From Casetext: Smarter Legal Research

Sheet Metal Workers v. Jersey Sheet Metal Works

United States District Court, E.D. New York
Jan 13, 2009
Case No. 07-CV-0131 (FB) (ARL) (E.D.N.Y. Jan. 13, 2009)

Opinion

Case No. 07-CV-0131 (FB) (ARL).

January 13, 2009

For the Plaintiffs: JEFFREY S. DUBIN, ESQ., Huntington, NY.

For the Defendants. ROGER ROTHMAN, ESQ., Bay Shore, NY.


MEMORANDUM AND ORDER


Before the Court is plaintiffs' motion to enforce the terms of the parties' Settlement Stipulation and Order ("Settlement Agreement"), executed December 19, 2007.

I

Plaintiffs are five employee benefit plans. Their complaint, filed on January 10, 2007, alleged, inter alia, that defendants failed to make required contributions to the plans in violation of § 515 of the Employee Retirement Income Security Act, 29 U.S.C. § 1145. See Compl. (Docket Entry #1). On December 19, 2007, the parties executed the Settlement Agreement, pursuant to which defendants agreed to pay plaintiffs $486,306.14 in 24 monthly installments in exchange for a release from all claims. See Settlement Agreement (Docket Entry #9). The Settlement Agreement contained the following provisions for its enforcement:

Default by defendant(s) is defined as the failure to make any required payment in full, including interest, within ten (10) days of its due date, and the failure to cure after ten (10) days['] . . . notice. . . .
Upon default by defendant(s), defendant(s) consent to the entry of a judgment against them, jointly and severally, without further notice, in the amount of $603,542.76, plus interest of 8.5% per annum, and attorney's fees and costs . . . from the date the payment was due, less any amounts paid hereunder, in the United States District Court for the Eastern District of New York. . . .
The Court shall retain jurisdiction of this matter for the purpose of enforcing the terms of this Settlement Agreement and any Order or Judgment resulting therefrom. . . .
Either party may, without notice, submit this Agreement to the Court to be "so ordered."

Settlement Agreement at 4-5. In light of the parties' settlement, an Order was issued dismissing this case on December 27, 2007.

On October 30, 2008, plaintiffs moved for entry of judgment against defendants in accordance with the Settlement Agreement, stating that "defendants defaulted . . . on October 1, 2008, by failing to make a payment when due and failing to cure said default after notice." Decl. in Support of Default J. (Docket Entry # 10, Ex. 3) at 4. Defendants, having been duly served, see Certificate of Service (Docket Entry # 12), did not respond. Consequently, the Clerk of the Court entered defendants' default on November 25, 2008. See Clerk's Entry of Default (unnumbered Docket Entry). That same day, plaintiffs withdrew their request for entry of judgment against Jersey Sheet Metal Works, Inc., since it had filed for Chapter 11 bankruptcy protection. See Decl. in Support of Default J. (Docket Entry #11, Ex. 3) at 5. On December 10, 2008, plaintiffs submitted a letter indicating that plaintiffs had agreed to withdraw their action against Stuart Phillips and requesting that judgment be entered only against Robert Phillips. See Mot. to Amend/Correct/Supplement Proposed J. (Docket Entry #13) at 1.

Prior to defendants' default, they had paid $182,364.84 of the amount due under the Settlement Agreement. See Proposed Default J. (Docket Entry #10, Ex. 1) at 2.

II

"A trial court has inherent power to enforce summarily a settlement agreement when the terms of the agreement are clear and unambiguous." Omega Eng'g, Inc. v. Omega, S.A., 432 F.3d 437, 444 (2d Cir. 2005) (internal quotation marks and citation omitted); see also Meetings Expositions, Inc. v. Tandy Corp., 490 F.2d 714,717 (2d Cir. 1974) ("A district court has the power to enforce summarily, on motion, a settlement agreement reached in a case that was pending before it.") (citations omitted). The parties' Settlement Agreement is unambiguous; its plain meaning dictates that, in the event defendants fail to make a payment when due and subsequently fail to cure, plaintiffs are entitled to an entry of judgment against defendants jointly and severally.

Defendants have not contested plaintiffs' allegations of default under the Settlement Agreement. In the face of defendants' silence, this allegation must be taken as true. See Greyhound Exhibitgroup, Inc. v. E.L.U.L. Realty Corp., 973 F.2d 155,158 (2d Cir. 1992); Flaks v. Koegel, 504 F.2d 702, 707 (2d Cir. 1974). Robert Phillips's liability for the liquidated damages specified in the Settlement Agreement follows as a matter of law.

CONCLUSION

For the reasons described above, the Court directs the Clerk to enter judgment against Robert Phillips in the amount of $431,476.59, consisting of the sum of (1) $421,177.92 in principal (i.e., the $603,542.76 in liquidated damages specified by the Settlement Agreement less the $182,364.84 already paid thereunder), and (2) $10,298.67 in interest (calculated at the rate of 8.5% per annum from the date of default, October 1, 2008, until the date of this Memorandum and Order). Plaintiffs are also entitled to post-judgment interest on this sum at the standard federal rate. See 28 U.S.C. § 1961(a).

The Settlement Agreement does not specify whether the interest should be simple or compound. Plaintiffs' calculations, however, indicate that they are seeking an award of simple interest, see Statement for Default J. (Docket Entry #10, Ex. 2), and the Court, therefore, awards only simple interest.

While the Settlement Agreement also entitles plaintiffs to attorney's fees and costs in the event of defendants' default, see Settlement Agreement at 4, plaintiffs' motion does not seek fees or costs, either expressly or implicity (e.g., by a request for "such other relief as the Court deems proper"). The Court, consequently, does not award them.

SO ORDERED.


Summaries of

Sheet Metal Workers v. Jersey Sheet Metal Works

United States District Court, E.D. New York
Jan 13, 2009
Case No. 07-CV-0131 (FB) (ARL) (E.D.N.Y. Jan. 13, 2009)
Case details for

Sheet Metal Workers v. Jersey Sheet Metal Works

Case Details

Full title:SHEET METAL WORKERS' NATIONAL PENSION FUND; NATIONAL ENERGY MANAGEMENT…

Court:United States District Court, E.D. New York

Date published: Jan 13, 2009

Citations

Case No. 07-CV-0131 (FB) (ARL) (E.D.N.Y. Jan. 13, 2009)