From Casetext: Smarter Legal Research

N.J. Power Light Co. v. Mabee

Supreme Court of New Jersey
Feb 3, 1964
41 N.J. 439 (N.J. 1964)

Summary

concluding the condition and age of the pole prior to the date of the collision were not relevant when computing the cost of replacement

Summary of this case from Jersey Cent. Power & Light Co. v. Pontecorvo

Opinion

Argued December 16, 1963 —

Decided February 3, 1964.

Appeal from Superior Court, Appellate Division.

Mr. Charles A. Sweeney argued the cause for plaintiff-appellant and cross-respondent ( Messrs. James Wyckoff, attorneys).

Mr. Robert P. Hanley argued the cause for defendants-respondents and cross-appellants ( Messrs. Eagan, O'Donnell, Hanley Clifford, attorneys). Messrs. Lloyd, Horn, Megargee Steedle filed a brief on behalf of Atlantic City Electric Company, Jersey Central Power and Light Company, New Jersey Bell Telephone Company, and Public Service Electric and Gas Company, amici curiae ( Mr. Henry P. Megargee, Jr., of counsel).


The opinion of the court was delivered


Defendants' automobile struck a pole which was part of an electric circuit. The pole had to be replaced. The sole issue is the measure of damages. Plaintiff sought $1,317.94, the sum actually expended, while defendants contended they should be held for only part of that cost, to wit, $708.29. The trial court sitting without a jury fixed the damages at $850. Both sides appealed and we certified the matter before argument in the Appellate Division.

Plaintiff urges the pole is a part of a circuit and the measure of damages should be the diminution of the value of the whole circuit (depreciated cost of $147,540.65), as to which the cost of repairs is appropriate evidence. Parisi v. Friedman, 134 N.J.L. 273 ( E. A. 1946); Rempfer v. Deerfield Packing Corp., 4 N.J. 135 (1950). Defendants, however, urge the pole is a distinct item; that it was 20 years old when it was destroyed; and that the life expectancy of a new pole being 36 years, plaintiff should receive (1) the amount of overtime pay which the emergency required and (2) four-ninths of all other expenditures, thereby to reflect only the loss of the remaining life of the pole.

Each side thus draws upon well known concepts in the field of damages. As we said in 525 Main Street Corp. v. Eagle Roofing Co., Inc., 34 N.J. 251 , 255 (1961), the sundry rules for measuring damages are subordinate to the ultimate aim of making good the injury done or loss suffered and hence "The answer rests in good sense rather than in a mechanical application of a single formula."

It is not feasible to prove the value of the whole circuit before and after the accident and of course no such evidence was offered. Both sides necessarily started with the cost of repairs. The need for the work done is not disputed. It is not suggested that any lesser expenditure would have sufficed to make good the damage done. Rather defendants argue that the work thus necessarily done served not only to make good the damage inflicted but also to confer upon plaintiff a further benefit for which there should be an appropriate reduction.

It seems to us that the true issue is whether the replacement of the pole did more than make plaintiff whole and whether, if it did, it would be just to make the victim of the wrong contribute so much of the cost as would reflect that further benefit.

If the life of every pole were 36 years and if it were clear that each pole would be replaced at the end of that period, defendants could well urge that a new pole clearly conferred a benefit beyond the amount of the damage done. The difficulty is that there is no discernible life expectancy of an individual pole and that although the period of 36 years is used for accounting purposes, the pole that was destroyed might well have served for a much longer period and the new pole may last for but a few years. Moreover, because of changes in circumstances or in technology, it cannot be known whether the pole would ever have been replaced. In short, at least upon the record before us, we cannot say with reasonable assurance that the installation of a new pole did more than remedy the wrong done. An injured party should not be required to lay out money, as defendants' approach would require, upon a questionable assumption that one day its worth will be recaptured.

The judgment is reversed and the matter remanded with directions to enter judgment for the plaintiff in the sum of $1,317.94.

For modification — Chief Justice WEINTRAUB, and Justices JACOBS, FRANCIS, PROCTOR, HALL, SCHETTINO and HANEMAN — 7.

Opposed — None.


Summaries of

N.J. Power Light Co. v. Mabee

Supreme Court of New Jersey
Feb 3, 1964
41 N.J. 439 (N.J. 1964)

concluding the condition and age of the pole prior to the date of the collision were not relevant when computing the cost of replacement

Summary of this case from Jersey Cent. Power & Light Co. v. Pontecorvo

In New Jersey Power Light Co. v. Mabee, 41 N.J. 439, 197 A.2d 194 (1964), the court took the position that the power company should recover the full cost of replacement without deduction for depreciation at all.

Summary of this case from In re the Appeal of AMP Inc.

In N.J. Power Light Co. v. Mabee, 41 N.J. 439, 441, 197 A.2d 194 (1964), the court stated: "[T]he sundry rules for measuring damages are subordinate to the ultimate aim of making good the injury done or loss suffered and hence `The answer rests in good sense rather than in a mechanical application of a single formula.'"

Summary of this case from Kansas Power Light Co. v. Thatcher

In New Jersey Power Light Co. v. Mabee, 41 N. J. 439 (197 A.2d 194) (1964), the power and light company, as here, was required to replace a pole hit by an automobile.

Summary of this case from Horton v. Ga. Power Co.

In New Jersey Power Light Co. v. Mabee, 41 N.J. 439, 197 A.2d 194 (1964), our highest court recognized that the proper measure of damages "rests in good sense rather than in a mechanical application of a single formula."

Summary of this case from Hyland v. Borras
Case details for

N.J. Power Light Co. v. Mabee

Case Details

Full title:NEW JERSEY POWER LIGHT CO., A CORPORATION OF THE STATE OF NEW JERSEY…

Court:Supreme Court of New Jersey

Date published: Feb 3, 1964

Citations

41 N.J. 439 (N.J. 1964)
197 A.2d 194

Citing Cases

Puget Power v. Strong

In light of this dilemma, we believe the onus properly lies with the plaintiff, not the defendant. Accord,…

Portland General Electric Co. v. Taber

Nevertheless, it has engendered a substantial division of opinion in other jurisdictions. That disagreement…