Action on contract. Richmond Superior Court. Before Judge Fleming.

Glower W. Jones, Joseph C. Staak, for appellants.

William A. Trotter III, Stanley C. House, A. Rowland Dye, Joseph R. Neil, Percy J. Blount, Thomas W. Tucker, Frederick N. Gleaton, Elwood F. Oakley III, Richard A. Slaby, Milton M. Avrett, Duncan D. Wheale, Stephen M. Phillips, Phillip O. Gossett, for appellees (case no. 63276).

Richard A. Slaby, William A. Trotter III, for appellees (case nos. 63277, 63278).


Phillips Construction Company, Inc. (Phillips) entered into a contract with the owner, Donald Golden (Golden), to construct the Richmond Plaza Shopping Center. Cowart Iron Works, Inc. (Cowart) and Rembrant, Inc. (Rembrant) subcontracted with Phillips to work on the project. In separate actions, Cowart and Rembrant sued Phillips and American Insurance Company (American), the bonding company, for breach of contract. Golden intervened as a defendant in the Cowart case, and was also a defendant in the Rembrant case. Golden filed cross-claims against Phillips and American for indemnification and counterclaims against Cowart alleging negligence and as a third party beneficiary of the subcontract between Cowart and Phillips. Phillips and American moved to dismiss the complaints and Golden's cross-claim, or, in the alternative, to stay the proceedings pending arbitration as provided for in the contract and subcontracts between the parties. The trial court denied the motions and Phillips and American appeal.

Appellees Golden and Rembrant moved to dismiss the appeals on the grounds that the order of the trial court is not a final judgment and appellants have failed to comply with the interlocutory review procedure found in Code Ann. § 6-701. This court has recently overruled Pace Const. Corp. v. Houdaille Indus., 155 Ga. App. 923, 924 ( 274 S.E.2d 44) (1980) and held that there is no direct appeal from an order denying a motion to stay proceedings pending arbitration. Tasco Industries v. Fibers Fabrics, 162 Ga. App. 593 ( 292 S.E.2d 439) (1982). We note that the substance of this case is controlled by Prince Faisal v. Batson Cook Co., 161 Ga. App. 219 ( 291 S.E.2d 249) (1982); however, we have no choice but to dismiss the appeals.

Appeals dismissed. Deen, P. J., and Pope, J., concur.

DECIDED JUNE 24, 1982 — REHEARING DENIED JULY 8, 1982 — CERT. APPLIED FOR.


Summaries of

Phillips Constr. Co. v. Cowart Iron Works, Inc.

Court of Appeals of Georgia
Jun 24, 1982
162 Ga. App. 861 (Ga. Ct. App. 1982)
Case details for

Phillips Constr. Co. v. Cowart Iron Works, Inc.

Case Details

Full title:PHILLIPS CONSTRUCTION COMPANY, INC. et al. v. COWART IRON WORKS, INC…

Court:Court of Appeals of Georgia

Date published: Jun 24, 1982

Citations

162 Ga. App. 861 (Ga. Ct. App. 1982)
293 S.E.2d 355

Citing Cases

Phillips Construction Co. v. Cowart Iron Works

On certiorari to the Supreme Court, our earlier decision that the above cause was not directly appealable but…

Phillips Constr. Co. v. Cowart Iron Works

DECIDED JANUARY 25, 1983. Certiorari to the Court of Appeals of Georgia — 162 Ga. App. 861 ( 293 S.E.2d 355).…