From Casetext: Smarter Legal Research

Pacific Northwest Reg'l Council of Carpenters v. Laborers Int'l Union of Northern America

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE
Jul 17, 2012
CASE NO. C11-1164 MJP (W.D. Wash. Jul. 17, 2012)

Opinion

CASE NO. C11-1164 MJP

07-17-2012

PACIFIC NORTHWEST REGIONAL COUNCIL OF CARPENTERS, Petitioner, v. LABORERS INTERNATIONAL UNION OF NORTHERN AMERICA, et al., Respondents.


ORDER ON SUMMARY

JUDGMENT MOTIONS

This matter comes before the Court on Respondent Laborer International Union of Northern America ("LIUNA") and Respondent Seattle/King County Building and Construction Trades Council AFL-CIO's ("BCTC") motions for summary judgment. (Dkt. Nos. 42, 66.) Having reviewed the motions, the responses (Dkt. Nos. 56, 78), the replies (Dkt. Nos. 63, 83), and all related papers, the Court DENIES Respondent LIUNA's motion for summary judgment and DENIES in part and RESERVES RULING in part on Respondent BCTC's motion for summary judgment to allow for additional discovery as requested by Petitioner.

Background

This case concerns a union dispute arising out of the assignment of compressed air tunnel work under the Sound Transit Link Light Rail Project Labor Agreement ("PLA"). The prime contractor, Traylor-Frontier-Kemper ("TFK") assigned compressed air tunnel work to Ballard Diving and Salvage ("Ballard"). (Dkt. No. 43-1 at 38.) On May 17, 2011, Ballard assigned its work to LIUNA-affiliated members. Petitioner Pacific Northwest Regional Council of Carpenters ("Carpenters") objected to this on May 24, 2011. (Id at 12.)

On June 27, 2011, Carpenters asserted that the disputed work assignment to Ballard involved allegedly "non-traditional" work and requested to proceed with dispute resolution under PLA Article 16.2(a). (Dkt. No. 43 at 5.) Under that article, the International Unions and the Contractor must meet to resolve disputes the local unions cannot resolve. (Dkt. No. 1-1 at 25.)

In an attempt to satisfy Article 16.2(a), an initial meeting occurred on June 29, 2011, with no agreement reached. It appears the meeting primarily involved Robert Abbott, on behalf of Respondent LIUNA, arguing that the disputed work was traditional and that 16.2(a) and (b) should not apply. Abbott is the assistant business manager for the Washington and Northern Idaho District Council of Laborers (a LIUNA-affiliate). (Dkt. No. 43-1 at 20.) Oddly, LIUNA now claims Abbott never represented it. (Dkt. No. 52-15 at 3.) Despite not being a party to the dispute or an International Union, BCTC attended that meeting and spoke against the Carpenter's position regarding the disputed work assignment. (Dkt. No. 43-1 at 20.) Ed Triezenberg, Director of Contract Administration at Carpenters, represented Carpenters at the meeting. (Dkt. No 53-1 at 2.) Triezenberg argued an arbitrator should be selected in accordance with 16.2(a) and 16.2(b) since Carpenters claimed the disputed work was non-traditional. (Dkt. No. 43-1 at 21.)

Any arbitration was frustrated by the death of the appointed arbitrator. Article 16.2(b) of the PLA provides that if the International Unions cannot resolve the dispute within 15 days, any party can refer the matter for arbitration to John Dunlop or a mutually agreed upon successor. (Dkt. No. 1-1 at 25.) Before the dispute could be arbitrated Dr. Dunlop died. The parties were required to mutually agree to a successor, but were unable to do so. On June 30, 2011, Carpenters proposed to Abbott that Michael Beck be appointed as successor, which Abbott rejected the same day. (Dkt. No. 53-4 at 2, Dkt. No. 53-5 at 2.) On July 12, 2011, Carpenters filed this action to compel arbitration and appoint Beck as arbitrator.

On August 24, 2011, the Joint Administrative Committee ("JAC"), which is composed of all parties to the PLA and responsible for its implementation, amended the PLA to create a new procedure for appointing arbitrators under Article 16.2(b). (Dkt. No. 43-1 at 48.) This procedure specifies that the arbitrator will be selected by the International Unions and Contractor through alternatively striking "from among the West Coast members of the jurisdictional issues arbitration panel of the Plan for the Settlement of Jurisdictional Disputes in the Construction Industry." (Dkt. No. 53-7 at 2.)

The parties dispute whether the new PLA 16.2(b) should apply, and no resolution as to who should arbitrate the dispute has been achieved. (Dkt. No. 43-1 at 52, 54, 57, 64.) On March 19, 2012, Alan Clune, business manager for Street Pavers, Sewer, Watermain and Tunnel Workers Local 440, a local affiliate of LIUNA and not a party to this suit, reiterated the offer to select an arbitrator pursuant to the amended 16.2(b). (Dkt. No. 43-1 at 60.) On April 6, 2012, Triezenberg responded to both Abbott and Clune by proposing four arbitrators from which Carpenters and LIUNA could work. (Dkt. No. 43-1 at 65.) This proposal was not in accordance with the amended PLA Art. 16.2(b). Abbott did not respond to this offer. Clune responded on April 16, 2012 that the list was acceptable to his Local and to LIUNA. (Dkt. No. 43-1 at 67.) Complicating matters is the fact Triezenberg's April 6, 2012, letter stated that Carpenters does not recognize Clune as a representative of LIUNA. (Dkt. No. 43-1 at 65.) Clune's response letter on April 16, 2012, states that neither he nor Abbott works for LIUNA. (Dkt. No. 43-1 at 67.) Carpenters maintains that Clune's acceptance of proposed arbitrators was not an agreement to arbitrate on behalf of LIUNA. (Dkt. No. 56 at 7.) Then on April 20, 2012, counsel for LIUNA sent a letter to Carpenters counsel stating that Abbott is not an employee or agent of LIUNA but instead "has always been acting on behalf of the District Council." (Dkt. No. 52-15 at 3.) On May 2, 2012, Carpenters received a letter from counsel for BCTC stating that it did not object to selecting the arbitrator from the list provided by Carpenters. (Dkt. No. 52-5 at 2.) LIUNA has not sent a similar letter to Carpenters.

Both LIUNA and BCTC have submitted motions for summary judgment primarily arguing the case is moot.

Analysis

I. Standard

"The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). The Court views the underlying facts in the light most favorable to the party opposing the motion. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986). A genuine dispute over a material fact exists if there is sufficient evidence supporting the claimed factual dispute, requiring a judge or jury to resolve the differing versions of the truth. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 253 (1986). "A fact issue is genuine 'if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.'" Villiarimo v. Aloha Island Air, Inc., 281 F.3d 1054, 1060 (9th Cir. 2002) (quoting Anderson, 477 U.S. at 248). The moving party is entitled to judgment as a matter of law when the nonmoving party fails to make a sufficient showing on an essential element of a claim in the case on which the nonmoving party has the burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1985).

II. LIUNA's Motion for Summary Judgment

LIUNA contends that the case is moot and that Carpenters lack standing. Neither argument has traction.

A. Mootness

The Court rejects LIUNA's argument that the case is moot. Both the appointment of an arbitrator and arbitration of the dispute are live issues for which the Court can grant relief.

"Federal courts lack jurisdiction to decide moot cases because their constitutional authority extends only to actual cases or controversies." Iron Arrow Honor Soc'y v. Heckler, 464 U.S. 67, 70 (1983). "To qualify as a case fit for federal-court adjudication, 'an actual controversy must be extant at all stages of review, not merely at the time the complaint is filed.'" Arizonans for Official English v. Arizona, 520 U.S. 43, 67 (1997) (citation omitted). Where a party has not agreed to everything that the opposing party has demanded, the case is not moot. See GCB Commc'ns Inc. v. U.S. South Commc'ns, Inc., 650 F.3d 1257 (9th Cir. 2011) (finding the case not moot where one party had only agreed to pay less than the full amount demanded by the opposing party).

A dispute of fact exists as to whether LIUNA has complied with the first step in resolving this dispute short of arbitration. Article 16.2(a) of the PLA requires that "the International unions and the involved Contractor shall meet promptly to resolve the dispute." It is not clear whether Abbott sufficiently represented LIUNA at the initial meeting between Carpenters and LIUNA on June 29, 2011 to satisfy Article 16.2(a). (Dkt. No. 1-1 at 25, Dkt. No. 56 at 3.). Sound Transit has stated its belief that the meeting was inadequate to satisfy 16.2(a). (Dkt. No. 43-1 at 40.) LIUNA now contends that Abbott has not acted on its behalf and there is no evidence showing LIUNA was actually present at the meeting. It is unclear whether the requisites of 16.2(a) have been met, though it would not appear to be Carpenters' fault should it be the case. Separately, the Court notes Abbott objected to even proceeding under the Article 16.2(a) and 16.2(b) procedures because he claimed the work was not "non-traditional" and therefore did not trigger those dispute resolution articles. (Dkt. No. 53-5 at 2.) Yet Article 16.2(a) clearly states that a party need only claim that the work is non-traditional to trigger the articles, which Petitioner clearly did. (Dkt. No. 1-1 at 25.) LIUNA's argument that it has mooted Petitioner's claim by agreeing to arbitrate is erroneous when it appears it may never have adequately participated in the 16.2(a) meeting.

Even if LIUNA has satisfied its obligations under Article 16.2(a), the facts do not confirm LIUNA has ever expressed an agreement to appoint a successor arbitrator. Article 16.2(b) also requires the agreement of the International Unions in the appointment of a successor to Dr. Dunlop. (Dkt. No. 1-1 at 25.) This is true of both the original and amended 16.2(b) procedure. (Dkt. No. 53-7 at 2.) Respondent LIUNA has not directly made any offer to Petitioner and cannot claim that it has mooted Petitioner's petition to compel arbitration. Petitioner reasonably concludes that Clune, who works for a Local Union, was not representing the International Union—LIUNA—when he dropped any conditions on appointing the arbitrator in his last letter on April 16, 2012. (Dkt. No. 43-1 at 67.) On this record, the Court cannot find the petition moot.

Because the Court finds that Petitioner's petition is not moot, the Court DENIES Respondent LIUNA's motion for summary judgment.

B. Standing

The Court continues to find Petitioner has standing.

The party invoking federal jurisdiction bears the burden of establishing the three elements of standing: (1) actual or imminent injury in facts; (2) a causal connection between the injury and the conduct complained of; and (3) likelihood that a favorable decision will redress the injury. See Lujan v. Defenders of Wildlife, 504 U.S. 555, 561-62 (1992). Respondent argues that a favorable decision by this Court would not redress the injury complained of by Petitioner because what Petitioner asks for is a modification of the PLA, which none of the parties has the unilateral authority to amend. (Dkt. No. 42 at 19.)

The Court has already held that Petitioner is not seeking to alter the PLA and that it is merely seeking to compel arbitration and appoint an arbitrator for this particular dispute. (Dkt. No. 26 at 3-4.) Petitioner is not seeking to appoint an arbitrator for any other dispute and thus is requesting a remedy firmly within the scope of the PLA. The Court finds no reason to revisit this issue. The Court DENIES LIUNA's motion for summary judgment on this issue.

C. Amendment of PLA Article 16.2(b)

The parties dispute whether the original Article 16.2(b) or the amended version should apply in this case. The Court finds that the original Article 16.2(b) governs this dispute.

Under LMRA § 301, courts interpret whether a party has breached the arbitration clause in a collective bargaining agreement because "arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit." United Steelworkers of Am. v. Warrior & Gulf Nav. Co., 363 U.S. 574, 582 (1960). "When deciding whether the parties agreed to arbitrate a certain matter . . . courts generally . . . should apply ordinary state-law principles that govern the formation of contracts." First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944 (1995).

Washington State law governing contract interpretation states that "'the cardinal rule with which all interpretation begins is that its purpose is to ascertain the intention of the parties.'" Berg v. Hudesman, 115 Wn.2d 657, 663 (1990) (citation omitted). Extrinsic evidence is admissible to determine the intended meaning of the parties: "In discerning the parties' intent, subsequent conduct of the contracting parties may be of aid, and the reasonableness of the parties' respective interpretations may also be a factor in interpreting a written contract." Id. at 668.

The evidence indicates the parties did not mutually intend to be retroactively bound by the amended Article 16.2(b). The amended PLA contains no statement regarding its retroactive application to preexisting disputes. Extrinsic evidence indicates there was no mutual intent of the parties to be retroactively bound by the amended version of 16.2(b). When the JAC amended Article 16.2(b), those present suggested the solution was only forward-looking. (See Dkt. No. 43-1 at 48.) Alec Stephens of Sound Transit, who proposed the amendment, suggested the amendment applied prospectively only, stating it is "for the parties to determine as they proceed with their dispute." (Id.) He also stated that "Sound Transit is responding to the fact that Article 16.2(b) as it currently is written does not work and we want to amend the PLA to make it work over the long term." (Id.) The Court finds the original Article 16.2(b) properly governs the procedure for appointment of an arbitrator in this dispute, not the amended Article.

III. BCTC's Motion for Summary Judgment

BCTC argues the case is moot because the project is complete and the disputed work was never performed. The Court DENIES this aspect of the motion. Petitioner asks the Court to permit it further discovery on BCTC's substantive challenge to the claim against it, which the Court GRANTS. The Court thus RESERVES RULING on this aspect of the motion for summary judgment. Lastly, the Court addresses the request for attorneys' fees, which BCTC challenges.

A. Mootness

BCTC incorrectly argues the completion of the tunneling project moots Petitioner's petition to compel arbitration. Completion of the underlying project does not moot the request for arbitration.

The Ninth Circuit has held that the completion of work underlying a jurisdictional dispute does not moot a request to compel arbitration and appoint an arbitrator. United Ass'n of Journeymen and Apprentices v. Bechtel Constr. Co., 128 F.3d 1318, 1322 (9th Cir. 1997). The role of the Court is to determine whether an agreement was entered into and "[o]nce a court determines that the parties agreed to arbitrate a dispute, then that dispute must be submitted to the arbitrator." Local Union No. 370 of Int. Union of Operating Eng. v. Morrison-Knudsen Co., Inc., 786 F.2d 1356, 1358 (9th Cir. 1986). "All claims on the merits - even if they appear frivolous - should be decided by the arbitrator." Pipe Trades Council of Northern California v. Underground Contractor's Ass'n of Northern California, 835 F.2d 1275, 1277 (9th Cir. 1988). Additionally, procedural issues regarding compliance with the PLA dispute resolution steps are to be decided by the arbitrator since, "labor disputes . . . cannot be broken down so easily into their 'substantive' and 'procedural' aspects." John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 556 (1964). For example, in Bechtel the question of whether work had actually been completed on the project was decided by the arbitrator in that case. Bechtel, 128 F.3d at 1321.

This case is not mooted by the completion of the underlying work. The Court need only decide whether an agreement to arbitrate was entered, whether arbitration happened or was delayed and how to ensure arbitration goes forward. The issue of whether the disputed work assignment has been completed or not and how that impacts the underlying dispute is for the arbitrator to decide. The Court DENIES this aspect of BCTC's motion and does not find the claim moot.

B. Petitioner's Request to Defer Summary Judgment for Discovery

BCTC seeks dismissal of the suit against it on the theory it is not a party to the request to arbitrate and that it did nothing to delay the arbitration. The Court defers summary judgment to allow for additional discovery on the claim that BCTC colluded with LIUNA to delay arbitration.

Federal Rule of Civil Procedure 56(d) allows the Court to deny or continue a motion for summary judgment if the non-moving party establishes that it cannot present facts essential to justify its opposition. Fed. R. Civ. P. 56(d). The party seeking such a continuance must make (a) a timely application which (b) specifically identifies (c) relevant information, (d) where there is some basis for believing that the information sought actually exists. Emplrs. Teamsters Local Nos. 175 & 505 Pension Trust Fund v. Clorox Co., 353 F.3d 1125, 1129-1130 (9th Cir. 2004). The Court may deny the request unless the party opposing summary judgment articulates how additional discovery may preclude summary judgment and demonstrates diligence in pursuing discovery thus far. Qualls v. Blue Cross of California, Inc., 22 F.3d 839, 844 (9th Cir. 1994). The burden is on the nonmoving party to establish that proceeding with additional discovery would produce evidence sufficient to defeat summary judgment and that the evidence it seeks is in existence. Chance v. Pac-Tel Teletrac Inc., 242 F.3d 1151, 1161 n.6 (9th Cir. 2001).

Here, the issue is whether there is a sufficient evidentiary basis for Petitioner to maintain that BCTC has colluded with LIUNA to delay arbitration. To adequately support its case, Petitioner seeks access to individuals it has currently been unable to depose due to Respondents' delay and to documents previously requested but not produced. Carpenters has provided sufficient indication that it may be able to discover the evidence it seeks through these depositions and review of the unreleased discovery. The Court finds it appropriate to permit more discovery on this aspect of the case before ruling on the present motion for summary judgment.

The Court GRANTS Petitioner's request for additional time and RESERVES RULING on Respondent BCTC's motion for summary judgment. Petitioner must refile its opposition to the motion for summary judgment within 10 days of completing the depositions and obtaining the requested discovery. BCTC must file its reply within 4 days after Carpenters files its opposition. Briefing shall be limited to the sole question of whether the facts show collusion between BCTC and LIUNA in delaying Petitioner's request to arbitrate and appoint a successor to Dr. Dunlop to arbitrate the discrete dispute over the tunnel work.

C. Attorney's Fees

BCTC correctly argues attorneys' fees cannot be awarded on the basis of a finding of bad faith delay tactics, where the delay itself is an element of the underlying cause of action.

"A court may assess attorney's fees when a party has 'acted in bad faith, vexatiously, wantonly or for oppressive reasons.'" Chambers v. NASCO, 501 U.S. 32, 45-46 (1991). The Ninth Circuit has held "that an unjustified refusal to abide by an arbitrator's award may equate an act taken in bad faith, vexatiously or for oppressive reasons." Int'l Union of Petroleum & Indus. Workers v. W. Indus. Maint., Inc., 707 F.2d 425, 428 (9th Cir. 1983).

The Ninth Circuit has also held that attorneys' fees are improperly shifted "based solely upon a finding of bad faith as an element of the cause of action presented in the underlying suit." Ass'n of Flight Attendants, AFL-CIO v. Horizon Air Indus., Inc., 976 F.2d 541, 550 (9th Cir. 1992). If a court were to issue sanctions for pre-litigation bad faith conduct that is implicitly part of the underlying cause of action there is a danger of over-expanding the scope of the Court's punitive authority and over-expanding this exception to the American Rule. Id. The Court separately notes there is no dispute that Petitioner's request for attorney's fees does not present an independent cause of action in this case. (Dkt. No. 78 at 15.)

BCTC correctly argues that pre-litigation delays in arbitration cannot form the basis of a finding of bad faith sufficient to justify the imposition of attorney's fees. The facts of Horizon Air support this argument. In Horizon Air, a flight attendants' union brought an action under the Railway Labor Act alleging that Horizon had violated its duty "to exert every reasonable effort to reach an agreement" in labor negotiations. Id. at 543-44. Delay of negotiations was the essence of the cause of action, since "the court's decree prohibited Horizon only from 'engaging in any conduct designed to forestall an agreement' with the union." Id. at 544. Looking to the NLRA (now the LMRA) for interpretive guidance, the court defined Horizon's duty as "at least the avoidance of 'bad faith' as defined under the NLRA, that is 'going through the motions with a desire not to reach an agreement.'" Id. at 544. The court declined to extend the bad faith exception in that case "solely upon a finding of bad faith as an element of the cause of action presented in the underlying suit." Id. at 550. Here, similarly, the Court will not award attorney's fees based solely on evidence of bad faith delay that occurred prior to the filing of the petition. A claimed violation of the duty to arbitrate under the PLA necessarily includes allegations of delay, whether they rise to the level of bad faith or not. It would thus be improper to allow Petitioner to use the same evidence of pre-litigation delay as evidence of bad faith in support of an award of attorneys' fees. Any request for attorney's fees based on claims of bad faith cannot be based exclusively on evidence of pre-litigation delay.

Given that discovery is ongoing on this issue, the Court does not render any judgment on the factual merits of the request for fees.

Conclusion

The Court DENIES LIUNA's motion for summary judgment. Petitioner's claim against LIUNA is not moot. The Court also DENIES in part BCTC's motion as to mootness, finding the claims against BCTC not to be moot. The Court RESERVES RULING in part on Respondent BCTCs motion for summary judgment in order to allow for additional discovery on the issue of whether Petitioner's claim against BCTC can move forward.

The clerk is ordered to provide copies of this order to all counsel.

________________________

Marsha J. Pechman

United States District Judge


Summaries of

Pacific Northwest Reg'l Council of Carpenters v. Laborers Int'l Union of Northern America

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE
Jul 17, 2012
CASE NO. C11-1164 MJP (W.D. Wash. Jul. 17, 2012)
Case details for

Pacific Northwest Reg'l Council of Carpenters v. Laborers Int'l Union of Northern America

Case Details

Full title:PACIFIC NORTHWEST REGIONAL COUNCIL OF CARPENTERS, Petitioner, v. LABORERS…

Court:UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE

Date published: Jul 17, 2012

Citations

CASE NO. C11-1164 MJP (W.D. Wash. Jul. 17, 2012)