From Casetext: Smarter Legal Research

Powers Regulator Co. v. United States Fidelity & Guaranty Co.

Appeals Court of Massachusetts
May 3, 1979
7 Mass. App. Ct. 913 (Mass. App. Ct. 1979)

Summary

In Fidelity, where a surety's bond incorporated by reference an arbitration clause in a construction contract, the Court of Appeals of New York held that while the surety was bound by arbitration decisions as to disputes under the construction contract, it had not agreed to arbitrate "separate and distinct controversies" that might arise between it and the obligee under the performance bond.

Summary of this case from Kearsarge Metallurgical Corp. v. Peerless Ins. Co.

Opinion

May 3, 1979.

Jerold Newirth for the United States Fidelity Guaranty Company.

Sally A. Corwin ( Joseph A. Pisarri with her) for the plaintiff.


1. The judge did not err in ruling that the plaintiff, a supplier of materials to the defendant subcontractor Brandt-Jordan Corp., could recover from the defendant surety company on the payment bond given by the subcontractor to the general contractor. That bond was conditioned on the subcontractor's making "payment to all persons supplying to [it] labor and material in the prosecution of the work provided for in [the] contract and [on the subcontractor's sav[ing] harmless the [general contractor] against any expenditure or loss . . . arising from claims against the [general contractor] . . . by those claiming to have supplied labor and materials to [the subcontractor] . . . in connection with the said work" (emphasis supplied). By the express terms of G.L.c. 149, § 29A, the plaintiff, as a supplier of materials to whom payment was due, could bring an action on the bond directly against the surety. "The purpose of § 29A was to create a statutory exception to the rule of law in this Commonwealth which had been held to preclude recovery under a contract by a third-party beneficiary." M. Lasden, Inc. v. Decker Elec. Corp., 372 Mass. 179, 182 (1977). The statute "should be broadly construed to effectuate its self-evident policies." Id. at 183. It is not a requirement of § 29A that a supplier be named in the bond as an obligee in order to sue thereon; nor does the statute distinguish between a bond given by a general contractor to the owner and one given by a subcontractor to the general contractor. Compare 17 Am.Jur.2d Contractors' Bonds §§ 15 and 16 (1964). Cases reaching the same result in the absence of such a statute include Pacific States Elec. Co. v. United States Fid. Guar. Co., 109 Cal.App. 691, 694 (1930); Pacific Natl. Fire Ins. Co. v. Cummins Diesel of Georgia, Inc., 213 Ga. 4, 7 (1957); Fidelity Deposit Co. v. Pittman, 52 Ga. App. 394, 398-399 (1936); Griffith v. Stucker, 91 Kan. 47, 52-53 (1913); Parliament Ins. Co. v. L.B. Foster Co., 533 S.W.2d 43, 50 (Tex. Ct. Civ. App. 1975). See also cases collected at 118 A.L.R. 90 (1939). 2. The judge did not err in adopting that portion of the master's report wherein the master found the subcontractor liable to the plaintiff for extra work in accordance with the finding of an arbitrator. Arbitration of "any disputes arising out of or relating to this subcontract" was expressly provided for in the subcontract, which, in turn, was incorporated by reference in the payment bond. As the surety company agreed implicitly to that method of determining the contractual liability of its principal (the subcontractor), it could avoid the result of the arbitration only by showing that it was obtained by fraud or collusion. See Giatas v. Demoulos, 271 Mass. 51, 53-54 (1930); Martiniello v. Robitaille, 293 Mass. 200, 202-203 (1936). No such contention was made.

Judgment affirmed.


Summaries of

Powers Regulator Co. v. United States Fidelity & Guaranty Co.

Appeals Court of Massachusetts
May 3, 1979
7 Mass. App. Ct. 913 (Mass. App. Ct. 1979)

In Fidelity, where a surety's bond incorporated by reference an arbitration clause in a construction contract, the Court of Appeals of New York held that while the surety was bound by arbitration decisions as to disputes under the construction contract, it had not agreed to arbitrate "separate and distinct controversies" that might arise between it and the obligee under the performance bond.

Summary of this case from Kearsarge Metallurgical Corp. v. Peerless Ins. Co.
Case details for

Powers Regulator Co. v. United States Fidelity & Guaranty Co.

Case Details

Full title:POWERS REGULATOR COMPANY vs. UNITED STATES FIDELITY GUARANTY COMPANY…

Court:Appeals Court of Massachusetts

Date published: May 3, 1979

Citations

7 Mass. App. Ct. 913 (Mass. App. Ct. 1979)
388 N.E.2d 1205

Citing Cases

Travelers Surety v. Long Bay

A surety like Reliance (and now Travelers) is generally obligated to arbitrate a dispute with a contractor or…

C & I Steel, LLC v. Travelers Casualty & Surety Co. of America

As mentioned earlier, C I neither demanded arbitration against Travelers nor made claims against Travelers in…