Opinion
5:17-cv-10164-JEL-KGA
05-19-2022
Flint Water Cases Bellwether I
ORDER REGARDING MOTION TO COMPEL SERVICE AND COMPLIANCE WITH LOCAL RULES
JUDITH E. LEVY, United States District Judge.
On May 18, 2022, Co-Liaison Counsel for individual Plaintiffs filed a motion for an emergency order compelling the production of documents from Defendant Veolia Water North America Operating Services, LLC, Non-Parties Veolia Water contract Services, Veolia Water Logistics, LLC, Veolia Water Municipal Services North American, and Veolia Environmental Services. (ECF No. 827.) On May 5, 2022, Plaintiffs served these entities with trial subpoenas, all of which are attached as exhibits to Plaintiffs' motion. (ECF Nos. 827-2- 827-6.) The law firm Todd & Weld LLP responded with objections to the subpoenas on behalf of all entities. (ECF Nos. 827-7- 827-10.)
Four of the subpoenaed Veolia entities are not parties to the Flint Water litigation or the Bellwether I trial. Accordingly, Plaintiffs' certificate of service, which states only that it was filed electronically using the CM/ECF system, does not effectuate service on the four nonparty Veolia entities. (See ECF No. 827, PageID.51563.) This does show that service was made on Defendant Veolia Water North America Operating Services, LLC, however. Plaintiffs must properly serve their motion to compel on the non-party Veolia entities before the Court can consider or rule on the motion.
Further, Eastern District of Michigan Local Rule 7.1(a) requires that a movant “must ascertain whether the contemplated motion . . . will be opposed.” E.D. Mich. LR 7.1(a). Rule 7.1 is written broadly and applies to motions against both parties and non-parties. Id. (“If the movant obtains concurrence, the parties or other persons involved may make the subject matter of the contemplated motion or request a matter of record by stipulated order.” (emphasis added)). Plaintiffs' motion does not contain an indication that concurrence was sought from any of the subpoenaed entities.
If Plaintiffs wish to have the Court consider their motion, they must correct these deficiencies no later than Monday, May 23, 2022. Otherwise, the motion will be stricken for non-compliance with the local rules.
IT IS SO ORDERED.