Pryor v. Bass

Supreme Court of Florida, en Banc
Jun 2, 1953
65 So. 2d 45 (Fla. 1953)

Opinion

April 14, 1953. Rehearing Denied June 2, 1953.

Appeal from the Circuit Court, Okaloosa County.

Fisher Hepner, Pensacola, for appellants.

John B. Amos, Fort Walton, and Yonge, Beggs Lane, Pensacola, for appellee.


William C. Pryor and wife, appellants here, entered into a contract with Theodore Bass, the appellee, to construct for them a home in Fort Walton, Florida. The specifications and drawings for the house had been planned originally for Mr. and Mrs. Charles H. Pease of Indiana. The Pease specifications did not entirely meet the needs of the appellants, in that the standard of construction required reached a cost not acceptable to them. Certain modifications were made, after which the drawings, specifications and modifications were made a part of the contract calling for the construction of the house for the price of $20,000. During the course of construction, numerous changes were requested by the appellants, which resulted in additions and deletions. At one time during the course of construction, the contractor — apparently because of what he considered unreasonable change orders — abandoned the job and testified that he did not return and complete the job until the owners agreed that he would be paid the cost involved in the change orders, plus 15 percent for supervision and profit.

Certain advancements were made by the owners during construction; and upon completion the balance of the contract price of $20,000 was paid in full. Subsequent to the final payment by the owners, the Modern Flooring Company filed a lien against the job in the amount of $1,774; and in order to protect the property against foreclosure of the lien and upon advice of counsel, the owners paid Modern Flooring Company $1,700. This last item brought the total payments by the owners to an aggregate of $21,700.00.

The contractor then presented his claim for extras in the amount of $7,659.52, which included his claim of $999.03 for profit and supervision on the extras. The owners admitted liability for a few of the extras, but denied liability as to most of them, and contended that the prices charged were exorbitant. They contended also that many of the items called for in the drawings and specifications had been omitted and that they were entitled to payment for such omissions.

The parties being unable to adjust their differences, the appellee-contractor, who was plaintiff below, instituted this suit in chancery to enforce collection of his alleged balance, contending that the contract had been abandoned and completely abrogated and that he was entitled to settlement on a quantum meruit basis, and, in the alternative, that he was entitled to the contract price of $20,000.00 plus his claim of $7,659.52 for extras ordered by the owner. The owners filed an answer and counterclaim, in which they denied that certain of the items were extras and contended that the charges were excessive. The owners also set up in their answer and counterclaim the necessary payment of $1,700.00 to Modern Flooring Company and alleged damages of $2,500.00 to their property because of faulty construction.

The cause came on for trial before the Chancellor, who heard the testimony. There were numerous conflicts in the testimony as to the value of the extras put into the job by the contractor and the value of the omissions and substitutions by the contractor. At the conclusion of the evidence, the court entered its decree which, except for the enforcement provision, was in the following form:

"This cause coming on for final hearing upon bill of complaint, answer, incorporating a set-off or counterclaim, the testimony and briefs of counsel, and the court having considered the same finds for the plaintiff and that the defendants are indebted to him on account of the matters and things alleged in the bill in the sum of $3,547.74, for which he is entitled to a lien upon the the property described in the bill, to wit: * * *." (The emphasis is supplied.)

Concurrently with the filing of the final decree, the Chancellor also filed what he identified as a memorandum in support of the decree and which was in the following language:

"The only real dispute between the parties appears to be as to the extent and value of the alterations required from time to time during the construction of the building. Defendants do not deny — on the contrary they admit — that several of the alterations specified by the plaintiff in his claim were made; that they were deviations from the original plans and that it was agreed that plaintiff would be paid therefor the costs (material and labor) plus 15%. It is clear that the defendants recognized that plaintiff had a just claim for some amount. When they could not agree and plaintiff filed his claim which they considered exorbitant they countered with an off-set or counterclaim which the court is constrained to hold has not been supported by the evidence. The decree is for an amount which the court finds from the evidence to be just and equitable."

It is obvious from a reading of the final decree and memorandum supporting it that the Chancellor held the contract to be in full force and effect and allowed the contractor the sum of $3,547.74 for "the matters and things alleged in the bill." Although the value of such extras was highly controversial, it was a determination of fact made by the Chancellor who heard the witnesses, and the cases are legion which hold that this court will not disturb such findings, where amply supported by evidence in the record. Lovett v. Peoples First Nat. Bank of Quitman, 130 Fla. 142, 178 So. 124; Nolen v. Nolen, 121 Fla. 130, 163 So. 401.

It should be noted, however, that in the memorandum supporting the decree, the court commented: "When they could not agree and plaintiff filed his claim which they considered exorbitant, they countered with an off-set or counterclaim which the court is constrained to hold has not been supported by the evidence." (Emphasis is supplied.) During the progress of this appeal, and pursuant to an order of this court, the Chancellor enlarged upon this memorandum opinion by stating specifically that "* * * the item of $1,700 paid by the defendants [was] disallowed." This was error. The owners alleged in their answer and counterclaim that the contractor had allowed a lien by the Modern Flooring Company to be filed and that it was necessary for them to pay $1,700 to extinguish this lien. William C. Pryor, one of the owners, testified positively that he paid Modern Flooring Company the sum of $1,700, and such testimony was never disputed nor denied by the contractor. Chancellors are accorded a broad range of discretion in settling the conflicts in testimony. But where, as here, the allegation of payment of the sum of $1,700 is not denied in the pleadings and where there is clear, positive, convincing and undenied testimony that such a sum was paid by the owners to settle a bill owed by the contractor for the flooring in the property, the proof was so clear and convincing that it was error to ignore it.

For the reasons stated, the decree should be modified by crediting the counterclaimed item of $1,700, leaving a balance due of $1,847.74.

As modified, the decree is affirmed.

ROBERTS, C.J., and TERRELL, THOMAS, SEBRING, HOBSON, and MATHEWS JJ., concur.

DREW, J., dissents.


The Chancellor below heard all of the evidence. As I read and understand his original memorandum, as well as the memorandum filed here during the progress of the appeal, he struck a balance which he felt, after weighing all the evidence, represented, as near as possible, the amount remaining due. I feel that this is the type of a case where we should not disturb the findings of the Chancellor.


Summaries of

Pryor v. Bass

Supreme Court of Florida, en Banc
Jun 2, 1953
65 So. 2d 45 (Fla. 1953)
Case details for

Pryor v. Bass

Case Details

Full title:PRYOR ET UX. v. BASS

Court:Supreme Court of Florida, en Banc

Date published: Jun 2, 1953

Citations

65 So. 2d 45 (Fla. 1953)