From Casetext: Smarter Legal Research

Strabag, Spa v. Credit Agricole Cib

Supreme Court of New York, First Department
Nov 9, 2023
221 A.D.3d 437 (N.Y. App. Div. 2023)

Opinion

978-, M–4325 Index No. 650865/23 Case No. 2023–02383

11-09-2023

STRABAG, SPA, Plaintiff–Respondent, v. CREDIT AGRICOLE CIB, Defendant, Alto Maipo SPA, Defendant–Appellant. Professor Boris Kozolchyk, Amicus Curiae.

Linklaters LLP, New York (Adam S. Lurie, Michael Pilcher and Rebecca Zeldin of counsel), for appellant. Troutman Pepper Hamilton Sanders LLP, New York (Stephen G. Rinehart of counsel), for respondent. Weaver Mancuso Brightman PLLC, Rochester (John A. Mancuso of counsel), for amicus curiae.


Linklaters LLP, New York (Adam S. Lurie, Michael Pilcher and Rebecca Zeldin of counsel), for appellant.

Troutman Pepper Hamilton Sanders LLP, New York (Stephen G. Rinehart of counsel), for respondent.

Weaver Mancuso Brightman PLLC, Rochester (John A. Mancuso of counsel), for amicus curiae.

Webber, J.P., Friedman, Gonza´lez, Kennedy, O'Neill Levy, JJ.

Order, Supreme Court, New York County (Andrea Masley, J.), entered April 4, 2023, which, in this proceeding to enjoin defendant from drawing down on a letter of credit, granted plaintiff's motion for a preliminary injunction enjoining defendant Alto Maipo SPA from drawing down on the letter of credit, unanimously reversed, on the law, with costs, the motion denied and the injunction vacated.

Defendant Alto Maipo SPA is the owner of a hydroelectric powerplant project near Santiago, Chile. Plaintiff is a contractor for substantial work, including of tunnels that are to supply water from the upper basin of the Maipo River to the powerplant. Through a series of agreements, the parties negotiated a performance schedule that included completion dates for certain "Critical Milestones" of performance on the project. In the event these milestones are not met, the agreements allow defendant to draw down on a standby letter of credit issued by defendant Credit Agricole CIB in the amount of contractually set liquidated damages.

One pre-condition to completion of certain of the milestones was testing of the water flow through the tunnels. These tests required that the water flow in the tunnels be at their maximum. However, the parties realized that because most of the water that would flow through the tunnels was frozen in surrounding mountains, testing could not be complete until the spring and summer thawed sufficient ice to bring the water levels to that needed for testing. As such, they agreed to extend the completion date to the extent that testing was delayed by insufficient water.

Initially, we find that the court was correct that the prior ruling of an ICC emergency arbitrator who expressly did not reach the issue of material fraud was not a bar to consideration of the instant motion ( Zimmerman v. Tower Ins. Co. of New York, 13 A.D.3d 137, 139, 788 N.Y.S.2d 309 [1st Dept. 2004] [no collateral estoppel effect unless prior order necessarily decided identical issue]).

Ordinarily, under the doctrine of independent contracts, a party's conduct with regard to the underlying transaction will not be a basis for barring a draw on a clean, standby letter of credit ( BasicNet S.p.A. v. CFP Servs. Ltd., 127 A.D.3d 157, 167–168, 4 N.Y.S.3d 27 [1st Dept. 2015] ). However, there is a narrow exception where the draw would be in furtherance of a fraud (see UCC 5–109 ). Where the fraud is related to the alleged grounds for drawing on the letter, the "material fraud" exception will bar the draw, provided the beneficiary has "no colorable" basis under the agreements for the drawdown ( 3M Co. v. HSBC Bank USA, N.A., 2018 WL 1989563, *9, 2018 U.S. Dist. LEXIS 69666, *24 [S.D.N.Y., Apr. 25, 2018, No. 16 CIV 5984(PGG) [internal quotation marks omitted]).

In this matter, defendant has a colorable argument that the provision of the agreements setting forth the extension based on water levels does not apply "day for day" to the delays. Rather, the text of the section and the other sections of the agreements give rise to a reasonable interpretation that the extension only applies to the extent that the low water levels push the completion of testing past the cut-off date for completion of the Critical Milestones. Moreover, there is no dispute that the tunnel collapse prevented water testing and supports defendant invoking its rights pursuant to the drawdown provision of the parties’ agreement. As such, the court abused its discretion in finding that plaintiff had a likelihood of success to establish the material fraud exception here.

Motion to file amicus brief, granted.


Summaries of

Strabag, Spa v. Credit Agricole Cib

Supreme Court of New York, First Department
Nov 9, 2023
221 A.D.3d 437 (N.Y. App. Div. 2023)
Case details for

Strabag, Spa v. Credit Agricole Cib

Case Details

Full title:Strabag, Spa, Plaintiff-Respondent, v. Credit Agricole Cib, Defendant…

Court:Supreme Court of New York, First Department

Date published: Nov 9, 2023

Citations

221 A.D.3d 437 (N.Y. App. Div. 2023)
199 N.Y.S.3d 465
2023 N.Y. Slip Op. 5671