Reybold Venture Grp. VII v. ODA Architecture, PLLC

Superior Court of Delaware
Nov 22, 2024
C. A. N22C-05-012 VLM (Del. Super. Ct. Nov. 22, 2024)

Opinion

C. A. N22C-05-012 VLM

11-22-2024

Reybold Venture Group VII, LLC and Reybold Construction Group, LLC v. ODA Architecture, PLLC, Overcash Demmitt Architects, PLLC, and Wave Engineering, PLLC

Jeffrey M. Weiner, Esquire Law Offices of Jeffrey M. Weiner Joseph J. Bellew, Esquire Joseph E. Brenner, Esquire Gordon Rees Scully Mansukhani, LLP Eric Scott Thompson, Esquire Franklin & Prokopik


Submitted: September 11, 2024

Jeffrey M. Weiner, Esquire Law Offices of Jeffrey M. Weiner

Joseph J. Bellew, Esquire Joseph E. Brenner, Esquire Gordon Rees Scully Mansukhani, LLP

Eric Scott Thompson, Esquire Franklin & Prokopik

Dear Counsel:

On September 11, 2024, the Court held a remote hearing on Plaintiffs' Motion for Partial Summary Judgment. For the reasons stated below, Plaintiffs' Motion is DENIED.

Factual and Procedural Background

Unless otherwise noted, this Court's recitation is drawn from Plaintiff's Amended Complaint (hereafter "Am. Compl.") and all documents the parties incorporated by reference. D.I. 3.

This case arises from a dispute over the design and implementation of an HVAC system in a lifestyle storage facility. On May 23, 2017, Plaintiff Reybold Venture Group VII, LLC ("RVG") and Defendant ODA Architecture, PLLC ("ODA") entered into a contract for engineering and architectural services for RVG's Lifestyle Storage Facility ('LSF") project. Three months later, ODA subsequently subcontracted with Defendant Wave Engineering, PLLC ("Wave") on August 13, 2017, for mechanical, electrical, and plumbing engineering services for the same LSF project. Defendants proceeded and prepared plans necessary for the construction of the LSF project. Wave commenced its project design in October 2017 to the point of issuing permit drawings. The project then sat dormant for nearly two years. Thereafter, building permits were issued in August 2019, and Certificates of Occupancy were issued in July 2021.

Id. at 3; D.I. 7 at 1 (hereinafter "Def. ODA's Answer").

Def. ODA's Answer at 2.

Am. Compl. at 3.

D.I. 118 at 16 (hereinafter "Pls.' Mot. for Partial Summ. J. Opening Br.").

Id.

During the construction of the HVAC system, Plaintiffs' HVAC contractor, East Coast Plumbing & HVAC, Inc. ("East Coast"), prepared submissions of 4 Split System with Electric heat based upon the equipment produced by Trane, allegedly based on Wave's M-101 drawing. On October 22, 2019, an engineer of Wave reviewed these submissions and acknowledged that each had been reviewed as noted for "general compliance with the intent of the Contract documents." See id.

Am. Compl. at 3.

Upon occupancy, RVG experienced inadequate HVAC system performance issues and elevated humidity. RVG retained McHugh Engineering Associates ("McHugh") to review the HVAC system. On February 10, 2022, McHugh issued a report finding that Wave had oversized the HVAC equipment, which is manufactured by Trane, that likely caused operational issues and lack of humidity control.

See Pls.' Mot. for Partial Summ. J. Opening Br. at 5.

Am. Compl. at 3.

The report found that Wave had oversized the HVAC equipment by including an additional 1 watt/sq ft load (29.2 tons) that McHugh could not verify the origin of. See Pls.' Mot. for Partial Summ. J. Opening Br., at 5.

See id. at 6.

On June 23, 2022, Plaintiffs filed an Amended Complaint alleging Breach of Contract (Count I) and Professional Negligence (Count II) against Defendants. On April 18, 2024, Plaintiffs filed a Motion for Partial Summary Judgment as to Liability against Defendants Wave and ODA. Wave oppose, with ODA joining. Arguments were heard on September 11, 2024. The matter is ripe for review.

Am. Compl.

D.I. 114 (hereinafter "Pls.' Mot. for Partial Summ. J.").

D.I. 120 (hereinafter "Def. Wave's Answer to Pls.' Mot. for Partial Summ. J.).

D.I. 121.

Standard of Review

The burden of proof on a motion for summary judgment under Superior Court Civil Rule 56 falls on the moving party to demonstrate that "there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." If the moving party satisfies its initial burden, the non-moving party must sufficiently establish the "existence of one or more genuine issues of material fact." Summary judgment will not be granted if there is a material fact in dispute or if "it seems desirable to inquire thoroughly into [the facts] in order to clarify the application of the law to the circumstances." "All facts and reasonable inferences must be considered in a light most favorable to the non-moving party."

Super. Ct. Civ. R. 56(c).

Quality Elec. Co., Inc. v. E. States Const. Serv., Inc., 663 A.2d 488, 1995 WL 379125, at *3-4 (Del. 1995); see also Moore v. Sizemore, 405 A.2d 679, 681 (Del. 1979).

Ebersole v. Lowengrub, 180 A.2d 467, 469-70 (Del. 1962). See also CNH Indus. Am. LLC v. Am. Cas. Co. cf Reading, 2015 WL 3863225, at *1 (Del. Super. June 8, 2015).

Nutt v. A.C. & S. Co., Inc., 517 A.2d 690, 692 (Del. Super. 1986) (citing Mechell v. Plamer, 343 A.2d 620, 621 (Del. 1975); Allstate Auto Leasing Co. v. Caldwell, 394 A.2d 748, 752 (Del. Super. 1978)).

Discussion

The elements of a breach-of-contract claim are "(1) the existence of a contractual obligation; (2) a breach of that obligation; and (3) damages resulting from the breach." Plaintiffs seeks partial summary judgment on the issue of liability for two reasons: that it is undisputed that Wave oversized the HVAC system in its design, and it further failed to notice during its review that Trane had changed the blower motor size. This, they say, establishes liability.

Buck v. Viking Holding Mgmt. Co. LLC, 2021 WL 673459, at *3 (Del. Super. Feb. 22, 2021) (citing VLIW Tech., LLC v. Hewlett-Packard Co., 840 A.2d 606, 612 (Del. 2003)).

Plaintiffs contend that Wave oversized the HVAC system in its design by including an unjustified additional 1 watt/sq ft load for the entire 72,000 sq ft building, resulting in equipment approximately 60% larger than required by Code. See Pls.' Mot. for Partial Summ. J. Opening Br. at 6.

Plaintiffs allege that the change in blower motor size caused shortened HVAC operational run times, HVAC system short cycling, and elevated humidity levels. See id. at 8.

A. Reason for Oversizing of the HVAC System is Question of Fact

Plaintiffs first argue that because it is undisputed that Wave oversized the HVAC system in its design, the interpretation of the calculation that resulted in the oversizing establishes liability. Wave contests this interpretation, arguing that their calculations were appropriate for a "permittable set of plans."

Plaintiffs support this claim with expert analysis from McHugh, which found a minimal difference of 0.7 tons between their calculations and Wave's, excluding the additional 1 watt/sq ft. See id. at 5-10.

Def. Wave's Answer to Pls.' Mot. for Partial Summ. J. at 6.

Although perhaps there are some undisputed facts (ex. the addition of 1 watt/sq ft.), the appropriateness of this calculation in the context of professional engineering standards remains a genuine issue of material fact. Thus, Wave's assertion that decisions based on interpretations/calculations were within acceptable professional judgment creates a factual dispute that requires further examination by the factfinder.

B. Change in Blower Motor Size is Question of Fact

Plaintiffs next argue that liability is established as a matter of law regarding Wave's failure to notice that Trane had changed the blower motor size. Specifically, that documentation shows Wave reviewed the "equipment," and their responses included "Equipment Reviewed." Plaintiffs argue these undisputed facts entitle them to summary judgment. Not so.

See Pls.' Mot. for Partial Summ. J. Opening Br. at 11.

D.I. 124 at 10 (hereinafter "Pls.' Reply Br. in Supp. of Mot. for Partial Summ. J.").

Id.

Wave acknowledges there was a change but contends that the responsibility for detecting such changes lay with other parties, including the construction manager, Trane, and the installation contractor. Furthermore, Wave maintains that their general note disclaiming responsibility for "equipment substitution" absolves them of liability.

See Def. Wave's Answer to Pls.' Mot. for Partial Summ. J. at 10-13.

The general note also disclaims responsibility for "quantities or counts." See Def. Wave's Answer to Pls.' Mot. for Partial Summ. J. at 4-5.

At the outset, whether the circumstances here fall within the scope of the disclaimer presents a genuine issue of material fact. The interpretation of Wave's responsibilities under their contract and professional standards-even considering their own documentation and disclaimers-presents factual questions that cannot be resolved at this juncture and must also be left to the factfinder. This, coupled with the allocation of responsibility of detecting equipment changes that involved other individual in the project, also precludes summary judgment.

Wave has raised questions about other potential factors affecting system performance, including references to a "Green Roof' and the involvement of other contractors in the equipment selection and installation process. See id. at 2.

Conclusion

Viewing in the light most favorable to the non-moving party, genuine issues of material fact exist as to whether the interplay of various factors, including design decisions, equipment changes, and installation practices contributed to the claimed inefficiencies alleged. Therefore, Plaintiffs' Motion for Partial Summary Judgment is DENIED.

Sincerely,

Vivian L. Medinilla, Judge


Summaries of

Reybold Venture Grp. VII v. ODA Architecture, PLLC

Superior Court of Delaware
Nov 22, 2024
C. A. N22C-05-012 VLM (Del. Super. Ct. Nov. 22, 2024)
Case details for

Reybold Venture Grp. VII v. ODA Architecture, PLLC

Case Details

Full title:Reybold Venture Group VII, LLC and Reybold Construction Group, LLC v. ODA…

Court:Superior Court of Delaware

Date published: Nov 22, 2024

Citations

C. A. N22C-05-012 VLM (Del. Super. Ct. Nov. 22, 2024)