Opinion
12-03-1885
W. J. Robertson and J. A. Watts and W. G. Robertson, for the plaintiff in error. Penn & Cocke, for the defendant in error.
Error to judgment of circuit court of Roanoke city, rendered December 18th, 1884, in action of assumpsit by A. P. Howison against the Norfolk and Western Railroad Company.
During 1882 and up to April, 1883, said company had certain bridges built under contract with the Clark Bridge Company. In November, 1882, Howison furnished said Bridge Company with lumber, which was to be, and was, used in constructing said bridges. Plaintiff furnished defendant March 14th, 1883, with notice and affidavit that, as sub-contractor, he would hold defendant responsible to him for the payment of $1,963.02, the amount due to plaintiff from the general contractor for said lumber. At the time the notice was given defendant did not owe, and since then has not owed, the general contractor anything.
Defendant demurred to the declaration, but the circuit court overruled the demurrer, and, a jury being waived and the facts agreed, rendered judgment for the plaintiff for the amount claimed. And the defendant having excepted, obtained a writ of error and supersedeas to the judgment.
W. J. Robertson and J. A. Watts and W. G. Robertson, for the plaintiff in error.
Penn & Cocke, for the defendant in error.
OPINION
LACY, J.
The case, as appears by the statement in the record of the facts agreed, is as follows: During the year 1882, and up to the month of April, 1883, the Clark Bridge Company, a corporation whose chief office was situated in the city of Baltimore, Maryland, was engaged in erecting bridges along the line of the New River Division of the Norfolk and Western Railroad, which line of railroad was, at that time, being constructed by the Norfolk and Western Railroad Company. During the progress of this work the Clark Bridge Company, being the general contractors for the said bridges, became indebted to the plaintiff in this case in the sum of nineteen hundred and sixty-three dollars and two cents for lumber furnished by said Howison to be used, and which was used, by the said Clark Bridge Company in and about the construction of the said bridges. On the 14th day of March, 1883, the plaintiff, A. P. Howison, gave notice to the Norfolk and Western Railroad Company, under chapter one hundred and fifteen of the Code of Virginia, and the acts amendatory thereof, in writing, of the value of labor performed and materials furnished, and on the same day furnished the said defendant, the Norfolk and Western Railroad Company, with an affidavit showing a correct account of the amount due to him by the contractor and remaining unpaid; and notice that, as sub-contractor, he would hold the Norfolk and Western Railroad Company responsible for the payment of the amount due to him by the general contractor, the Clark Bridge Company.
At the time the said notice was served upon the Norfolk and Western Railroad Company, the said company did not owe the Clark Bridge Company anything; nor has it owed the Clark Bridge Company anything since that time. The lumber mentioned was furnished in the month of November, 1882. The defendant, at the trial, demurred to the declaration, and to each count thereof, pleaded non-assumpsit, and, neither party requiring a jury, the case was submitted to the court upon the said defendant's demurrer and the facts agreed upon, for its judgment. And the court overruled the demurrer, and gave judgment for the plaintiff against the said defendant for the sum of nineteen hundred and sixty-three dollars and two cents, with interest from the 14th day of March, 1883, until paid, and his costs. To which judgment, the defendant excepted, and applied to this court for a writ of error and supersedeas, which was awarded.
The ground of demurrer set up by the defendant is that the declaration did not aver that the account therein alleged to have been furnished to the defendant was approved by the general contractor, or that the general contractor, after ten days' notice to him of the filing of the account with the defendant, had failed to file with the defendant any objections to the said account; or that the same had been ascertained to be due from the general contractor to the sub-contractor, in the manner provided for in the sixth section of chapter one hundred and fifteen of the Code; and that such approval or failure to object on the part of the general contractor, or ascertainment of the amount due, being required by said sixth section to authorize the defendant to pay anything to the plaintiff. And for the further reason that the declaration does not aver when the notice therein alleged to have been given by the plaintiff to the defendant, was given, nor show that when it was given anything was due, or thereafter to become due, to the Clark Bridge Company, from the defendant under its contract with the said defendant.
As to the first ground of demurrer set forth above, that the declaration does not set forth what, if anything, was done under the provisions of the sixth section: The said sixth section provides what may be done between the owner and the general contractor, concerning the account furnished by the sub-contractor to the owner. The statute gives the sub-contractor a lien on the property as against the owner after complying with the provisions of the law; and the transactions between the owner and the general contractor concerning the account, are not a part of the sub-contractor's claim. If the general contractor confess the debt, or fail to dispute it within ten days, the owner may pay without going further. If he dispute it, or deny its correctness, the section provides for the ascertainment of its true amount. This may be matter of defence, if such exists, but it does not constitute any part of the plaintiff's case, and could not find legitimate place in his declaration. His claim to a lien is not made to depend by the law upon the admissions of the general contractor, or his failure to object to or dispute it within ten days after notice by the owner, which the owner may not give. It is matter of defence which must depend upon proof whether all or any part of the claim is due and unpaid; but it is not a part of the plaintiff's demand; and the demurrer, on this ground, was rightly overruled.
As to the second ground of demurrer, that the declaration does not set forth when the notice was given: The declaration alleges that notice in writing was given in pursuance of the statute, and that subsequently the required affidavit was filed within twenty days after the completion of the bridges, of the amount due and unpaid, & c. This ground of demurrer cannot, therefore, be sustained.
And as to the third and last ground of demurrer, that the declaration did not allege that, when the notice was given, anything was due from the owner to the general contractor: the claim of the sub-contractor is not made to depend upon that circumstance. It is immaterial to the sub-contractor when he serves his notice and account, with the required affidavit, whether anything is due from the owner to the general contractor, or whether the whole cost of the building or bridge has been paid by the owner to the general contractor or not; provided, only, that he serves his notice and files his account and affidavit as required by the statute within twenty days after the building or bridge has been completed, or the work otherwise terminated. The sub-contractor is not dependent now, as under the eighth section, upon the state of the accounts between the owner and the general contractor. Under the fourth section he is accorded the benefit of the act upon the same terms as the general contractor.
He is no longer authorized to give notice of the probable value of the labor to be performed and materials furnished. He is now authorized to give notice of the value of the labor actually performed and the value of the materials actually furnished, and he is allowed until twenty days after the building or other improvement is completed, or the work thereon otherwise terminated, to furnish his account, supported by affidavit, to the owner, of the amount due and unpaid to him. If he does this, then the owner is liable to him under the law for such amount of his account, provided the same does not exceed the amount set forth in the said affidavit, whether the owner has already settled with the general contractor or not.
The contention of the plaintiff in error that the judgment should be reversed because, " There is not a word to indicate that the plaintiff, within twenty days after the bridges were completed or the work thereon otherwise terminated, furnished the owner with an affidavit showing a correct account of the amount due to the plaintiff and remaining unpaid by the Clark Bridge Company," is not sustained by the record; from which it appears that this notice was given on the 14th day of March, 1883, and the work was not terminated on the bridges until April, 1883.
The sub-contractor was not obliged to wait until the work was finished, or terminated otherwise, before he gave his notice. He was entitled under the amended law to serve his notice at any time after the labor was performed and the materials furnished before the expiration of twenty days from the completion of the building or other improvement, or the day the work was otherwise terminated.
The questions involved in this case have been the subject of examination and decision in this court in several recent cases.
The first cases decided here were The Roanoke Land and Im provement Company v. Karn & Hickson, and Same v. Snead & Winston, decided at Wytheville at the last June term, and reported in 80 Va., p. 589.
In a late case this section was again construed by this court, in which it was held that, it is plain from the language thus employed, that the intention of the legislature was to authorize notice to be given after the materials have been furnished by the sub-contractor, and to prescribe a limitation within which the essential affidavit showing a correct account due to the sub-contractor shall be furnished, namely, twenty days after the completion of the work, and no longer. In other words, the sub-contractor may give notice as soon as the materials are furnished, and may, at the same time, if he pleases, furnish the required affidavit, or at any time thereafter, provided the same is furnished within twenty days after the work is completed. If he delays furnishing the affidavit until after the expiration of that time from the completion of the work, then his right to avail himself of the benefit of the fifth section of the statute is gone.
This construction is not less favorable to the owner than that contended for by the company, as it apprises him in advance of the completion of the work of the claim of the sub-contractor, and certainly the language of the statute admits of no other reasonable construction.
See the opinion of Lewis, P., in the case of the Shenandoah Valley Railroad Company v. Miller, decided during the last term of this court, at Staunton (80 Va. 521), and cases cited. The defendant in error has strictly complied with the statute in the prosecution of his claim against the plaintiff in error, and we see no error in the judgment complained of, and the same must be affirmed.
JUDGMENT AFFIRMED.