From Casetext: Smarter Legal Research

Risman v. Granader

Michigan Court of Appeals
May 21, 1981
309 N.W.2d 562 (Mich. Ct. App. 1981)

Opinion

Docket No. 48297.

Decided May 21, 1981.

Tucker, Barbour Mack, for plaintiffs.

Lawrence J. Stockler, P.C., for defendants.

Before: M.J. KELLY, P.J., and V.J. BRENNAN and T.M. BURNS, JJ.


Plaintiffs appeal as of right an August 24, 1979, lower court order confirming a modified arbitration award. We affirm.

We summarily reject plaintiffs' argument that the members of the arbitration panel exceeded their authority. Specifically, plaintiffs contend that the arbitration panel exceeded its authority because it assessed an award against Realtek Industries, Incorporated, and provided that the award be paid to Westland Towers Apartments and indirectly to Donald Horace. Plaintiffs note that even though the modified arbitration award deleted the name of Realtek Industries, the amount of the award remained unchanged, and, hence, the award still sought to hold Realtek liable.

There is no dispute with the fact that Realtek was not a party to the arbitration agreement. However, the arbitration panel's award should be taken at face value. The modified award makes no mention of Realtek, and, moreover, there is no indication that plaintiffs were not subjected to personal liability for the several claims made against them in the arbitration dispute.

It is apparent that the claims submitted by the defendants to the arbitration panel were directed against plaintiffs for mismanagement. It would be incorrect to construe these claims as being directed against Realtek.

Nor did the arbitrators exceed their authority because their award enured to the benefit of Donald Horace and Westland Towers Apartments. The partnership agreement incorporated all of the terms and conditions of the joint venture agreement. It is clear that the partnership agreement itself bound all of the parties to an agreement to arbitrate all disputes arising out of the agreement. Because the partnership itself was a party to the agreement, the fact that it, or one of the individual partners, may have received some benefit from the arbitration award is not sufficient to have that award set aside.

Plaintiffs next argue that the lower court erred in failing to vacate the arbitration award because the arbitrators rendered a blanket award rather than a separate award for the specific claims presented to it. However, while this Court has suggested on prior occasions that arbitrators should address themselves to each claim in a multiple-claim case rather than render a blanket award, it is not necessary for arbitrators to do so. See Detroit Demolition Corp v Burroughs Corp, 50 Mich. App. 129; 212 N.W.2d 827 (1973), rev'd on other grounds 392 Mich. 769; 219 N.W.2d 613 (1974), E E Tripp Excavating Contractor, Inc v Jackson County, 60 Mich. App. 221; 230 N.W.2d 556 (1975), lv den 394 Mich. 834 (1975).

The fact that the arbitrators did not address in their award each of the individual claims presented to them is not sufficient under these facts and on this record to require that the award be vacated. Cf. North American Steel Corp v Siderius, Inc, 75 Mich. App. 391; 254 N.W.2d 899 (1977), where the panel was ordered to make specific findings of fact and had not complied. It would be inappropriate on the facts of this case to establish a rule of law requiring arbitration panels in all cases to individually address multiple claims — particularly so since this record does not contain a complete list of the various claims submitted to arbitration.

Plaintiffs' final argument is that the lower court erred in failing to set aside the award because the arbitrators refused to hear evidence material to the controversy. See GCR 1963, 769.9(1)(d). Our examination of the record indicates that the arbitrators did give plaintiffs a full and fair opportunity to present all pertinent facts to the arbitration panel the first time that this case was submitted to it. We note, in particular, that the lower court order vacating the original arbitration award and remanding this controversy to the arbitration panel did not order the panel to conduct further fact-finding. Further, although plaintiffs allege that new and additional facts should have been submitted to the arbitration panel on remand, plaintiffs do not indicate what these new facts are, nor have they established that these facts are material. Therefore, the fact that plaintiffs were denied permission to present new facts to the arbitration panel prior to the panel's issuance of this amended award does not require that that award be vacated.

Affirmed.


Summaries of

Risman v. Granader

Michigan Court of Appeals
May 21, 1981
309 N.W.2d 562 (Mich. Ct. App. 1981)
Case details for

Risman v. Granader

Case Details

Full title:RISMAN v GRANADER

Court:Michigan Court of Appeals

Date published: May 21, 1981

Citations

309 N.W.2d 562 (Mich. Ct. App. 1981)
309 N.W.2d 562