Pratt v. Van Rensselaer

Supreme Court of Michigan
Jul 22, 1926
235 Mich. 633 (Mich. 1926)

Opinion

Docket No. 85.

Submitted June 23, 1926.

Decided July 22, 1926.

Error to Oakland; Tappan (Harvey), J., presiding. Submitted June 23, 1926. (Docket No. 85.) Decided July 22, 1926.

Assumpsit by Walter M. Pratt against Ruby I. Van Rensselaer for a balance due on a building contract. Judgment for plaintiff. Defendant brings error. Affirmed.

Fred H. Aldrich and Arnold F. Zeleznik, for appellant.

Lynch Lovett, for appellee.


Plaintiff brought this suit to recover upon a contract under which he did the carpenter work on defendant's house and for extras. The contract price was $8,092.60, the claim for extras amounted to $2,305.31. He had been paid by defendant on order of her architect $9,510, and claimed with interest a balance due of $887.91. Defendant did not give notice of recoupment but insisted plaintiff had not properly performed the terms of the contract in several particulars and was not entitled to recover the balance due on the contract price. It does not seem to be seriously contended that the extras were not furnished or the price charged was not correct. Many minor defects in workmanship and material were claimed by defendant, but the chief complaint grows out of the laying of the floors. The specifications and blueprints are not before us but the record discloses that there was to be a sub-floor, overlaid by paper felt, and that the flooring proper was to be laid diagonal to that of the sub-floor. Defendant contends that the floor bulged, and claims this resulted from a failure to lay the flooring diagonal to the sub-floor, that it paralleled it and that the paper felt was not put in. Plaintiff contends that the bulging of the floors arose from another cause. The house was turned over to defendant about Christmas time and shortly thereafter she went to Europe and the house remained without heat during the cold winter months, and he insists the dampness, frost, weather and other conditions caused the bulging. Both parties had expert evidence sustaining their respective claims. Plaintiff also claims that the paper felt was put in and that there was a substantial compliance with the requirement to lay the floor diagonally; that he commenced laying the floor at an angle of 45 degrees but that the contour of the rooms would not permit a maintaining of that exact degree but that none of it was laid parallel with the sub-floor and all was laid diagonally to some degree and to the satisfaction of defendant's architect. It may be well to state at this point, in view of defendants' motion for a directed verdict, that plaintiff upon this record made a case for the jury. A verdict for something less than plaintiff's claim was followed by judgment which this writ of error reviews.

After plaintiff's testimony had been given, he called defendant's architect for cross-examination under the statute. Several assignments of error are based on the overruling of objections to questions asked him. If he had been plaintiff's witness another question, somewhat doubtful, however, would be presented. We do not perceive that any of the questions asked him were not proper on cross-examination. He gave testimony on such cross-examination tending to establish his agency for defendant in the erection of the house and in dealing with the various contractors. While defendant later modified her testimony, she did say on cross-examination:

"The contract was let entirely through the architect. * * * He prepared the plans and specifications, and he superintended the job. He had authority from me to do all those things."

With this testimony in the case, we need not consider the authority of an architect as matter of law, as we are satisfied on this record the authority of the architect and the extent of it were jury questions.

Plaintiff had been given a certificate by the architect for $650 which was a part of plaintiff's claim. Defendant assigns error on the giving of plaintiff's first request, which was as follows:

"I charge you, members of the jury, that the architect is the agent of the owner, and that if you find that the defendant gave her architect the exclusive right to pass upon or determine the amount of money due to the plaintiff at any stage of his work, then the defendant is bound by the certificate of February 27, 1924, and you must find for the plaintiff in the amount of $650 and interest at the rate of 5 per cent. per annum, to the date of the trial."

But an examination of the charge discloses that after reading this request the trial judge said:

"Now, that is the request. I will give that with this provision: That is, provided you find that the plaintiff complied with all the terms and conditions of his contract and his duty in relation to material and character of work, as I have explained."

The charge must be considered in its entirety. Excerpts, without considering what precede and what follow them may not be made the basis of reversals. In the instant case it will be noted that the trial court by what he said following the reading of the request practically nullified it. If the request was improper, a question not necessary to decision, it could not be harmful to defendant as the modification made compliance with the contract necessary before the certificate of the architect was available in plaintiff's behalf; obviously if plaintiff had complied with the contract he was entitled to recover. A like situation was presented as to plaintiffs' second request.

One of defendant's expert witnesses, who was familiar with the work of defendant's architect, was asked on cross-examination if he was a careful architect. While the answer might well have been excluded, we do not think it constituted reversible error. And in this connection, we think the court properly refused to give defendant's requests, the tenor of which were that if the architect was negligent, his acts did not bind defendant. There was no testimony to sustain such a claim. The architect not only drew the plans, specifications, and contracts, but he devoted much time to the work of supervision. His home was but a short distance away, and he was on the job practically every day. Defendant caused many changes to be made as the work progressed and the architect, so far as this record discloses, was faithful to her interest and frequently present as the work progressed. That the house cost more than defendant expected it would was no doubt largely due to the many changes suggested by her.

The other assignments of error have been considered but do not merit discussion.

The judgment will be affirmed.

BIRD, C.J., and SHARPE, SNOW, STEERE, WIEST, CLARK, and McDONALD, JJ., concurred.


Summaries of

Pratt v. Van Rensselaer

Supreme Court of Michigan
Jul 22, 1926
235 Mich. 633 (Mich. 1926)
Case details for

Pratt v. Van Rensselaer

Case Details

Full title:PRATT v. VAN RENSSELAER

Court:Supreme Court of Michigan

Date published: Jul 22, 1926

Citations

235 Mich. 633 (Mich. 1926)
209 N.W. 807

Citing Cases

Ins Co of N America v. Cuevas

The thrust of the plaintiff's claim is that the jury was not properly instructed. To assay the validity of…

Zylstra v. Graham

We have repeatedly held that the charge must be considered in its entirety as it was given by the trial court…