as it was made without leave of court (see Matter of Thomas v. New York City Hous. Auth., 200 A.D.3d 1051, 155 N.Y.S.3d 807 ), or for the more than three-month delay in commencing this proceeding after the expiration of the 90–day statutory period. Moreover, the petitioner's ignorance of the law and claim of law office failure by her attorney did not constitute a reasonable excuse for the failure to serve a timely notice of claim and the delay in commencing this proceeding (see Matter of Lugo v. GNP Brokerage, 185 A.D.3d 824, 826, 127 N.Y.S.3d 527 ; Matter of Nunez v. Village of Rockville Ctr., 176 A.D.3d 1211, 1214, 111 N.Y.S.3d 71 ; Matter of Naar v. City of New York, 161 A.D.3d 1081, 1083, 77 N.Y.S.3d 706 ).

Contrary to the petitioner's contention, the respondent did not acquire timely, actual knowledge of the essential facts constituting the petitioner's claim (see Matter of Rios v. County of Nassau, 212 A.D.3d 631, 181 N.Y.S.3d 608 ; Matter of Robinson v. City of New York, 208 A.D.3d 587, 588, 173 N.Y.S.3d 307 ). The petitioner's contention that the respondent acquired actual knowledge of the claim based on, inter alia, general and conclusory allegations that the respondent was aware of the identity and job duties of the employees who caused and created the alleged defective condition and were responsible for performing inspections and repairs at the accident location is without merit.

Finally, the petitioner failed to meet her burden of presenting some evidence or plausible argument that supports a finding that the delay would not substantially prejudice the respondent in maintaining its defense on the merits (see Matter of Newcomb v. Middle Country Cent. Sch. Dist., 28 N.Y.3d at 466, 45 N.Y.S.3d 895, 68 N.E.3d 714 ; Matter of Robinson v. City of New York, 208 A.D.3d at 588–589, 173 N.Y.S.3d 307 ; cf. Matter of McGrue v. City of New York, 195 A.D.3d 932, 146 N.Y.S.3d 507 ; Matter of McVea v. County of Orange, 186 A.D.3d 1221, 1223, 130 N.Y.S.3d 63 ).

IANNACCI, J.P., CHAMBERS, DOWLING and VOUTSINAS, JJ., concur.


Summaries of

Sumi v. Vill. of Stewart Manor

Supreme Court of New York, Second Department
Aug 2, 2023
219 A.D.3d 490 (N.Y. App. Div. 2023)
Case details for

Sumi v. Vill. of Stewart Manor

Case Details

Full title:In the Matter of Shamima N. Sumi, appellant, v. Village of Stewart Manor…

Court:Supreme Court of New York, Second Department

Date published: Aug 2, 2023

Citations

219 A.D.3d 490 (N.Y. App. Div. 2023)
194 N.Y.S.3d 120
2023 N.Y. Slip Op. 4127

Citing Cases

Jeudy v. City of New York

"In determining whether to grant leave to serve a late notice of claim, the court must consider all relevant…

F.Z. v. City of New York

Here, the petitioner failed to establish that the City had acquired actual knowledge of the essential facts…