Opinion
No. 05-16-00509-CV
08-15-2017
On Appeal from the 193rd Judicial District Court Dallas County, Texas
Trial Court Cause No. DC-14-11847
MEMORANDUM OPINION
Before Justices Lang, Fillmore, and Schenck
Opinion by Justice Lang
Quickset Concrete, Inc. appeals from the trial court's judgment confirming an arbitration award of damages to RoeschCo Construction, Inc. ("RCC"). In two issues, appellant asserts the trial court erred by denying its "Motion for New Trial and Motion to Modify Arbitration Holding" because: (1) there was an evident miscalculation in the arbitration award; and (2) the arbitrator exceeded his authority. RCC argues in response that appellant "has waived its right to a modification of the arbitration award" because it "failed to timely file a motion to vacate or modify the arbitration award."
We decide against appellant on its issues. Because the law to be applied in this case is well settled, we issue this memorandum opinion. See TEX. R. APP. P. 47.2, 47.4.
I. Factual and Procedural Context
This case involves a construction contract dispute. Appellant was a subcontractor for RCC on two construction projects, one of which, the "Trinity Strand Project," is the subject of this case. On June 24, 2013, the parties signed a Master Subcontract Agreement ("MSA") which the parties agree governs the two subcontracts. The MSA provided that:
Subject to the limiting provisions set forth below, all claims, disputes and other matters in question between the Contractor and the Subcontractor that are not subject to Section 3F of this Subcontract, arising out of, or relating to this Subcontract or the breach thereof shall be decided by arbitration which shall be held in Dallas, Texas in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect unless the parties mutually agree otherwise. The award rendered by the arbitrator(s) shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction.
Appellant stopped work on the Trinity Strand Project in March 2014 before the project was completed. Appellant claimed RCC "breached the contract by wrongfully deducting $29,000 from work performed and in creating a negative pay application and other grounds." RCC also claimed appellant breached the contract.
On October 8, 2014, appellant filed suit. In its "First Amended Original Petition," appellant requested monetary damages based on breach of contract and quantum meruit. On November 3, 2014, RCC filed its "Original Answer Subject to Its Motion to Abate and Compel Arbitration" and a separate "Motion to Abate and Compel Arbitration." In its "Motion to Abate and Compel Arbitration," RCC sought enforcement of the arbitration provision in the MSA. On January 8, 2015, the trial court signed an "Agreed Order Granting Motion to Abate" abating the case pending the outcome of arbitration.
The arbitration proceeding took place in January 2016. On March 1, 2016, the arbitrator rendered his written "Award of Arbitrator." In this award the arbitrator found, among other things, that "Appellant was not justified in abandoning the Trinity Strands Project" and that "RoeschCo is the 'Prevailing Party' as defined" in the contract. The arbitrator awarded $91,240.00 in damages to RCC. On March 8, 2016, RCC filed in the trial court a "Motion to Lift Abatement and Application to Confirm Arbitration Award."
On March 16, 2016, appellant filed, with the American Arbitration Association (AAA), "Claimant's Motion to Correct Award." In that motion appellant argued that it was the prevailing party, "was entitled to recover its legal fees and costs," and that the arbitrator should "correct the award" and "enter judgment" for appellant as requested. On March 21, 2016, RCC responded to this motion by filing a "Response to Quick Set Concrete, Inc.'s Motion to Correct Award." Then, on March 23, 2016, appellant filed with the AAA its "Reply to Response of RoeschCo Construction Inc."
Appellant did not file a response in the trial court to RCC's motion to confirm the arbitration award. So, on March 21, 2016, the trial court signed a final judgment. In that judgment, the trial court found appellant had not filed an application to vacate the arbitration award, the allegations in RCC's "Application to Confirm the Arbitration Award" were true and correct, and that RCC was damaged by appellant in the amount of $91,240.00 as found in the arbitration award.
On March 24, 2016, appellant filed in the trial court a "Motion for New Trial." In that motion appellant argued that its "motion to correct award was timely filed," albeit with the AAA, and requested that, "[i]f the arbitrator does not rule in Plaintiff's favor . . . the Court modify and correct the award and enter judgment for Plaintiff." On March 31, 2016, the arbitrator signed an "Order on Motion to Correct Award" that denied appellant's motion. In that order, the arbitrator stated: "I find the relief requested is not authorized by AAA Construction Rule 48, is outside of my authority as arbitrator, and appears in fact to seek a substantive change in the Award having duly been entered by me in this arbitration case." The arbitrator also stated that the "Award dated March 1, 2016, is reaffirmed and remains in full force and effect."
On April 8, 2016, appellant filed with the trial court its "First Amended Motion for New Trial and Motion to Modify Arbitration Holding." That motion advised the trial court the arbitrator declined to modify the arbitration award and requested the trial court correct the arbitrator's "miscalculation." After RCC responded to the motion, the trial court held a hearing where both parties presented evidence. The trial court rendered an order denying appellant's motion. This appeal was timely perfected.
II. Motions to Vacate or Modify Arbitration Awards
A. Applicable Law
Section 171.091 of the Texas Arbitration Act ("TAA") provides in relevant part:
(a) On application, the court shall modify or correct an award if:
(1) the award contains:
(A) an evident miscalculation of numbers; or
(B) an evident mistake in the description of a person, thing, or property referred to in the award;
TEX. CIV. PRAC. & REM. CODE ANN. § 171.091(a) (West 2011). Thus, the TAA "require[s] the trial court to confirm an arbitration award unless 'grounds are offered for vacating, modifying, or correcting an award. . . .'" Hamm v. Millenium Income Fund, L.L.C., 178 S.W.3d 256, 262 (Tex. App.—Houston [1st Dist.] 2005, pet. denied) (citing TEX. CIV. PRAC. & REM. CODE ANN. § 171.087 (West 2011)). Thus, "confirmation is the default result unless a challenge to the award has been or is being considered." Id; see also New Med. Horizons II, Ltd. v. Jacobson, 317 S.W.3d 421, 427 (Tex. App.—Houston [1st Dist.] 2010, no pet.); In re Guardianship of Cantu de Villarreal, 330 S.W.3d 11, 18 (Tex. App.—Corpus Christi 2010, no pet.).(2) the arbitrators have made an award with respect to a matter not submitted to them and the award may be corrected without affecting the merits of the decision made with respect to the issues that were submitted; or
(3) the form of the award is imperfect in a manner not affecting the merits of the controversy."
"Additionally, the TAA provides that (1) if the court denies a motion to vacate, to modify, or to correct an arbitration award, it must confirm the award and (2) if the court grants a motion to modify or to correct an award, it must confirm the award as modified or corrected." Hamm, 178 S.W.3d at 263 (citing TEX. CIV. PRAC. & REM. CODE ANN. §§ 171.088(c) (West 2011), 171.091(c)). "Taken together with the section requiring confirmation unless statutory grounds not to do so are shown, sections 171.088(c) and 171.091(c) also indicate that motions to modify, to vacate, and to correct an arbitration award should be heard either before or simultaneously with motions to confirm the award." Id. Finally, the TAA provides that "a judgment confirming (or modifying or correcting) an arbitration award is a final judgment like any other." Id.
B. Application of Law to the Facts
Appellant raises two issues complaining the trial court erred in "not modifying the arbitration holding." According to appellant, the trial court erred by denying its "Motion for New Trial and Motion to Modify Arbitration Holding" because: (1) there was an evident miscalculation by the arbitrator, and (2) the arbitrator "exceeded his authority in assessing RCC's legal fees and arbitration costs against Appellant who should have been found to be the prevailing party." RCC contends the trial court did not err because the trial court had no discretion but to deny appellant's "Motion to Modify Arbitration Holding" since appellant did not file its motion before the trial court ruled on RCC's "Motion to Lift Abatement and Application to Confirm Arbitration Award." We agree with RCC on this point.
The threshold question is whether appellant timely filed a motion to vacate or modify the arbitration award. The parties agree the TAA applies. Under the TAA, "[a] motion to vacate, to modify, or to correct an arbitration award must be raised or considered before or simultaneously with a motion to confirm the award." Hamm, 178 S.W.3d at 269. Further, "a party that moves to vacate, to modify, or to correct an arbitration award, and adduces evidence in support, only after the award has been confirmed and final judgment rendered has waived that challenge—or, at least, a trial court does not abuse its discretion if it overrules such a post-judgment motion." Id. at 268.
RCC filed a motion to confirm the arbitration award in the trial court on March 8, 2016. Appellant was aware of the filing of this motion, had an opportunity to challenge the award, and failed to do so. While appellant filed a "Claimant's Motion to Correct Award" with the AAA on March 16, 2016, before the trial court confirmed the arbitration award, appellant did not challenge the arbitration award in the trial court until after the award was confirmed and final judgment rendered. Cf. Sydow v. Verner, Liipfert, Bernhard, McPherson & Hand, Chartered, 218 S.W.3d 162, 171 (Tex. App.—Houston [14th Dist.] 2007, no pet.) (court concluding appellant did "timely place[] the issue of prejudgment interest before the court when he applied to have amended award confirmed (and when he responded to [the appellee's] application to confirm the original award)," despite also filing a motion to reconsider in the arbitration forum); Brown v. Potter Concrete Residential, Ltd., No. 05-13-00585-CV, 2014 WL 2993809, at *2 (Tex. App.—Dallas June 30, 2014, pet. denied) (mem. op., not designated for publication) ("Although the Browns did not specifically move to vacate the award, they did file a response arguing the applications to confirm should be denied.").
On this record, we conclude the trial court did not abuse its discretion by denying appellant's untimely "Motion for New Trial and Motion to Modify Arbitration Holding."
III. Conclusion
For the foregoing reasons, we decide each of Appellant's issues against it. The trial court's judgment is affirmed. 160509F.P05
/Douglas S. Lang/
DOUGLAS S. LANG
JUSTICE
JUDGMENT
On Appeal from the 193rd Judicial District Court, Dallas County, Texas
Trial Court Cause No. DC-14-11847.
Opinion delivered by Justice Lang. Justices Fillmore and Schenck participating.
In accordance with this Court's opinion of this date, the judgment of the trial court is AFFIRMED.
It is ORDERED that each party bear its own costs of this appeal. Judgment entered this 15th day of August, 2017.