From Casetext: Smarter Legal Research

Ortman v. Dejager

Supreme Court of South Dakota
Aug 4, 2010
787 N.W.2d 299 (S.D. 2010)

Opinion

No. 25272.

Considered on Briefs March 22, 2010.

Decided August 4, 2010.

Appeal from the First Judicial Circuit Court, Yankton County, Arthur L. Rusch, J.

Michael D. Bornitz of Cutler Donahoe, LLP, Sioux Falls, South Dakota, Attorney for plaintiffs and appellants.

Shawn M. Nichols of Cadwell, Sanford, Deibert Garry, LLP, Sioux Falls, South Dakota, Attorney for defendants and appellees.


[¶ 1.] Thomas and Jennifer Ortman hired Rick DeJager, Carolyn DeJager, and DeJager Construction Log Homes, Inc. (collectively DeJager) to build a house. Disputes arose between the parties during construction. Ortmans eventually sued DeJager claiming damages for breach of contract, conversion, and fraud. Ortmans specifically sought $116,837 in damages for their conversion claim. A jury found against Ortmans on the conversion and fraud claims but awarded Ortmans $234,632.53 in damages for breach of contract. DeJager asked the trial court for judgment notwithstanding the verdict, remittitur, or a new trial on grounds that the jury miscalculated the damages. DeJager argued that the jury erroneously included $116,837 for conversion damages in the breach of contract award. The trial court agreed, granted remittitur, and entered an order reducing the jury's award. The order also provided for a new trial on breach of contract damages if Ortmans declined the remittitur, which they eventually did. Ortmans ask us to reverse the trial court and allow the verdict to stand. The question is whether the trial court abused its discretion by granting a new trial based on its perception that the jury incorrectly included conversion damages in the breach of contract award. We affirm the trial court.

[¶ 2.] Ortmans hired DeJager to build a luxury log house near Lewis Clark Lake outside Yankton, South Dakota. The agreed contract price for the 9,400 square-foot house was $667,280. During construction, conflicts arose concerning allegations that Ortmans were "dealing directly with subcontractors and suppliers" and were making "substantial changes to the plans and specifications." Other allegations included that DeJager "demanded more money for the project because of cost overruns he purposely caused and because of his financial difficulties." Deteriorated communication between the parties eventually necessitated the use of third parties to exchange the details for completing the project. Although the house's scheduled completion date was May 1, 2007, it remained unfinished when a fire destroyed it in December 2007.

[¶ 3.] At the time of the fire, Ortmans had paid DeJager $736,644. Because DeJager had failed to pay some of the subcontractors, the subcontractors filed mechanic's liens against the house for $116,837. Before trial, the parties disagreed on how to present the mechanic's liens to the jury since DeJager's insurance had paid the subcontractors and satisfied the liens. The trial court's pre-trial order allowed Ortmans to introduce evidence of the mechanic's liens, but disallowed evidence of insurance satisfying the liens. The issue resurfaced during trial when DeJager renewed his objection. The trial court again prohibited any reference to insurance paying the liens but reserved the right to offset a verdict on the conversion claim by the amount paid by insurance. As a result of the trial court's ruling, Mr. Ortman was allowed to tell the jury that he sustained damages of $116,837 as a result of the mechanic's liens.

[¶ 4.] At trial, Ortmans combined their breach of contract and conversion damages in Exhibit 18. The damages were presented in Exhibit 18 as follows:

Damages Contract Price $667,281 Base cost for a completed house Change Orders $18,765 Invoices $1,694 Total Due DeJager $687,740 Final cost for a completed house Total Payments $736,644 Overpayment $48,904 Total Payments minus Total Due DeJager Mechanic's Liens $116,837 Amounts owed to subs/suppliers Work Not Done $94,743 Credit for completed house but not done TOTAL Damages $260,484 After the jury returned a verdict of $234,632.53 on the breach of contract claim, DeJager filed a motion for judgment notwithstanding the verdict. Alternatively, DeJager sought remittitur or a new trial on damages. DeJager claimed that the jury's verdict mistakenly included the mechanic's liens in the breach of contract award. The trial court agreed with DeJager and granted the remittitur based on (1) Ortmans' general statement of damages in Exhibit 18, (2) a question from the jury during deliberations regarding the mechanic's liens, and (3) the way Ortmans argued their case. The trial court reduced the damages by $116,837. Ortmans declined the remittitur, and the trial court granted DeJager's motion for a new trial.

[¶ 5.] We review the granting of a new trial under an abuse of discretion standard. Reinfeld v. Hutcheson, 2010 SD 42, ¶ 5, 783 N.W.2d 284, 286-87 (citing Morrison v. Mineral Palace Ltd. P'ship, 1998 SD 33, ¶ 7, 576 N.W.2d 869, 870 (citations omitted)). We "will not overturn the [trial] court's ruling unless it appears affirmatively from the record [that] there has been an abuse of discretion." Id. (quoting Morrison, 1998 SD 33, ¶ 7, 576 N.W.2d at 870). "If the trial court finds an injustice has been done by the jury's verdict, the remedy lies in granting a new trial." Id. (quoting Waldner v. Berglund, 2008 SD 75, ¶ 11, 754 N.W.2d 832, 835 (citations omitted)). Because a new trial was granted, "more deference is given to the trial court[.]" Id. (quoting Tunender v. Minnaert, 1997 SD 62, ¶ 9, 563 N.W.2d 849, 851). "This is because orders allowing new trials `are not conclusive or decisive of any rights or issues. They merely open the way for a reinvestigation of the entire case upon its facts and merits.'" Id. (quoting Jensen v. Miller, 80 S.D. 384, 389, 124 N.W.2d 394, 396 (1963)).

[¶ 6.] Based on the record, we find no abuse of discretion in granting a new trial on damages. A trial court can grant a new trial under SDCL 15-6-59(a)(1) when there is an "[i]rregularity in the proceedings . . . by which either party was prevented from having a fair trial." The trial court noted that there was an irregularity in the verdict concerning the mechanic's liens. Ortmans claimed $116,837 in mechanic's liens as conversion damages, not as breach of contract damages. Yet, the jury appeared to have included the mechanic's liens in the amount of damages awarded for breach of contract. The trial court surmised that the jury mistakenly included the mechanic's liens in the general verdict award. This was because Ortmans' Exhibit 18 included the mechanic's liens in the total damage claim. It appeared to the trial court that in order for the jury to arrive at the verdict amount of $234,632.53, the jury must have included the mechanic's liens. The trial court intended to apply an offset if the jury awarded damages for conversion. Instead, the trial court applied the offset against the breach of contract award in the form of remittitur. While the judge acknowledged that he was not absolutely sure what the jury had done, he determined that either remittitur or a new trial on contract damages was justified. On review, we defer to the trial court. The record supports the trial court's rationale. Because Ortmans declined the remittitur, the trial court did not abuse its discretion by granting a new trial on damages.

[¶ 7.] The order for a new trial on damages is affirmed.

[¶ 8.] GILBERTSON, Chief Justice, and KONENKAMP, ZINTER, and SEVERSON, Justices, concur.


Summaries of

Ortman v. Dejager

Supreme Court of South Dakota
Aug 4, 2010
787 N.W.2d 299 (S.D. 2010)
Case details for

Ortman v. Dejager

Case Details

Full title:Thomas and Jennifer ORTMAN, Plaintiffs and Appellants, v. Rick DeJAGER…

Court:Supreme Court of South Dakota

Date published: Aug 4, 2010

Citations

787 N.W.2d 299 (S.D. 2010)
2010 S.D. 65