From Casetext: Smarter Legal Research

State, ex Rel. Dinneen Excavating Co., v. Sykes

Supreme Court of Ohio
Dec 14, 1988
40 Ohio St. 3d 84 (Ohio 1988)

Opinion

No. 87-344

Submitted April 12, 1988 —

Decided December 14, 1988.

Public works contracts — Funds due subcontractors placed in escrow pursuant to R.C. 1311.28 — Funds released to parties on pro-rata basis pursuant to R.C. 1311.31, when.

O.Jur 3d Mechanic's Liens §§ 240, 243.

When funds due subcontractors have been placed in escrow pursuant to R.C. 1311.28, a court of competent jurisdiction must order the release of the escrow funds to specific parties, in specific pro-rata amounts, and at specific times, as properly determined by that court unless the parties agree to the amount owed. Where the parties agree to the amounts owed, the owner must distribute the funds on a pro-rata basis according to R.C. 1311.31.

APPEAL from the Court of Appeals for Franklin County, No. 84AP-885.

This action was commenced by Dinneen Excavating Company, Inc. ("Dinneen") which sought a writ of mandamus ordering appellant, William G. Sykes, Director of Administrative Services ("director") to pay Dinneen the amount due it pursuant to a lien perfected against appellant. The lien amount represented labor and materials supplied to Bildoc, Inc., as the general contractor of a state public works contract involving construction at the Chillicothe Correctional Institution.

Appellant moved to have other necessary parties joined. These parties also had claims or liens against funds held by appellant; a total of nineteen other lienholders were so joined.

It is undisputed that the funds held by appellant, stipulated to be $368,208.38 plus interest earned in escrow, were insufficient to pay the full amount of all the claims.

The director took the position that he could not pay any claim in any amount without a court order directing to whom payments were to be made and specifying the amounts. Dinneen and the other lienholders, including relators-appellees, Gemma, Inc. and Price Brothers Co., urged that appellant was required, pursuant to R.C. 1311.31, to distribute all funds to bona fide lienholders on a pro-rata basis.

The following appellees joined with the briefs submitted on behalf of appellee Price Brothers Co., but did not otherwise file briefs on their own: A.J. Stockmeister, Inc.; Basic Construction Materials; Geotechnical Consultants, Inc.; Reolite, Division of H.H. Robertson Co.; Water Pollution Control Corp.; and Varec Division, Emerson Electric Co.

The court of appeals first determined that mandamus was available only where there was a clear legal right to it and there were no disputes between proper parties to be resolved.

The court further determined that, pursuant to R.C. 1311.31, appellant was under a clear legal duty to distribute the escrow funds, on a pro-rata basis, to all claim holders whose claims and priorities were not disputed and to withhold that portion of the funds representing claims that were disputed. A writ of mandamus was issued to that effect.

The cause is now before this court on an appeal as of right.

Cavitch, Familo Durkin and Ralph E. Cascarilla, for appellee Gemma, Inc.

Murphey, Young Smith and Glenn W. Myers, for appellee Price Brothers Co.

Anthony J. Celebrezze, Jr., attorney general, Diane Goss Paynter and Richard A. Green, for appellant.


The pertinent law is set forth in R.C. 1311.26 through 1311.32.

R.C. 1311.26 provides that any subcontractor who has performed labor or furnished material for the construction of any public building provided for in a contract may file with the owner or agent thereof (here, the director) a sworn and itemized statement of the amount and value of labor and materials furnished, stating when the last of each was furnished.

R.C. 1311.28 provides that:

"Upon receiving the notice required by section 1311.26 of the Revised Code, such owner, board, officer, public authority, or authorized clerk, agent, or attorney thereof, shall detain from the principal contractor all subsequent payments as do not in the aggregate exceed such claim or claims.

" An owner referred to in section 153.01 of the Revised Code shall place such detained funds in an escrow account as provided for under section 153.63 of the Revised Code, to be released at such times, in such amounts, and to such persons as may be ordered by a court of competent jurisdiction or by agreement of the principal contractor and the subcontractor, material-man, laborer, or mechanic who filed the notice provided for in section 1311.26 of the Revised Code." (Emphasis added.)

R.C. 1311.29 defines the priorities awarded when there are several claimants, such as in this case. Any claimant filing a statement pursuant to R.C. 1311.26 must notify other potential claimants by filing, within ten days of filing the R.C. 1311.26 statement, a copy of the statement with the county recorder of the county where such property is situated. The filing for record of such notice gives the subcontractor preference, as to payments subsequently due from the owner, over other subcontractors or claimants who have failed to file an R.C. 1311.26 statement prior to the date any payment is due. All claimants who have filed statements have no priority among themselves; payment is to be made on a pro-rata basis.

The amounts are prorated according to the amount of the then-existing valid claim of each claimant. Also, failure of a claimant to file for record a copy of his statement with the county recorder does not affect the validity of the lien. After those lienholders with a preference (priority) have been paid, other claimants are also paid on a pro-rata basis.

R.C. 1311.31 provides:

"The owner, board, officer, or clerk, agent, or attorney thereof, upon the receipt of the statement referred to in section 1311.26 of the Revised Code shall, or the lien claimant, his agent, or attorney, in the name of such owner, board, or officer, may furnish the principal contractor with a copy thereof, within five days after receiving it, together with the notice that such principal contractor must give notice of his intention to dispute such claim within ten days. If such lien claimant performed such labor for, or furnished such material, fuel, or machinery to, a subcontractor or such principal contractor, such lien claimant shall, within ten days after the filing of such statement, furnish a copy thereof to such contractor. If such principal contractor fails within ten days after such receipt by him to notify, in writing, such owner, board, officer, or clerk, agent, or attorney thereof of his intention to dispute such claim, he has assented to its correctness, provided that within ten days after receipt by any subcontractor of a copy of such statement, such subcontractor may give such notice of such intention to dispute on behalf of such principal contractor. Thereupon, provided all statements filed on the same improvement have been assented to, the amount detained from the principal contractor shall be applied by and payment made by such owner, his agent, or attorney, in the order of preference prescribed in section 1311.29 of the Revised Code, pro rata, upon such claims on which statements have been filed. Where more than one statement has been filed with respect to the same improvement, and one or more of such statements has not been assented to, then the amount detained shall be applied pro rata among all such lien claimants in the order of preference prescribed in section 1311.29 of the Revised Code, payment being made in the amount of their pro rata shares to all lien claimants whose statements have been assented to, and the pro rata shares of lien claimants whose statements have not been assented to shall be detained by the owner until the dispute with respect to any such statement has been resolved in any manner provided by law, whereupon payment in whole or in part shall be made to such lien claimants in whose favor such dispute is resolved and any remaining part of said pro rata shares shall be applied pro rata among and payment made to all lien claimants as provided in this section. Each subsequent payment falling due shall be applied among and payment made to the lien claimants as provided in this section." (Emphasis added.)

Finally, R.C. 1311.32 provides that the duty to pay lien claimants the amounts and in order of preference provided may be enforced by an action in mandamus or the subcontractor may, when such amounts are due, recover against the owner the whole claim or pro-rata share of the amount.

Appellant contends that, pursuant to R.C. 1311.28, the court of appeals should have ordered him to pay specific amounts to specific parties as the court determined to be proper. Appellant further urges that R.C. 1311.28 conflicts with R.C. 1311.31 and that the procedures set forth in R.C. 1311.28 supersede the procedures in R.C. 1311.31, citing Lee Turzillo Contracting Co. v. Cincinnati Metro. Housing Auth. (1967), 10 Ohio St.2d 5, 39 O.O. 2d 3, 225 N.E.2d 255.

R.C. 1311.28 does not clearly conflict with R.C. 1311.31. R.C. 1311.28 provides that whenever an owner receives notice of claims statements having been filed, he must detain the funds in an escrow account. Escrow funds are released at such times, and in such amounts, and to such persons as may be ordered by a court of competent jurisdiction, or by agreement of the principal contractor and the subcontractor(s).

R.C. 1311.31 provides that if the principal contractor fails to notify the owner of intent to dispute such claim, the correctness of the claim is assented to. Thereafter, if all statements (claims) are assented to, the owner applies the funds held in escrow to all claimholders on a pro-rata basis.

The court of appeals, acting pursuant to R.C. 1311.31, held that because the principal contractor assented to all the claims, the owner (the director) was under a clear legal duty to apply the funds on a pro-rata basis to each of the claimholders whose claims were not disputed.

Appellant contends that R.C. 1311.28 controls and he can not release or apply any of the escrow funds without a court order, relying on Lee Turzillo Contracting Co., supra.

In Turzillo, supra, this court held, in paragraph three of the syllabus, that even though a principal contractor assents to the correctness of a claim, he does not assent to payment of the claim without satisfactory proof of performance.

Further, in paragraph five of the syllabus, the Turzillo decision held that where a principal contractor assents to the claim, a claimholder acquires no right to have escrow funds applied to his claim until the principal contractor has the opportunity to assert any defense he may have against the claimholder, except as to the correctness of the amount and value of the claim.

Turzillo, a 1967 decision, involved the language contained in both R.C. 1311.28 and 1311.31 prior to amendments effective in 1963 (130 Ohio Laws 349, 350-351).

The prior language of R.C. 1311.31 (97 Ohio Laws 502) did contain the basic provision that when a principal contractor assented to the correctness of a claim, the owner was required to pay it, when due, on a pro-rata basis. The prior language of R.C. 1311.28 (97 Ohio Laws 501) required the owner to detain subsequent payments "in his hands" to secure the claims of subcontractors. There was no provision for placing funds in escrow or receiving any orders from any court.

The Turzillo court held that merely filing a statement, the correctness of which the principal contractor assented to, did not automatically entitle a subcontractor to receive the funds claimed on a pro-rata basis. The court held that a claim could not be paid until due. The language "when due" was deleted in the 1963 amendment. The Turzillo court further held that it had to be shown that the work was actually and satisfactorily performed.

In 1963, the General Assembly amended R.C. 1311.32 (formerly G.C. 8331) (130 Ohio Laws 352) to provide that the duty to pay lien claimants the amounts and in order of preference as provided "may be enforced by action of mandamus." However, in the alternative, a subcontractor could recover against the owner the whole or pro-rata share of his claim when due. Accordingly, R.C. 1311.32 provides a remedy by way of either a mandamus action or a legal action.

In 1975, the General Assembly amended R.C. 1311.28 (136 Ohio Laws, Part I, 641) and provided that an owner shall place in escrow those funds detained pursuant to R.C. 1311.26 "to be released at such times, in such amounts, and to such persons as may be ordered by a court of competent jurisdiction or by agreement of the principal contractor and the subcontractor * * * who filed the notice * * *." (Emphasis added.) Reading R.C. 1311.28 in pari materia with R.C. 1311.31, it is not difficult to resolve the conflict. If the principal contractor has "assented" to the correctness of the claim (R.C. 1311.31), the principal contractor and his subcontractor have reached "agreement" (R.C. 1311.28) and the funds can be released from escrow. Equating "assent" of the correctness of the claim with "agreement" on the amounts to be paid to a subcontractor at particular times does not conflict with R.C. 1.42, which provides that words and phrases shall be read in context and construed according to common usage.

Clearly, amendments to the same statute are to be harmonized if possible to give effect to each. R.C. 1.52. If amendments are substantively irreconcilable, the latest in date of enactment prevails. Id. Amendments are irreconcilable only when changes made by each cannot reasonably be put into simultaneous operation. Id. By analogy to this provision it is possible to harmonize R.C. 1311.28 and 1311.31.

In these cases, the General Assembly has provided a means of payment of escrow funds. If the principal contractor assents to the subcontractor's claim, then the owner pays the subcontractor a pro-rata share of the escrow funds. If, however, the principal contractor disputes the amount owed, then the parties may ask a court of competent jurisdiction to resolve the dispute.

Turzillo does not require a different result. That case merely stands for the proposition that even where the principal contractor assents to the correctness of the claimed amount, certain contractual obligations must still be satisfied. Turzillo did not hold that escrow funds can never be released by the owner without court approval.

Therefore, we hold that, when funds due subcontractors have been placed in escrow pursuant to R.C. 1311.28, a court of competent jurisdiction must order the release of the escrow funds to specific parties, in specific pro-rata amounts, and at specific times, as properly determined by that court unless the parties agree to the amount owed. Where the parties agree to the amount owed, the owner must distribute the funds on a pro-rata basis according to R.C. 1311.31.

Here, the principal contractor assented only to the correctness of some of the claims and the owner requested that the court of appeals determine which parties were owed the detained funds. Unless the owner disputes the correctness of the amounts, he must distribute such funds to the subcontractors. The court of appeals did not err by ordering appellant to release the funds to those subcontractors whose claims it did not dispute.

There is disagreement as to how many claimholders filed a statement and a notice pursuant to statute. Appellant states that sixteen claimholders should receive payments of the escrow funds; appellee Price Brothers. Co. identifies eleven claimholders; and the referee for the court of appeals identifies fifteen claimholders. Appellee Gemma, Inc. states that it is owed $116,169.30 and that this is undisputed; however, Price Brothers. Co. states that Gemma's claim is for $118,451.80.

Accordingly, the decision of the court of appeals is affirmed. The owner must disburse the funds on a pro-rata basis to claimants whose claims are not disputed. Thereafter, the disbursement of the remaining funds should be determined by a court of competent jurisdiction in accordance with this decision.

Judgment affirmed.

MOYER, C.J., SWEENEY, LOCHER, DOUGLAS, WRIGHT and H. BROWN, JJ., concur.


Summaries of

State, ex Rel. Dinneen Excavating Co., v. Sykes

Supreme Court of Ohio
Dec 14, 1988
40 Ohio St. 3d 84 (Ohio 1988)
Case details for

State, ex Rel. Dinneen Excavating Co., v. Sykes

Case Details

Full title:THE STATE, EX REL. DINNEEN EXCAVATING COMPANY, INC.; GEMMA, INC. ET AL.…

Court:Supreme Court of Ohio

Date published: Dec 14, 1988

Citations

40 Ohio St. 3d 84 (Ohio 1988)
531 N.E.2d 1309

Citing Cases

State, ex Rel. Supply Co., v. Jordano Elec

GESCO and the other appellants further maintain that by the 1975 amendment creating the escrow scheme, the…

Poenisch v. Kingsley-Dunbar, Inc.

Even if the lien does not attach until the money is owed the contractor, the subcontractor or materialman is…