From Casetext: Smarter Legal Research

Rowley v. Salladin

Supreme Court of Connecticut
Mar 31, 1953
139 Conn. 642 (Conn. 1953)

Summary

In Rowley, the general contractor had abandoned the project without paying the subcontractor, who then filed a mechanic's lien.

Summary of this case from Prof'l Elec. Contractors, Inc. v. Stamford Hosp.

Opinion

Under our mechanic's lien statute, where a contractor, without fault on the owner's part, has abandoned his contract before its substantial completion, so that nothing is due him under his contract, the subcontractors have no lien for labor or materials furnished by them; and this is so although the expense of completing the building would be less than the balance remaining unpaid.

Argued March 5, 1953

Decided March 31, 1953

Action for the foreclosure of a mechanic's lien, brought to the Court of Common Pleas in Middlesex County and tried to the court, Parmelee, J.; judgment for the plaintiff, appeal by the named defendant and cross appeal by the plaintiff. Error; judgment directed.

Bernard A. Kosicki, for the appellant-appellee (named defendant).

C. O. Dunbar, Jr., for the appellant-appellee (plaintiff).


The plaintiff had judgment of strict foreclosure of a mechanic's lien. The named defendant, hereinafter called the defendant, and the plaintiff have appealed. Both parties have attacked the finding, but neither can prevail on this issue since the additions they request involve facts which are neither admitted for undisputed. Practice Book 397. The single paragraph of the finding which the defendant seeks to strike as found without evidence is immaterial in the view we take of the case.

The finding is as follows: On or about December 28, 1949, the defendant entered into a written contract with the defendant Bishop for the construction of a cottage on premises owned by the former in Clinton. One thousand dollars in cash was paid in good faith on the signing of the contract. The balance of $2200 was to be paid when the work was completed. The plaintiff furnished materials of the value of $1506.02 to be used by Bishop in building the house and filed a proper mechanic's lien against the defendant's property. Bishop abandoned the job after it was partially completed. The defendant spent $538.19 to protect the property from the weather, and it will cost her $1000 additional to complete it.

On these facts the trial court reached the following conclusions: Bishop abandoned the construction of the house and defaulted on his contract without fault on the part of the defendant; the plaintiff is entitled to $661.81, the difference between $2200, the sum still due on the contract price, and $1538.19, the amount spent and to be spent to complete the cottage. The court set the debt at $661.81 plus interest and rendered judgment of strict foreclosure.

The defendant claimed that the plaintiff had no right to a mechanic's lien because Bishop had none. It is clear that Bishop had none. He had abandoned his contract, without fault on the part of the defendant, and the amount found necessary to complete it shows that he could not claim substantial performance. It follows that the plaintiff was entitled to no further payment; Fabrizio v. Fabrizio, 133 Conn. 108, 112, 48 A.2d 3715; and had no right to a mechanic's lien. Section 1273b of the 1951 Cumulative Supplement (formerly 7217 of the General Statutes) provides: "No mechanic's lien shall attach to any . . . building or its appurtenances or to the land on which the same may stand in favor of any subcontractor to a greater extent in the whole than the amount which the owner shall have agreed to pay to any person through whom such subcontractor shall claim. . . . Any such subcontractor shall be subrogated to the rights of the person through whom such subcontractor claims." "So under such statutes [as ours], where a contractor, without fault on the owner's part, has abandoned his contract before its substantial completion, so that nothing is due him under his contract, the subcontractors have no lien for labor or materials furnished by them; and this is so although the expense of completing the improvement according to the contract would be less than the balance of the contract price for the entire work remaining unpaid." Tice v. Moore, 82 Conn. 244, 248, 73 A. 133; Drazen Lumber Co. v. Jente, 113 Conn. 344, 347, 155 A. 505; Avery v. Smith, 96 Conn. 223, 225, 113 A. 313; Waterbury Lumber Coal Co. v. Coogan, 73 Conn. 519, 521, 48 A. 204. The plaintiff's lien was unenforceable and the judgment was erroneous.

The cross appeal of the plaintiff does not affect this result. His attack on the finding has been disposed of above. His only other assignment complains of the overruling of the defendant's claims of law. If we assume that he means his own claims, it appears that they refer only to claims of fact as to which the court found against him.


Summaries of

Rowley v. Salladin

Supreme Court of Connecticut
Mar 31, 1953
139 Conn. 642 (Conn. 1953)

In Rowley, the general contractor had abandoned the project without paying the subcontractor, who then filed a mechanic's lien.

Summary of this case from Prof'l Elec. Contractors, Inc. v. Stamford Hosp.
Case details for

Rowley v. Salladin

Case Details

Full title:NATHAN W. ROWLEY v. VALEDA C. SALLADIN ET AL

Court:Supreme Court of Connecticut

Date published: Mar 31, 1953

Citations

139 Conn. 642 (Conn. 1953)
96 A.2d 219

Citing Cases

Prof'l Elec. Contractors, Inc. v. Stamford Hosp.

In light of the legislative history of No. 502 of the 1953 Public Acts and the purpose for which it was…

Starkel v. Edward Balf Co.

The defendant seeks to have stricken from the finding two of the paragraphs, but the request is denied since…