Start Elevator, Inc. v. City of N.Y.

Supreme Court, Appellate Division, First Department, New York.
Mar 14, 2013
104 A.D.3d 488 (N.Y. App. Div. 2013)

Opinion

2013-03-14

In re START ELEVATOR, INC., Petitioner–Appellant, v. The CITY OF NEW YORK, et al., Respondents–Respondents.

Agulnick & Gogel, LLC, Great Neck (William Gogel of counsel), for appellant. Michael A. Cardozo, Corporation Counsel, New York (Diana Lawless of counsel), for The City of New York, The New York City Department of Correction, and The New York City Office of Administrative Trials and Hearings, respondents.



Agulnick & Gogel, LLC, Great Neck (William Gogel of counsel), for appellant. Michael A. Cardozo, Corporation Counsel, New York (Diana Lawless of counsel), for The City of New York, The New York City Department of Correction, and The New York City Office of Administrative Trials and Hearings, respondents.
Peggy Kuo, New York, for The Contract Dispute Resolution Board, respondent.

GONZALEZ, P.J., TOM, RICHTER, and ABDUS–SALAAM, JJ.

Judgment, Supreme Court, New York County (Eileen Bransten, J.), entered January 10, 2012, denying the petition to annul the determination of respondent New York City Contract Dispute Resolution Board (CDRB), dated February 28, 2011, which dismissed petitioner's claim due to its untimely filing of a petition to CDRB, and dismissing the proceeding brought pursuant to CPLR article 78, unanimously affirmed, without costs.

Judicial review of a CDRB determination is limited to the question of whether it was “made in violation of lawful procedure, was affected by an error of law, or was arbitrary or capricious or an abuse of discretion” (9 RCNY 4–09[g] [6] ). Here, CDRB's dismissal of the petition as untimely was proper. Petitioner submitted the materials in support of its notice of claim in March 2009. Once the New York City Comptroller failed to address this claim within 45 days thereafter, petitioner had 30 days in which to file a petition with CDRB, pursuant to the parties' contract and the New York City Procurement PolicyBoard (PPB) Rules (9 RCNY 4–09[e][4], [g] ). Petitioner, however, petitioned CDRB in November 2010, well after the 30–day period had expired. The court properly interpreted the provision stating that petitioner “may” petition CDRB within that period to require petitioner to do so in order to exhaust its administrative remedies, given that the contract and the PPB Rules provide that the time period is triggered once the Comptroller fails to respond within its 45–day period ( see JCH Delta Contr., Inc. v. City of New York, 44 A.D.3d 403, 843 N.Y.S.2d 245 [1st Dept. 2007] ).


Summaries of

Start Elevator, Inc. v. City of N.Y.

Supreme Court, Appellate Division, First Department, New York.
Mar 14, 2013
104 A.D.3d 488 (N.Y. App. Div. 2013)
Case details for

Start Elevator, Inc. v. City of N.Y.

Case Details

Full title:In re START ELEVATOR, INC., Petitioner–Appellant, v. The CITY OF NEW YORK…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Mar 14, 2013

Citations

104 A.D.3d 488 (N.Y. App. Div. 2013)
104 A.D.3d 488
2013 N.Y. Slip Op. 1610

Citing Cases

Tutor Perini Corp. v. City of New York

Order, Supreme Court, New York County (Carol R. Edmead, J.), entered May 12, 2020, which denied Tutor Perini…

Rockmore Contracting Corp. v. Contract Dispute Resolution Bd. of N.Y.

"Judicial review of a CDRB determination is limited to the question of whether it was made in violation of…