From Casetext: Smarter Legal Research

Stennett v. Moveway Transfer & Storage, Inc.

Supreme Court, Appellate Division, Second Department, New York.
Jul 11, 2012
97 A.D.3d 655 (N.Y. App. Div. 2012)

Summary

finding that the plaintiff's claim for failure to pay overtime wages “is premised upon the minimum wage directives set forth in 12 NYCRR 142–2.2, which were promulgated by the New York State Commissioner of Labor pursuant to authority vested in the Commissioner” (citing Ballard v. Community Home Care Referral Serv., 264 A.D.2d 747, 695 N.Y.S.2d 130 (1999) )

Summary of this case from Rocha v. Bakhter Afghan Halal Kababs, Inc.

Opinion

2012-07-11

Christopher STENNETT, appellant, v. MOVEWAY TRANSFER & STORAGE, INC., respondent.

David Abrams, New York, N.Y., for appellant. T. Kevin Murtha & Associates, P.C., Westbury, N.Y. (William Bird III of counsel), for respondent.



David Abrams, New York, N.Y., for appellant. T. Kevin Murtha & Associates, P.C., Westbury, N.Y. (William Bird III of counsel), for respondent.
DANIEL D. ANGIOLILLO, J.P., ANITA R. FLORIO, ARIEL E. BELEN, and CHERYL E. CHAMBERS, JJ.

In an action, inter alia, to recover damages for breach of contract and for violation of Labor Law § 231, the plaintiff appeals from an order of the Supreme Court, Queens County (Rosengarten, J.), dated July 19, 2011, which, upon treating the defendant's motion to dismiss the complaint pursuant to CPLR 3211(a) as a motion to dismiss the amended complaint, in effect, granted those branches of the defendant's motion which were pursuant to CPLR 3211(a)(7) to dismiss the amended complaint.

ORDERED that the order is modified, on the law, by deleting the provisions thereof, in effect, granting those branches of the defendant's motion which were pursuant to CPLR 3211(a)(7) to dismiss the common-law cause of action in the amended complaint, which alleged that the defendant breached certain contract provisions requiring it to pay the prevailing wage, and the cause of action in the amended complaint alleging a violation of the New York State Minimum Wage Act (Labor Law art. 19), and applicable regulations, for failure to pay overtime wages, and substituting therefor a provision denying those branches of the motion; as so modified, the order is affirmed, with costs to the plaintiff.

In determining a motion to dismiss a pleading pursuant to CPLR 3211(a)(7), the pleading must be afforded a liberal construction, and the court must “accept the facts as alleged in the complaint as true, accord plaintiffs the benefit of every possible favorable inference, and determine only whether the facts as alleged fit within any cognizable legal theory” ( Leon v. Martinez, 84 N.Y.2d 83, 87–88, 614 N.Y.S.2d 972, 638 N.E.2d 511;see First Keystone Consultants, Inc. v. DDR Constr. Servs., 74 A.D.3d 1135, 1136, 904 N.Y.S.2d 113). The first cause of action in the amended complaint includes both statutory and common-law causes of action. Here, accepting the facts alleged in the amended complaint as true, and according the plaintiff the benefit of every favorable inference, the Supreme Court properly granted that branch of the defendant's motion which was to dismiss, for failure to state a cause of action, the statutory cause of action alleging that the defendant failed to pay the plaintiff the prevailing wage in violation of Labor Law § 231, which requires every contractor that employs building service workers under a contract with a public agency to pay the prevailing wage to all service employees who are subject to or covered by such a contract. The Labor Law contains an administrative enforcement mechanism for violations of section 231 ( seeLabor Law § 235) and the plaintiff has no private right of action to recover damages for the underpayment of wages in violation of that section until a final administrative determination has been made ( seeLabor Law § 235[6]; cf. Winsch v. Esposito Bldg. Specialty, Inc., 48 A.D.3d 558, 852 N.Y.S.2d 199;Marren v. Ludlam, 14 A.D.3d 667, 790 N.Y.S.2d 146;Pesantez v. Boyle Envtl. Servs., 251 A.D.2d 11, 673 N.Y.S.2d 659). Since the amended complaint contains no allegation that such an administrative determination was sought or made, the Supreme Court correctly granted that branch of the defendant's motion which was, in effect, pursuant to CPLR 3211(a)(7) to dismiss the statutory cause of action.

However, the Supreme Court erred in granting that branch of the defendant's motion which was pursuant to CPLR 3211(a)(7) to dismiss the common-law cause of action alleging breach of contract. In situations where the Labor Law requires the inclusion of a provision for payment of the prevailing wage in a labor contract between a public agency and a contractor, a contractual obligation is created in favor of the contractor's employees, and an employee covered by or subject to the contract, in his or her status as third-party beneficiary to the contract, possesses a common-law cause of action against the contractor to recover damages for breach of such a contractual obligation ( see Cox v. NAP Constr. Co., Inc., 10 N.Y.3d 592, 861 N.Y.S.2d 238, 891 N.E.2d 271;Wright v. Wright Stucco, 50 N.Y.2d 837, 430 N.Y.S.2d 52, 407 N.E.2d 1348;Maldonado v. Olympia Mech. Piping & Heating Corp., 8 A.D.3d 348, 777 N.Y.S.2d 730;Melissakis v. Proto Constr. & Dev. Corp., 294 A.D.2d 342, 741 N.Y.S.2d 731). Here, the plaintiff alleged that the defendant failed to pay him the prevailing wage in breach of five municipal contracts, each of which was specifically described by identification number and government agency, and all of which included prevailing wage provisions pursuant to Labor Law § 231. Contrary to the defendant's contention, the allegations were sufficiently specific to allege common-law breach of contract ( see Wright v. Wright Stucco, 50 N.Y.2d at 839, 430 N.Y.S.2d 52, 407 N.E.2d 1348;Melissakis v. Proto Constr. & Dev. Corp., 294 A.D.2d at 342, 741 N.Y.S.2d 731;cf. Maldonado v. Olympia Mech. Piping & Heating Corp., 8 A.D.3d at 348, 777 N.Y.S.2d 730). Thus, the Supreme Court should have denied that branch of the defendant's motion which was pursuant to CPLR 3211(a)(7) to dismiss the common-law breach of contract cause of action.

Further, the Supreme Court erred in granting that branch of the defendant's motion which was pursuant to CPLR 3211(a)(7) to dismiss the second cause of action, which alleged that the defendant failed to pay overtime wages in violation of the Minimum Wage Act (Labor Law art. 19), and applicable regulations. Contrary to the defendant's contention, such a cause of action is not dependent upon the viability of a statutory cause of action pursuant to Labor Law § 231, which is codified in article 9 of the Labor Law, and a Labor Law article 19 cause of action does not fail as a consequence of the dismissal of a Labor Law § 231 cause of action. Rather, the second cause of action in the amended complaint is premised upon the minimum wage directives set forth in 12 NYCRR 142–2.2, which were promulgated by the New York State Commissioner of Labor pursuant to authority vested in the Commissioner by Labor Law article 19 ( see Ballard v. Community Home Care Referral Serv., 264 A.D.2d 747, 747–748, 695 N.Y.S.2d 130). An employee may commence a civil action to recover wages to which he or she is entitled under article 19 of the Labor Law, and, unlike a Labor Law § 231 cause of action, there is no requirement that an employee exhaust his or her administrative remedies prior to commencement of an action alleging a violation of Labor Law article 19 ( seeLabor Law §§ 663[1], [3] ). Accordingly, the Supreme Court should have denied that branch of the defendant's motion which was pursuant to CPLR 3211(a)(7) to dismiss the second cause of action in the amended complaint.


Summaries of

Stennett v. Moveway Transfer & Storage, Inc.

Supreme Court, Appellate Division, Second Department, New York.
Jul 11, 2012
97 A.D.3d 655 (N.Y. App. Div. 2012)

finding that the plaintiff's claim for failure to pay overtime wages “is premised upon the minimum wage directives set forth in 12 NYCRR 142–2.2, which were promulgated by the New York State Commissioner of Labor pursuant to authority vested in the Commissioner” (citing Ballard v. Community Home Care Referral Serv., 264 A.D.2d 747, 695 N.Y.S.2d 130 (1999) )

Summary of this case from Rocha v. Bakhter Afghan Halal Kababs, Inc.

regarding contracts for building services employees, also subject to a prevailing wage requirement under NYLL § 231

Summary of this case from Velasquez v. Vikrant Contracting & Builders, Inc.
Case details for

Stennett v. Moveway Transfer & Storage, Inc.

Case Details

Full title:Christopher STENNETT, appellant, v. MOVEWAY TRANSFER & STORAGE, INC.…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Jul 11, 2012

Citations

97 A.D.3d 655 (N.Y. App. Div. 2012)
949 N.Y.S.2d 91
2012 N.Y. Slip Op. 5510

Citing Cases

Singh v. Zoria Hous., LLC

Here, the plaintiff stated viable breach of contact causes of action based on violations of statutorily…

Renaud v. Bedford- Carp Constr.

e is not a fact at all and unless it can be said that no significant dispute exists regarding it, dismissal…