From Casetext: Smarter Legal Research

Prepakt Concrete Co. v. Whitehurst Bros

Supreme Court of Arkansas (Division I)
Jul 18, 1977
552 S.W.2d 212 (Ark. 1977)

Opinion

No. 77-31

Opinion delivered June 13, 1977 [Rehearing denied July 18, 1977.]

1. ARBITRATION — PROCEDURAL RULES STATUTES — FAILURE OF SUBCONTRACTOR TO SHOW DIFFERENCE, EFFECT OF. — In the absence of showing that the procedure for arbitration under the American Arbitration Association's rules and regulations is different from the procedure for arbitration under the Uniform Arbitration Act of Arkansas, a subcontractor cannot complain of the trial court's determination that arbitration must proceed under the Uniform Act. 2. CONTRACTS — PLACE CONSUMMATED — EFFECT. — A subcontract arising out of a proposal submitted in Arkansas, accepted by a general contractor in Arkansas, and performed in Arkansas should be construed as an agreement finally consummated in Arkansas. 3. CONTRACTS — AMBIGUITY — CONSTRUCTION AGAINST PREPARER. — if there is any ambiguity in a contract, it must be construed most strongly against the preparer.

Appeal from Pulaski Circuit Court, Third Division, Tom F. Digby, Judge; affirmed.

Wright, Lindsey Jennings, for appellant.

Plegge, Lowe Whitmore, for appellee.


Appellee Whitehurst Bros., Inc. was the General Contractor for the construction of the Central Fire Station for the City of Little Rock. At the time of letting the bids, appellant Prepakt Concrete Co. had submitted a proposal for a subcontract "To furnish equipment, material and labor to install 231-14 [inch] Diameter Cast-in-Place augered pile in accordance with plans and specifications by Wilkins, Griffin, Sims, Architects." After appellant had been approved by the owner and architect, appellee accepted appellant's subcontract proposal in Arkansas. Appellant subsequently caused the contract to be marked "Accepted by Prepakt: F. B. Akers, Jr., Executive Vice-President" at its home office in Ohio. The work has been performed in Arkansas. The issue now between the parties arises over where the parties shall arbitrate the dispute in question in Ohio as contended by appellant or in Arkansas as contended by appellee. Appellee denies any liability to appellant but in the alternative makes demands against the City of Little Rock.

The arbitration agreement in the subcontract proposal submitted to appellee at the time of its bids on the General Contract provides:

"Any controversy or claim arising out of or relating to this agreement, or any alleged breach thereof shall be settled by arbitration under the rules and regulations of the American Arbitration Association. Any arbitration shall be held, and any award shall be made and judgment upon any such award may be entered in the county of the State wherein this agreement is finally consummated. Upon mutual agreement, arbitration may be held, award made and judgment entered elsewhere."

The plans and specifications submitted by the architects provided for the settlement of claims and disputes "by arbitration in accordance with the Uniform Arbitration Act of Arkansas."

The trial court restrained appellant from demanding that the arbitration be held in Ohio and concluded "that the parties hereto must proceed in accordance with the Uniform Arbitration Act of Arkansas. . . ." We agree with the trial court but not necessarily for the same reasons.

In the first place, appellant has shown no prejudice because it has not shown that the arbitration procedure under the rules and regulations of the American Arbitration Association is any different than the procedure outlined in the Uniform Arbitration Act of Arkansas (assuming that the Uniform Arbitration Act of Arkansas would permit a different procedure). In the next place, we cannot agree with appellant that the subcontract arising out of a proposal submitted in Arkansas, accepted by the General Contractor in Arkansas and performed in Arkansas should be construed as "an agreement finally consummated" at any place other than Arkansas. Since appellant prepared the language upon which it relies to take the arbitration proceedings to Ohio, we must apply the well-known rule of contract construction that if there is any ambiguity in the contract, it must be construed most strongly against the preparer. Leslie v. Bell, 73 Ark. 338, 84 S.W. 491 (1904).

Affirmed.

We agree: HARRIS, C.J., and FOGLEMAN and HICKMAN, JJ.


Summaries of

Prepakt Concrete Co. v. Whitehurst Bros

Supreme Court of Arkansas (Division I)
Jul 18, 1977
552 S.W.2d 212 (Ark. 1977)
Case details for

Prepakt Concrete Co. v. Whitehurst Bros

Case Details

Full title:PREPAKT CONCRETE COMPANY v. WHITEHURST BROS., INC

Court:Supreme Court of Arkansas (Division I)

Date published: Jul 18, 1977

Citations

552 S.W.2d 212 (Ark. 1977)
552 S.W.2d 212

Citing Cases

Lee v. Hot Springs Village Golf SCH

In so holding, we have also applied the well-known rule of contract construction that, if there is any…

Wessell Bros. Drill. v. Crossett Sch. Dist., No. 52

[1, 2] The same rules of construction and interpretation apply to arbitration agreements as apply to…