Opinion
October 5, 1987
Appeal from the Supreme Court, Queens County (Goldstein, J.).
Ordered that the order is affirmed insofar as appealed from, with costs.
Compliance with Education Law § 3813 is a condition precedent to the commencement of an action against the Board of Education (see, Public Improvements v. Board of Educ., 56 N.Y.2d 850). This statutory mandate requires that a notice of claim be filed within 90 days after the accrual of a cause of action. It is well established that a claim accrues for the purposes of Education Law § 3813 upon substantial completion of work performed pursuant to a contract with the board (in this case, removal of asbestos from school ceilings) (see, Crescent Elec. Installation Corp. v Board of Educ., 50 N.Y.2d 780; Amsterdam Wrecking Salvage Co. v Greater Amsterdam School Dist., 56 N.Y.2d 828). It is undisputed that the work which constitutes the basis of this claim was substantially completed by October 3, 1983. Additionally, the plaintiff was aware of its extra costs three weeks prior to October 3, 1983, as it had sent the defendant a letter, dated September 11, 1983, setting forth the additional compensation sought. Since the plaintiff failed to file its notice of claim until January 6, 1984, more than 90 days after its claim accrued, said filing was untimely. The mere fact that communications were exchanged between the parties is insufficient to relieve the plaintiffs of its statutory duty (see, Parochial Bus Sys. v Board of Educ., 60 N.Y.2d 539). Further, as the plaintiff failed to seek leave to file a late notice of claim within the one-year Statute of Limitations, the relief provisions of Education Law § 3813 (2-a) are unavailable. Weinstein, J.P., Rubin, Kunzeman and Kooper, JJ., concur.