Opinion
3:11-cv-00346-HDM-WGC
01-29-2014
FINDINGS OF FACT AND
CONCLUSIONS OF LAW;
ORDER
This case was tried before the court sitting without a jury commencing November 18, 2013. The court has considered the testimony of the witnesses, the exhibits introduced during trial, and the arguments of counsel and with good cause appearing finds and concludes as follows:
FINDINGS OF FACT
1. During January of 2004, IGT entered into an Industrial Lease Agreement (hereinafter "Lease") with DP Industrial, LLC under the terms of which IGT leased 100,800 square feet of industrial space located at 1150 Trademark Drive, Suite 102, Reno, Nevada, from Dermody Properties. IGT was to use the premises for storing slot machines and other related equipment and the Lease was set to expire on February 27, 2008.
2. During May of 2005 the Lease was amended and extended through June 30, 2008 and incorporated an additional 36,000 square feet of space.
3. The Lease was assigned to Prologis by Dermody Properties during July of 2007.
4. Subsequent to the assignment of the Lease to Prologis, IGT and Prologis entered into negotiations to extend the Lease. The extension was incorporated in a Second Amendment to the Lease (hereafter "Second Amendment"). Robert Stecker negotiated on behalf of IGT and Travis Durfee negotiated on behalf of Prologis.
5. The relevant portion of the Second Amendment related to an early termination option. IGT proposed that the Lease contain an early termination option along with an extension of the term of the Lease for an additional five years. IGT proposed the extended term in order to obtain a lower rental rate. Mr. Stecker proposed the early termination option and requested that it be included in the Second Amendment. The evidence established that IGT wanted the early termination option so it would have the ability to move out early in the event it was able to secure space at another location where IGT had existing facilities. This was an important provision to IGT. Prologis was reluctant to have the early termination included in the Lease but ultimately agreed to the extension and the early termination provision. The relevant language is as follows:
"Provided no event of default shall then exist and no condition shall then exist which with the passage of time or giving of notice or both would constitute an event of default, Tenants shall have the right at any time on or before May 1, 2010, to send Landlord written notice (the "Termination
Notice") that Tenant has elected to terminate this lease effective on June 30, 2010.
If Tenant elects to terminate this Lease pursuant to the immediately preceding sentence, the effectiveness of such termination shall be conditioned upon Tenant paying to Landlord $370,560 contemporaneously with Tenant's delivery of the Termination Notice to Landlord. Such amount is consideration for Tenant's option to terminate and shall not be applied to rent or any other obligation of Tenant. Landlord and Tenant shall be relieved of all obligations accruing under this Lease after the effective date of such termination but not any obligations under the Lease prior to the effective date of such termination." (Trial Exhibit 6).
6. Both Prologis and IGT are large sophisticated corporations with legal departments. The Second Amendment was adopted after it was reviewed by Prologis' legal department and IGT's legal department. Mr. Stecker was aware of the terms of the early termination provision including the obligation to send such notice in writing and contemporaneously paying the $370,560.00 because he was involved in drafting the provision and specifically requested the provision on behalf of IGT.
7. The Second Amendment to the Lease was adopted on June 9, 2008.
8. The Lease during all relevant times expressly contained a provision that "time is of the essence of each term and provision of this Lease." This is contained in Section 38.04 of the original Lease. The termination option described above was subject to the "time is of the essence" provision.
9. IGT's representative, in all of these negotiations as to all matters involving the construction and implementation of the terms of the Lease and the Second Amendment, was Mr. Stecker. He was fully aware that under the terms of the Lease the notice and payment were due on or before May 1, 2010 and the notice had to be given in writing and time was of the essence.
10. During February or March of 2010, Mr. Stecker contacted Mr. Durfee and verbally advised him that IGT was going to elect to terminate the Lease effective on June 30, 2010. While Mr. Stecker offered to tender the written termination notice he was not prepared on behalf of IGT to send the $370,560.00 termination payment along with the termination notice at that time. Mr. Stecker testified that he was not prepared to tender the termination fee as IGT did not wish to make the payment until closer to the May 1, 2010 date. The court is persuaded from the evidence that IGT made a deliberate decision to hold the early termination notice and the payment so that it could collect additional interest on the money.
11. Mr. Durfee, on behalf of Prologis, after receiving the verbal communication from Mr. Stecker advised Brandon Page, Prologis' Market Officer, that IGT was planning to exercise its termination rights. Mr. Durfee also advised Mr. Stecker that he should not send the written termination notice until he was prepared to tender the payment as required by the terms of the Lease as amended.
12. As a consequence of the verbal representation that IGT planned to vacate the premises within a few months, Mr. Page directed the property manager to send a standard move-out form letter to IGT. This was accomplished on March 11, 2010. This is the same move-out letter which Prologis sends to every tenant prior to the end of a lease. The court specifically finds and concludes that this form letter did not constitute any acknowledgment or acquiescence or agreement by IGT that a verbal notice of IGT's intention to exercise its early termination option would replace the requirement of a written termination notice together with the early termination payment.
13. It is clear that by early March, 2010, IGT had made the decision that it was going to terminate the Lease early and was committed to terminating the Lease regardless of any actions taken by Prologis. Edwin Strickland was designated by IGT to manage all aspects of the construction and demolition work that would be required by IGT to leave the Prologis property. He worked with Prologis employees in the Spring of 2010 to prepare demolition plans for the tenant improvements that IGT had made to the Prologis property.
14. On March 11, 2010, Prologis' Property Manager Alisa Weber sent IGT a pending move-out checklist. One of the things the move-out checklist provided for was a preliminary inspection of the property. It also provided IGT with a number of tasks that were going to be required to be performed in advance of the Lease expiration date including making various repairs to the property and turning over the keys to the property to Prologis.
15. Prior to May 12, 2010, IGT and Prologis participated in two inspections of the premises in anticipation of the move-out. The termination notice was not discussed during the inspections. Prologis had an obligation under the terms of the Lease to facilitate IGT's move-out and re-letting of the premises and Prologis' participation in the move-out discussions were strictly pursuant to the non-binding oral indications by IGT that it intended to vacate the premises early.
16. On April 22, 2010, IGT provided Prologis with its tenant improvement drawings of the offices IGT constructed at the leased premises.
17. Through no fault of Prologis, IGT negligently failed to provide Prologis with the written notice of termination or with the $370,560.00 specified in the Second Amendment to the Lease on or before May 1, 2010.
18. On May 5, 2010, Prologis returned the drawings to IGT along with a tentative demolition plan. At that time, Prologis was unaware that IGT had failed to tender its written termination notice or the termination fee on or before May 1, 2010 as required for early termination under the terms of the Lease.
19. It was not until May 11, 2010, that Mr. Stecker, on behalf of IGT, realized he had missed the May 1, 2010 deadline because he had "forgotten the date". He testified that it was a mistake on his part to fail to comply with the express terms of the Lease and tender the money and the written notification of termination.
20. Mr. Stecker notified Mr. Durfee that he had made a mistake in not complying with the deadline for early termination in accordance with the terms of the Lease. He did so after he had spoken with his supervisor, Mr. Ciorciari.
21. When Mr. Stecker spoke with Mr. Durfee about the failure to execute the early termination in accordance with the Lease he advised Mr. Durfee that IGT would send the payment and written notice to Prologis the following day. Mr. Durfee indicated to Mr. Stecker that while he was surprised at the missed deadline he needed to confer with his superiors and that Mr. Stecker should not deliver the written notice and payment until he had an opportunity to review the Lease and consult with management.
22. On May 12, 2010, Mr. Stecker prepared a letter to Prologis in which he stated that the letter represented "formal notification" that IGT was exercising its early termination option. Mr. Stecker intended that this letter be the written notification under the Second Amendment as no previous written termination notification had been given by IGT to Prologis. That letter was never sent to Prologis. Instead on May 12, 2010, Mr. Strickland emailed Mr. Durfee seeking direction on certain demolition issues in an effort to keep the demolition work on schedule and "as painless as possible."
23. Mr. Stecker sent Mr. Durfee an e-mail on May 14, 2010 offering to have IGT's written notice and payment delivered to Prologis until Prologis could come to a decision. Mr. Durfee advised Mr. Stecker to hold the notice and payment because he could not accept them until a decision had been made by Prologis' management.
24. Mr. Stecker acknowledged that he had not calendared the deadline and he did not know of anyone else within the IGT organization who had calendared the deadline for giving written notification and the payment pursuant to the terms of the Lease.
25. The evidence showed that Mr. Stecker had signed copies of the Lease as did IGT's legal department and compliance department. The testimony established that IGT did not have a routine procedure or methodology for calendaring deadline dates like the termination notice contained in the Lease.
26. At no time did any representative of Prologis ever lead Mr. Stecker to believe that he did not need to send a formal written termination notice in accordance with the terms of the Lease. And, at no time did any representative of Prologis ever lead Mr. Stecker to believe that he was not required to tender the payment in the amount required under the Lease prior to the May 1, 2010 deadline.
27. On May 19, 2010, IGT's legal department prepared a letter which was hand-delivered to Prologis on May 19, 2010 providing written notification of IGT's desire to terminate the Lease.
28. While the letter uses the language "previous notices" of termination, the evidence is clear that the only notification was a verbal notification substantially in advance of the May 1, 2010 deadline without compliance with the written requirements of notification and the tender of payment for the amount required for early termination.
29. On May 24, 2010, Mr. Strickland called Mr. Durfee about the demolition. At that point in time IGT clearly intended to vacate the premises regardless of what Prologis did or did not do in connection with the move-out of IGT. IGT had already prepared office space and warehouse space on its own premises and intended to vacate the premises notwithstanding the dispute involving the early termination provisions of the Lease.
30. On May 24, 2010, Mr. Durfee advised IGT that Prologis was not accepting IGT's late termination and was not required to give any direction to proceed with demolition and move-out of IGT as Prologis determined that IGT had not exercised its early termination right in accordance with the provisions of the Lease. IGT was advised by Prologis that it might want to leave the space as-is in case a sub-tenant could use the additional tenant improvements. Although this is disputed, the court is persuaded that Mr. Strickland advised Prologis that IGT would proceed with demolition of all the tenant improvements unless Prologis consulted with IGT in connection with the move-out. This finding is consistent with the fact that IGT intended to vacate the premises notwithstanding its negligent conduct in failing to timely exercise the early termination option.
31. Prologis then proceeded to assist IGT in connection with the move-out but did so after expressly indicating that it was not waiving its rights under the terms of the Lease and that Prologis would continue to enforce its rights under the terms of the Lease.
32. Although IGT clearly understood that Prologis continued to assert that IGT was not properly vacating the premises and had not complied with the terms for early termination, IGT nevertheless proceeded to take the necessary steps to vacate the premises.
33. On May 25, 2010, Prologis sent a letter to IGT returning the check reflecting the payment to IGT and IGT received the check on May 26, 2010. The letter stated that "IGT did not properly exercise its termination option" and "the Lease remains in place."
34. On May 27, 2010, Prologis sent IGT an e-mail stating that "Section 42.01 of the First Amendment to Lease, at termination, allows Landlord, at its election, to require IGT to remove all of the Tenant Improvement finished office space at IGT's expense." In that letter, Prologis advised IGT "that the Lease between the two parties has not been terminated, so landlord is not legally required at this time to make any election as to the removal of tenant improvements."
35. Nevertheless, Prologis continued to attempt to accommodate IGT in the move-out and assist in preparing the premises for re-letting.
36. The court finds and concludes that these actions of Prologis were undertaken in an effort to mitigate any potential damages because IGT intended to vacate the premises notwithstanding the notifications by Prologis that IGT had failed to comply with the Lease and was legally bound for the remaining term of the Lease. Prologis then proceeded to identify those improvements which it desired to have remain on the premises. Again, Prologis expressly reserved all of its rights under the Lease.
37. On May 27, 2010, in its e-mail, Prologis stated "both this e-mail and Prologis' demolition suggestions shall in no way be construed as a waiver of any of landlords legal and contractual rights under the Lease Agreement . . . "
38. There is no doubt in the court's mind that IGT and its representatives fully understood that at the time they were vacating the premises in late May, 2010, Prologis reserved all of its rights under the terms of the Lease.
39. IGT then proceeded with its demolition work starting on June 7, 2010 and completed the work on June 23, 2010.
40. IGT paid $97,152.00 to demolish its tenant improvements. Even if IGT had occupied the premises for the remainder of the Lease it would have had this obligation to remove the tenant improvements.
41. On June 23, 2010, IGT requested a final inspection to confirm that no construction issues remained.
42. During the period May 1st to May 26th, 2010, IGT completed a substantial portion of the move of its warehouse property from the Prologis space to IGT's campus on Prototype Drive.
43. At that point in time Prologis reasonably determined that regardless of what it did or did not do, IGT intended to vacate the premises and move all of its operations to its facility on IGT's campus. The demolition work on the premises was reasonably undertaken by both Prologis and IGT in order to mitigate damages in response to IGT's insistence on leaving the property in breach of the Lease even though it had not complied with the provisions of the Lease for early termination.
44. On June 24, 2010, Prologis participated in the final inspection of the premises and IGT left the premises on or before June 30, 2010, on which date IGT changed the locks and IGT no longer had access to the building.
45. Thereafter IGT failed and refused to pay any rent or other payments as they came due under the terms of the Lease commencing July 1, 2010 and continuing until June 30, 2013, the termination date of the Lease.
46. On July 14, 2010, Prologis initiated a summary eviction action under the provisions of Chapter 40 of the Nevada Revised Statutes for IGT's non-payment of the July rent. IGT filed a tenant affidavit on July 21, 2010, contesting Prologis' eviction notice. IGT had no intention of possessing the premises and Prologis re-entered the premises and attempted to secure a replacement tenant. The eviction action was then dismissed by Prologis.
47. On December 6, 2010, Prologis was able to secure a replacement tenant, Laco, Inc., for 36,000 square feet of the premises vacated by IGT.
48. Prologis then continued to attempt to re-let the balance of the premises. In so doing, Prologis advertised the listing on LoopNet, which is an on-line listing service for commercial and industrial properties, and in brochure materials which were mailed to parties who made inquiries. Prologis also communicated with various brokers, discussed the premises by word-of-mouth, and posted a generic "notice of property available for lease" on Prologis' property. Prologis also received and considered proposals from potential tenants and prepared counter proposals. Prologis provided IGT with the names of brokers who could assist in locating possible sub-tenants and attempted to accommodate any request by IGT to conduct tours of the premises with potential sub-tenants.
49. Prologis was unable to secure a replacement tenant for the balance of the property.
50. IGT did not undertake any efforts to find a replacement tenant after it left the property on June 1, 2010.
51. Prologis has suffered damages as a result of IGT's failure to comply with the terms of the Lease and is entitled to recover those damages in accordance with the terms of the Lease. Those damages, as of November 18, 2013, amounted to $2,531,299.00 after credit is given for IGT's security deposit, and the rent and other charges received from Laco. This sum represents unpaid base rent in the amount of $1,844,160.00, operating costs in the amount of $413,312.00 (this represents a 10% reduction as a result of testimony that created some ambiguity as to actual costs), system replacement fees in the amount of $64,022.00, accrued interest in the amount of $566,204.00, the TI allowance for Laco in the amount of $38,362.00; brokerage commission for Laco in the amount of $19,972.00 (the sum of $9,836.00 paid to in-house brokers has been deducted). No allowance has been made for the repairs that were not made and IGT has been given credit for the deposit in the amount of $40,911.00. Interest will accrue at the contract amount from November 18, 2013 until the date of judgment and thereafter at the rate provided by law. The contract also provides for the prevailing party to recover attorneys' fees and costs.
CONCLUSIONS OF LAW
1. Prologis is a corporation organized under the laws of Delaware and has its principal place of business in Colorado.
2. IGT is a corporation organized under the laws of the State of Nevada and has its principal place of business in Nevada.
3. This court has jurisdiction pursuant to 28 U.S.C. § 1332 and venue properly lies in the district of Nevada.
4. The lease entered into by Prologis and IGT specifically provides that it is to be governed by and construed in accordance with the laws of the State of Nevada.
5. Because the court is exercising diversity jurisdiction, Nevada substantive law governs this action. Erie R.R. Co. v. Thompkins, 304 U.S. 64, 78 (1938); Nitco Holding Corp. V. Boujikian, 491 F.3d 1086, 1089 (9th Cir. 2007).
6. In determining the intent of the parties the court looks to the plain language of the contract. If the contract is clear the court will enforce the provisions even if the application of those conditions seems harsh or unfair. Cummings v. Bullock, 367 F.2d 182, 186 (9th Cir. 1966).
7. The dispute that resulted in this litigation involves the failure of IGT to comply with the early termination provision contained in the Lease. That provision states:
Tenant shall have the right at any time on or before May 1, 2010 to send Landlord written notice (the "Termination Notice") that Tenant has elected to terminate this Lease effective on June 30, 2010.
If Tenant elects to terminate this Lease pursuant to the immediately preceding sentence, the effectiveness of such termination shall be conditioned upon Tenant paying to Landlord $370,560.00 contemporaneously with Tenant's delivery of the Termination Notice to Landlord. (Trial Exhibit 6).
8. In addition the Lease explicitly provided in Section 38.04 that time is of the essence in the performance of its terms. Therefore, IGT was required to provide Prologis with written notice of its intention to exercise its early termination option, contemporaneously with payment in the amount of $370,560.00 on or before May 1, 2010.
9. It is undisputed that IGT did not deliver its written Termination Notice and payment to Prologis on May 1, 2010. Under the express terms of the contract IGT failed to comply with the terms of its early termination option. Because IGT failed to exercise its right in a timely manner it lost its right to terminate the Lease early and therefore IGT's lease obligations continued through the end of the stated lease term, that is June 30, 2013.
10. If a lease option provides a tenant with a unilateral option and time is of the essence in such an option contract the tenant is required to strictly comply with the terms of the option. G.S. Johnson Co. v. Nevada Packard Mines Co., 272 F. at 291, 296 (D.Nev. 1920); McCall v. Carson, 172 P.2d 171, 185 (Nev. 1946). Substantial compliance is not sufficient. White v. Miller, 518 S. W. 2d 383, 385 (Tex. Ct. App. 1974) (timely verbal notice insufficient where option required written notice). Exact compliance with an option contract's terms is stringently enforced. Cummings v. Bullock, 367 F.2d 182, 186 (9th Cir. 1966). In discussing the substantial compliance doctrine the Nevada Supreme Court has held as follows:
The optionor, before acceptance by the optionee, is bound only to the extent that he has expressly agreed to be bound. The obligation on his part is a mere offer, requiring unconditional acceptance in order that a contract may be created. If it were construed otherwise, an optionee could change the time specified for the payment of money, or impose conditions not contemplated by the parties at the time the agreement was entered into, and thereby, without the optionor's consent, foist a so-called contract upon him to which he had not agreed. Fundamentally, the law of contracts does not permit this, as there must be mutuality of consent to all the provisions - a meeting of the minds - in order that a contract may be created.McCall, 172 P.2d at 185; see also Cummings, 367 F.2d at 186.
11. These same rules apply to early termination options in commercial leases. Loitherstein v. IBM, 413 N.E.2d 1146 (Mass. App. Ct. 1980) (where sophisticated parties carefully chose clear option language, landlord properly rejected tenant's attempted early termination where notice of termination was 23 days early, but termination fee was 5 days late).
12. Here both Prologis and IGT are sophisticated parties. They both have legal departments. The early termination provision was added to the Lease for the benefit of IGT and IGT clearly understood its legal obligations to exercise the early termination provision in writing with a simultaneous payment of $370,560.00.
13. While IGT seeks equitable relief from the court for missing the option deadline, Nevada law does not permit such relief under the circumstances of this case. The Nevada Supreme Court has held that equity will not intervene to protect a lessee from its own negligent failure to give the required written option notice. Host International, Inc. v. Summa Corp., 583 P.2d 1080 (Nev. 1978). See also Holmby, Inc. v. Dino, 647 P.2d 392, 393-94 (Nev. 1982).
14. The language of the termination option is clear and unambiguous. IGT was entitled to terminate the Lease only if it provided written notice of its election on or before May 1, 2010 and contemporaneously with the written termination notice tendered the termination fee of $370,560.00 to Prologis. Early verbal notification of the termination was insufficient as a matter of law to exercise the early termination provision. In addition, it is clear that the fault for failing to give the notice was clearly IGT's negligence and the motivation for not tendering the $370,560.00 was IGT's business decision to retain the funds so they could draw interest beneficial to IGT.
15. Equity will not intervene to protect the lessee from its own negligent failure to give the required written notice. Host, 583 P.2d at 1082. Therefore, IGT's argument of substantial compliance is unavailing under the facts of this case.
16. As an affirmative defense IGT argues that Prologis waived its right to enforce the early termination provision under the Lease. IGT bears the burden of proving an existing right, a knowledge of its existence, and an actual intention to relinquish it or conduct so inconsistent with the intent to enforce the right as to induce a reasonable belief that it has been relinquished. Baroi v. Platinum Condo Development, LLC, No. 2:09-cv-00671, 2012 U.S. Dist LEXIS (D. Nev., 2012). Further, a waiver is not effective unless done with full knowledge of all its material facts. In addition, to prove waiver by conduct, which is the theory advanced by IGT, Prologis' conduct must be so manifestly consistent with an intent to relinquish voluntarily a particular right that no other reasonable explanation of one's conduct is possible. In re Spats Restaurant & Saloon, 64 B.R. 442, 446 (Bankr. D. Nev. 1986).
17. The court concludes that Prologis did not waive strict compliance with the Second Amendment to the Lease when Mr. Durfee advised Mr. Stecker in March of 2010 that he should not send the termination notice until he also sent the termination fee precisely in accordance with the clear language of the Second Amendment. This unequivocally established that Prologis was insisting on strict compliance with the terms of the option. Therefore, Mr. Stecker's March 2010 verbal inquiry was not a proper exercise of the termination option. The verbal inquiry was legally insufficient to satisfy the requirements of the early termination option.
18. In addition, the court concludes that Prologis did not intend to nor did it ever waive strict compliance with the terms of the option when it conducted inspections of the premises, provided demolition instructions to IGT and commenced efforts to market the premises prior to May 1, 2010. Prior to that date and because of IGT's verbal indication that it expected to exercise its option for early termination, Prologis had a reasonable expectation that IGT would eventually, prior to May 1, 2010, provide the timely termination option and payment in accordance with the provisions of the Lease. The conduct of Prologis prior to the May 1, 2010 deadline was consistent with reasonable business practices to prepare for the termination in the event compliance with the written termination was provided by IGT. Such conduct did not constitute an intention to waive rights nor did it induce a reasonable belief in IGT that Prologis was waiving its right to require strict compliance with the early termination provisions of the Lease.
19. In addition, the court concludes that when Prologis returned the tentative demolition plans to IGT on May 5, 2010 and conducted the inspection on May 7, 2010, after the May 1, 2010 deadline, such conduct was undertaken as a result of the mistaken belief by Prologis that IGT had complied with the written notice requirements. Prologis as a commercial landlord had no legal obligation to notify IGT of the pending or missed option deadline. See Warminster Equities, LLC. Warminster Commerce, LLC, No. 11-3238, 2012 U.S. App. LEXIS 19645 (3d Cir. Sept 19, 2012). There was no requirement in the Lease that Prologis had any duty to notify IGT of noncompliance with the early termination provisions or the payment of the termination fee. The court concludes that these actions of Prologis were not intended as a waiver of any of Prologis' rights under the Lease in relation IGT's early termination option. The court concludes that this conduct did not constitute an express or implied waiver and does not warrant equitable relief.
20. The conduct of Prologis in late May of 2010 in providing IGT with direction on what tenant improvements to leave on the premises, inspecting the premises and providing input on the demolition work did not constitute a waiver. IGT made it very clear to Prologis, even though it missed the May 1, 2010 deadline for exercising the early termination, that it intended to vacate the premises and abandon the Lease because it had constructed facilities on its own campus and that it was therefore going to move regardless of Prologis' conduct. IGT clearly understood from both written and verbal communications by Prologis that Prologis intended to enforce its rights under the express terms of the Lease. Under such circumstances it was not unreasonable for Prologis to work with IGT in restoring the premises to a condition where Prologis would be able to make reasonable efforts to re-let the premises to another tenant once IGT vacated the property. Prologis had a reasonable concern that if it did not provide direction to IGT, IGT would simply remove all of the improvements and leave the premises in a condition that would make it more difficult for Prologis to attempt to mitigate its damages by re-letting the property. Prologis had an obligation under the Lease to act in good faith in cooperating with IGT and had a further obligation to undertake a reasonable good faith effort to mitigate its damages under both the provisions of the Lease and the provisions of NRS 118.175.
21. Under the facts presented during the trial the court is persuaded that it was IGT, not Prologis, who insisted on the move-out and on demolition direction from Prologis, because IGT intended to vacate the premises even though it had negligently failed to comply with the provisions of the early termination section of the Lease.
22. For these reasons, the court specifically finds and concludes that the evidence established that Prologis' post-May 1, 2010 conduct does not support a finding of waiver, either express or implied. Prologis cooperated with IGT in connection with the demolition work in order to mitigate its damages by helping to restore the facility to a condition that would maximize the marketability of the property and enhance the prospect of securing new tenants once the property was vacated by IGT. The Lease provides that nothing undertaken by Prologis to mitigate damages shall waive Prologis' right to recover damages against IGT. Sections 20.01 and 20.03. It further provides that "whether the premises or any part thereof is a re-let" IGT shall remain liable under the Lease. Section 20.03 (B). Here Prologis had a duty to make reasonable efforts to re-let once it understood that IGT was going to vacate the premises even though it had been advised not to do so because of the failure to comply with the early termination provision. The remodeling and re-letting efforts did not constitute a waiver of Prologis'rights to reject the late tender by IGT of the payment and written termination notice. Accordingly, the court concludes there was no express or implied waiver of the early termination provisions of the Lease by Prologis during any of its pre- or post-May 1, 2010 conduct. At all times Prologis reserved its rights under the Lease and expressly disclaimed an intention to waive any rights in all of its communications with IGT. Nor did Prologis' conduct for the reasons set forth above support IGT's defense of estoppel, breach of the covenant of good faith and fair dealing, or surrender and acceptance. Therefore the court concludes that IGT has failed to meet its burden in establishing an entitlement to recover on its defenses of substantial performance, waiver, estoppel, breach of the covenant of good faith and fair dealing, and surrender and acceptance.
23. Finally the court concludes that Prologis used reasonable efforts to mitigate its damages. Prologis was able to secure a replacement tenant (Laco) for a portion of the premises within approximately six months of IGT's abandonment of the property. The only evidence provided at trial relating to the reasonableness of Prologis' mitigation efforts was evidence provided by Prologis. IGT offered no evidence, such as expert testimony, that the efforts of Prologis in attempting to secure new tenants fell below the standard of reasonableness. IGT had an obligation to show that Prologis' mitigation efforts were unreasonable. The efforts undertaken by Prologis to re-let the premises included listing the premises on the commercial MLS service, providing mass e-mailings to local brokers, using in-house brokers, and submitting brochures and erecting business park signage. Those were the usual and customary steps Prologis took on a regular basis to lease its other properties. These were reasonable and customary steps in the commercial marketplace. Therefore, the court concludes that Prologis took reasonable mitigation steps in an effort to re-let the premises after the premises were vacated by IGT. While it might have been preferable to hire an outside broker, there is no indication in the record that doing so would have assisted in the re-letting of the premises, particularly in the severely depressed commercial real estate market that existed at the time. In addition, the fact that Prologis was able to secure a new tenant for a portion of the property provides further support for the conclusion that Prologis used reasonable efforts to re-let the premises.
24. On the issue of damages the court finds and concludes that Prologis is entitled to recover damages against IGT as set forth in the Lease from the time that IGT left the premises until the expiration of the Lease on June 30, 2013.
25. The court finds that IGT's failure to properly exercise its termination option resulted in the Lease continuing through June 30, 2013. IGT continued to owe rent under the terms of the Lease and was otherwise obligated to comply with the terms of the Lease through the end of the term on June 30, 2013. Therefore, Prologis is entitled to a declaratory judgment that IGT failed to comply with the required conditions for exercising its termination option and therefore the option was not properly exercised; that the Lease continued as a valid and enforceable contract on and after July 1, 2010 such that IGT continued to owe the rentals and other charges under the Lease through June 30, 2013. The total sum owed under the terms of the Lease by IGT to Prologis through the end of the Lease term was in the amount of $2, 531, 299.00. (See Paragraph 52 of the court's Findings of Fact).
26. The court also finds and concludes that IGT breached the Lease by failing to properly exercise the early termination provision and by failing to pay the rent and other charges after July 1, 2010. The Lease obligated IGT to pay all rent and obligations in a timely manner. IGT failed to pay any rent or other charges after July 1, 2010.
27. Prologis properly notified IGT of its breach and IGT refused to take any corrective action.
28. Prologis performed all of its obligations and satisfied all of its conditions under the Lease.
29. Prologis made reasonable efforts to mitigate its damages once IGT left the premises.
30. IGT has failed to carry its burden on any of its defenses to Prologis' claims.
31. As a consequence of IGT's breach of the Lease, Prologis suffered damages and is entitled to an award of damages for breach of contract in the amount of $2,531,299.00 (reflecting damages through November 18, 2013). These damages shall bear interest in the contract amount from November 18, 2013 until the date of entry of judgment and thereafter at the rate provided by law. (See Paragraph 52 of the court's Findings of Fact).
As a general rule, in diversity actions, state law determines the rate of prejudgment interest and post-judgment interest is governed by federal law. Citicorp Real Estate, Inc. v. Smith, 155 F3d 1097 (9th Cir. 1998). See 28 U.S.C. § 1961. An exception to § 1961 exists when the parties contractually agree to waive its application. Fid. Fed. Bank, FSB v. Durga Ma Corp., 387 F3d 1021, 1023 (9th Cir. 2004). Here the Lease does not include a provision reflecting any intent of the parties to waive the application of § 1961 to post-judgment awards. See Cataphora, Inc. v. Parker, 848 F.Supp. 2d 1064, 1074-75 (D.Nev. 2012). Therefore the federal statutory rate of interest shall apply post-judgment to the amount awarded.
32. The court further concludes that Prologis is entitled to an award of costs and attorneys' fees as the prevailing party in accordance with the provisions of Section 22 in the Lease.
33. Prologis shall submit to the court its bill of costs and affidavits in support of reasonable attorneys' fees on or before March 1, 2014. The Clerk of Court will then tax costs. Any objection to the taxation of costs shall be filed within 20 days of the taxation of costs by the Clerk. Any objections to Prologis' request for attorneys' fees shall be filed within 20 days after the filing of Prologis' request for fees. Should either party object to the award of interest post judgment based on the legal rate rather than the contract rate, such objections should be filed in writing by March 1, 2014.
34. The Clerk of Court shall enter a judgment consistent with these Findings of Fact and Conclusions of Law and Order.
It is so ordered.