From Casetext: Smarter Legal Research

Smith Pipe Steel Co. v. Mead

Supreme Court of Arizona
Oct 7, 1981
634 P.2d 962 (Ariz. 1981)

Summary

noting legislature amended § 33–993 in 1973 to remove language that required description must be sufficient to identify the property in favor of current legal description requirement

Summary of this case from Wang Electric, Inc. v. Smoke Tree Resort, LLC

Opinion

No. 15331.

October 7, 1981.

Appeal from the Superior Court, Maricopa County, Sandra D. O'Connor, J., Cause No. C-375701.

Kaplan, Jacobowitz, Hendricks Bosse by Henry Jacobowitz, Phoenix, for appellant.

Abrams Schenk by Kenneth L. Abrams and Ronald M. Horwitz, Phoenix, for appellee.


This is an action by Smith Pipe Steel Co. (hereinafter "Smith") to foreclose a materialman's lien on certain property held in trust by William A. Mead. The Superior Court granted Mead's motion for summary judgment and Smith appeals. We take jurisdiction pursuant to 17A A.R.S. Rules of Civil Appellate Procedure, rule 19(e).

The facts pertinent to this appeal are brief and undisputed. Mead was a trustee for a trust which owned adjacent parcels of real property in Maricopa County. Smith sold and furnished construction materials to Flood Plumbing Company, a licensed plumbing subcontractor, for use in the construction of structures and improvements on the south parcel of the adjacent lots. Flood completed the work but subsequently went bankrupt and failed to pay Smith for the materials. Smith then recorded a Notice and Claim of Lien under the provisions of A.R.S. § 33-993. The Notice and Claim of Lien, however, gave the legal description of the north parcel, instead of the south parcel upon which the improvements were made. After Smith filed a complaint to foreclose the lien, Mead moved for summary judgment arguing that the erroneous description rendered the lien invalid. The trial court agreed and granted Mead's motion.

The sole issue presented is whether a lien claimant may perfect a materialman's lien where the Notice and Claim of Lien contains an erroneous legal description.

Smith contends that the erroneous description was sufficient to give notice to Mead which parcel was intended to be impressed with the lien. In making this argument, reliance is placed upon the familiar rule that the Arizona Mechanics' and Materialmen's Lien Statutes are to be liberally construed in favor of laborers and materialmen. Because the record is devoid of any indication that Mead was prejudiced by the erroneous legal description and no third-party rights were involved, Smith concludes that a liberal construction of the statute requires a finding that the lien was valid.

With regard to the content of the lien, the Court of Appeals has held that former A.R.S. § 33-993 did not require that the lien claim accurately describe the legal description of the property involved. Westinghouse Electric Supply Co. v. Western Seed Production Corp., 119 Ariz. 377, 580 P.2d 1231 (App. 1978); James Weller, Inc. v. Hansen, 21 Ariz. App. 217, 517 P.2d 1110 (1973). In 1973, however, the legislature amended § 33-993 to provide that the notice and claim of lien contain "[t]he legal description of the lands and improvements to be charged with a lien." (Emphasis added.) In light of this change, Mead submits that Smith has not achieved even substantial compliance with the statute's "legal description" requirement in that the legal description contained in its Notice and Claim of Lien is "unambiguously erroneous" and fails to describe the correct parcel of property. We agree.

Former A.R.S. § 33-993(1) provided that the notice and claim of lien contain "[a] description of the lands and improvements to be charged with a lien sufficient for identification."

The 1973 amendment to § 33-993(1) clarifies the manner in which the property to be charged with the lien is to be described. The inexact provision under former § 33-993(1), "[a] description . . . sufficient for identification" did not give any indication whether a legal description, street address, or physical description of the land or improvements would suffice. The amended version, however, removed this obvious ambiguity by requiring a legal description to be used when describing the property to be charged with the lien. Significantly, the legislature not only added the legal description requirement, but at the same time omitted the "sufficient for identification" language from the old statute. We believe this reflects a legislative intent that substantial compliance with the legal description requirement is necessary in order to perfect a lien. As was aptly stated by the Supreme Court of Idaho in a case with virtually identical facts, "[a]lthough the rule may be different with regard to a description which is merely loose, vague, or ambiguous, where the real property description in a mechanic's lien claim notice is `unambiguously erroneous' and describes with exactitude the wrong parcel of real property, substantial compliance is not achieved, and the claim of lien is invalid." Ross v. Olson, 95 Idaho 915, 917, 523 P.2d 518, 520 (1974). See also Banco Mortgage Co. v. E.G. Miller Enterprises, Inc., 264 N.W.2d 399 (Minn. 1978); Hudson Demolition Co. v. Ismore Realty Corp., 62 A.D.2d 980, 403 N.Y.S.2d 327 (1978).

Judgment affirmed.

STRUCKMEYER, C.J., HOLOHAN, V.C.J., and CAMERON and GORDON, JJ., concur.


Summaries of

Smith Pipe Steel Co. v. Mead

Supreme Court of Arizona
Oct 7, 1981
634 P.2d 962 (Ariz. 1981)

noting legislature amended § 33–993 in 1973 to remove language that required description must be sufficient to identify the property in favor of current legal description requirement

Summary of this case from Wang Electric, Inc. v. Smoke Tree Resort, LLC

In Smith Pipe Steel Co. v. Mead, 130 Ariz. 150, 151, 634 P.2d 962, 963 (1981) (" Smith"), the Arizona Supreme Court held that A.R.S. § 33-993(A)(1) "reflects a legislative intent that substantial compliance with the legal description requirement is necessary in order to perfect a [mechanics'] lien."

Summary of this case from Hartford Acc. Indem. v. Federal Ins. Co.

In Smith Pipe Steel, the defendant owned two adjacent parcels of real property. The plaintiff lien claimant provided materials for construction on the south parcel.

Summary of this case from MLM Construction Co. v. Pace Corp.

In Smith Pipe Steel Co. v. Mead, 130 Ariz. 150, 634 P.2d 962 (1981), the owner had two adjacent parcels of real property, one directly south of the other.

Summary of this case from S.K. Drywall v. Developers Fin. Group
Case details for

Smith Pipe Steel Co. v. Mead

Case Details

Full title:SMITH PIPE STEEL COMPANY, an Arizona Corporation, Appellant, v. William A…

Court:Supreme Court of Arizona

Date published: Oct 7, 1981

Citations

634 P.2d 962 (Ariz. 1981)
634 P.2d 962

Citing Cases

Hartford Acc. Indem. v. Federal Ins. Co.

A.R.S. § 33-993(A)(1) (1990). In Smith Pipe Steel Co. v. Mead, 130 Ariz. 150, 151, 634 P.2d 962, 963 (1981)…

Wang Electric, Inc. v. Smoke Tree Resort, LLC

Smoke Tree argues this recitation fails as a “legal description” but does not explain how. Aero asserts…