From Casetext: Smarter Legal Research

New Jersey Steel Iron Co. v. Robinson

Appellate Division of the Supreme Court of New York, First Department
Jul 1, 1903
85 App. Div. 512 (N.Y. App. Div. 1903)

Opinion

July Term, 1903.

H.B. Closson, for the appellant.

J. Orlando Harrison, for the respondents Barr, Thaw and Fraser.

James W. Gerard, for the respondents The American National Bank and Kinney.


This action is brought to foreclose a mechanic's lien filed by the plaintiff. The defendant Kinney is the owner of the premises; the defendant Andrew J. Robinson was the general contractor, and the plaintiff and the other defendants sub-contractors under him. The defendant Robinson made default in the performance of his contract with the defendant owner, and made a general assignment for the benefit of creditors. The owner thereafter completed the contract, pursuant to the provisions thereof authorizing him so to do, and upon completion a considerable sum of money became due and payable to the contractor under the terms of the contract, it having cost the owner much less to complete the building than the sum stipulated therein to be paid. This fund amounted, at the time of the trial of this action, to the sum of $70,761.90, out of which the liens of the respective parties have been adjudged to be paid so far as the same is found sufficient. The judgment entered upon the report of the referee determines that the plaintiff has a valid lien upon the fund for $37,077.25; that the other lienors are prior in point of time to the plaintiff's lien, and are entitled to be paid therefrom $37,877.41. Costs amounting to the sum of $4,852.49 are awarded to the respective parties in different amounts, and are made payable from the fund. The sum allowed as the lien of Thaw, Barr and Fraser is $16,575 and costs. Deducting the amount of the liens superior to the plaintiff's which are charged upon the fund, including the costs awarded and to be deducted therefrom, leaves a deficiency for the payment of the plaintiff's lien in the sum of $9,135.23. The defendant the American Exchange National Bank is the assignee of an undivided interest to the extent of $5,000 of the lien of Barr, Thaw and Fraser. Its rights in the premises are dependent upon the validity of the lien of such sub-contractors. The plaintiff's attack is upon that part of the judgment which determines that Barr, Thaw and Fraser have a lien for the amount adjudged, and also upon the allowance of costs, as between it and the defendant Kinney.

The appellant contends that the notice of lien filed by Barr, Thaw and Fraser is insufficient under the statute, and being so insufficient no lien upon the fund was acquired in their favor or in favor of their assignee as against this plaintiff. It is the settled law that to entitle a claimant under the Mechanics' Lien Law to the benefit of the statute, the notice of lien must comply substantially with all of its requirements, and if there is not such compliance no lien is acquired. ( McKinney v. White, 15 App. Div. 423; affd., 162 N.Y. 601.) This decision was rendered in construction of chapter 342 of the Laws of 1885. This lien law was revised in 1897; but, as stated by the revisers, no attempt was made to make any radical changes in the existing statute, the purpose being to retain all of the material features of the act in the revision. (Report Stat. Rev. Com. 1897 [22 Assem. Doc. (1897) pp. 381, 398]; Cumming Gilbert's Lien Laws of N.Y. pp. XXV, 73, note to Lien Law, § 9.) An examination of the provisions of the act of 1885 shows that while there was a different arrangement, all of the substantive parts of that act are found present in the revision of 1897. In section 4 of the act of 1885, the notice was required to be in writing and filed in the office of the clerk of the county where the property was situated, and was required to contain: "The names and residences of the claimants, the nature and amount of the labor and service performed, or the materials furnished or to be furnished, with the name of the owner, lessee, general assignee or person in possession of the premises against whose interest a lien is claimed; the name of the person or persons, firm or firms, corporation or association by whom he was employed, or to whom he furnished or is about to furnish such materials, or whether all the work for which the claim is made has been actually performed or furnished, and if not, how much of it, and also a description of the property." Under chapter 418 of the Laws of 1897 (Lien Law), the contents of the notice are prescribed in section 9, which is divided into subdivisions, subdivisions 4 and 5 of which only are material to the present question. They read as follows: "4. The labor performed or to be performed, or materials furnished or to be furnished and the agreed price or value thereof. 5. The amount unpaid to the lienor for such labor or materials." It is evident that this is a mere rearrangement of the subject-matter of the statute and does not in any respect change it in substance. A change of phraseology does not have the effect of requiring a different construction. ( May v. Bermel, 20 App. Div. 53.) So far, therefore, as the notice is concerned, it still remains the rule that there must be substantial compliance with the statute in order to effect a valid lien. ( Mahley v. German Bank, 174 N.Y. 499.)

The notice of Barr, Thaw and Fraser is claimed to be defective in the statement as to the work and labor performed and materials furnished, the amount and value thereof and the amount which was therein claimed to be due and unpaid for such work, labor and materials. The notice in this respect reads: "(4) The labor performed or to be performed is the cutting and setting of all the cut limestone for the building on the premises; and the materials furnished or to be furnished is the stone so to be cut and set, and the agreed price or value of such labor and materials is Forty-four thousand seven hundred dollars; there has also been furnished extra work and materials at agreed prices amounting to $1,543.00. (5) The amount unpaid to the lienors for such labor and materials is Forty-three thousand two hundred and forty-three dollars." The criticism upon this notice is that it does not state either the labor performed or the materials furnished, nor state the agreed price or the value of the labor or the materials furnished, nor of the labor to be performed or materials to be furnished, nor the agreed price or value of the labor to be performed and materials to be furnished, nor the amount paid for the labor or materials furnished, nor the amount unpaid for the labor or materials to be furnished. Each of these matters is stated in the alternative and, therefore, it is claimed that it is not an affirmation of either the one thing or the other; in other words, that a statement of the matters required to be stated in the notice in the alternative is not a statement of any facts, or of the facts as required by the statute. It is evident that the person who prepared this notice followed the literal language of the statute, and made the statements in the alternative form of all of the particular things which the statute requires, and omitted to state the particular matter which the statute provides should be stated in application of the facts out of which arises the lien. In the construction of similar statutes it has been held that an alternative statement is defective for the reason that it states neither the one fact nor the other, and in effect operates as an exclusion of the statement of any fact. Such rule was applied in respect to matters required to be stated in an application for an attachment, where the alternative statement was held to be bad. ( Cronin v. Crooks, 143 N.Y. 352.) The same rule was held by this court to be applicable to a mechanic's lien. ( Bradley Currier Co. v. Pacheteau, 71 App. Div. 148.) The decision in this case was reversed upon appeal ( 175 N.Y. 492) without opinion, but the memorandum handed down shows upon its face that the Court of Appeals did not disagree with the views entertained by this court in respect to this matter. This court had reversed the judgment of the Special Term and dismissed the complaint. The Court of Appeals reversed this order, and modified the judgment of the Special Term so as to award a personal judgment in favor of the person claiming a lien, based upon the provisions of section 3412 of the Code of Civil Procedure. By virtue of this provision the lienor, if he failed for any reason to establish a valid lien, but did establish that a sum was due to him, which he might recover in an action upon contract, became entitled to a personal judgment against the party to the action who was liable therefor. It necessarily follows from this determination that the Court of Appeals held the lien to be invalid, and as the defect related to the imperfect notice, the Court of Appeals must be held to have sustained in that respect the views which obtained in this court. While it is true that the law requires a liberal construction of the Lien Law in giving force and effect to the lien (Laws of 1897, chap. 418, § 22), yet in order to accomplish this result there must be facts stated which substantially comply with the statute, and from which it is made to appear that they fall within the provisions authorizing the lien. If by any liberal, that is, fair, construction, the statement can be construed to show the performance of the work, or the furnishing of materials, either or both, effect will be given thereto. But where the statement is so made that it neither includes one nor the other, and each statement excludes the other, there is nothing to which a liberal construction can attach, because there is no statement of any fact bringing the case within the terms of the statute. The statement contained in this notice, within the above authorities, so far as it relates to the work, labor and materials furnished under the contract, is clearly defective, and, therefore, no lien was acquired.

The notice, so far as the extra work is concerned, complies with the statute, as the statement relating to it is that there has been furnished such extra work and materials. To this extent the notice is good and should be upheld, were it not for another defect and reason why the lien in this case is void as to the plaintiff. The statement in the lien is that the labor performed or to be performed and the agreed price of such labor or materials is $44,700, and for extra work $1,543, and that the amount unpaid to the lienors for labor and materials is $43,243. The lienors intended and, except for a mistake to be hereinafter noticed, did state therein, assuming that there was a statement of fact, that the contract price was the first named sum and the extra work the given sum, and that the amount unpaid was $43,243. The lienors thus stated the full amount of the contract price, if they stated anything, as being the amount and value of the work, labor and materials furnished, and that the sum which they were entitled to receive was nearly that sum. In point of fact the reasonable value of the work and labor furnished under the contract did not equal such sum, but was only the sum of $15,000. The claim of the amount due was, therefore, grossly exaggerated, the excess over the true amount being $28,243. For the item of extra work, which was stated to be $1,543, only $500 had been furnished, an exaggeration of something over two-thirds. The learned referee found that the amount unpaid under the contract price was $44,300 and of extra work $1,521, and that the amount due and unpaid instead of being $43,243 was $42,821. With these corrections made the exaggeration in excess of the amount which the lienors were entitled to recover is $27,321.

The force of these facts was sought to be avoided by a finding that at the time of filing the notice of lien the price of the materials furnished could not be separated without an agreement between the parties thereto. It is evident that this finding has no effect whatever in relieving the lienors from their exaggerated statement. The amount and value of the materials which had been furnished and the work and labor bestowed upon the building could have been approximated at that time as well as at any other. Manifestly the statement that the lienors were entitled to have and receive by virtue of their lien the grossly exaggerated sum stated in the notice must have been known to them. It is not possible that they could then honestly have made the statement that $42,000 and upwards was due and owing to them when the fact was that, including the work performed under the contract and the extra work and labor, only the sum of $16,000 was owing. In Aeschlimann v. Presbyterian Hospital ( 165 N.Y. 296) MARTIN, J., after reviewing the authorities upon this subject, states: "We think the rule so generally established is a proper one and should be adopted by this court. There certainly can be no hardship in requiring a claimant to avoid intentionally and willfully making an exaggerated claim which he knows not to exist. The requirement that he shall truthfully state his claim is in no way unjust to the claimant, but it is pre-eminently just to the owner, to other claimants or lienors and to those who are engaged in administering the Lien Law. We are, therefore, of the opinion that the trial court having found that the plaintiffs `enormously exaggerated' their claim and intentionally and by pretense of a fictitious contract sought to enforce and establish a false and fabricated demand, was justified in holding that the plaintiffs had thereby forfeited their right to recover any judgment against the sureties upon the bond in question." While it is true that in that case there were elements of actual and affirmative fraud upon the part of the contractors which find no place in this case and with which the lienors cannot be charged, yet it is evident that they willfully, and, therefore, intentionally grossly exaggerated their lien, and thereby worked or might have worked an injury to subsequent lienors and other parties interested in the fund. Such gross exaggeration must be regarded in law as willfully made, as it must have been known to the lienors to be untrue at the time when the statement was made. Thereby there was a violation of the terms of the statute which requires (Laws of 1897, chap. 418, § 9, subd. 7) that the claim shall be truthfully stated, and it is in no way unjust to the claimants to insist upon compliance with the statute in this respect.

The case of Ringle v. Wallis Iron Works ( 149 N.Y. 439), which holds in effect that a mistake in stating the amount which the lienor is entitled to enforce does not invalidate the lien, in nowise conflicts with this view. That case recognized that a willful and intentional false statement might invalidate the lien. The two cases last cited indicate the state of the law upon this subject, and we think lay down the rule that where no mistake of fact exists the lienor is not justified in exaggerating his claim, and that where the exaggeration is gross, willful and intentional the lienor should be held to forfeit his lien. There is no hardship in such requirement, nor does such rule operate to defeat an honest claimant who has made a mistake.

It follows from these views that the judgment in favor of Barr, Thaw and Fraser cannot be upheld and that the judgment of the American Exchange National Bank, as it is dependent thereon, must also fall as to the plaintiff in the action. The judgment in this respect, however, is not invalid as to any party except the plaintiff, as no one else appeals, nor is it made to appear that any other party is aggrieved. It follows that the plaintiff becomes entitled to a judgment as against Barr, Thaw and Fraser and the American Exchange National Bank, declaring its lien to be superior to such lienors, including the costs awarded to it in the judgment. The fund is sufficient to pay the amount of the other lienors, aside from Barr, Thaw and Fraser and the American Exchange National Bank, with costs. It is, therefore, unnecessary to determine the plaintiff's equitable right to costs as against the defendant owner.

It follows that the judgment should be modified by declaring the lien of the plaintiff superior to the lien of Barr, Thaw and Fraser and the American Exchange National Bank, such amount with all costs awarded to the plaintiff to be paid from the fund before the last-named parties shall be entitled to receive anything; and as modified the judgment should be affirmed, with costs to the appellant.

VAN BRUNT, P.J., O'BRIEN, INGRAHAM and McLAUGHLIN, JJ., concurred.

Judgment modified as directed in opinion, and as modified affirmed, with costs to appellant.


Summaries of

New Jersey Steel Iron Co. v. Robinson

Appellate Division of the Supreme Court of New York, First Department
Jul 1, 1903
85 App. Div. 512 (N.Y. App. Div. 1903)
Case details for

New Jersey Steel Iron Co. v. Robinson

Case Details

Full title:THE NEW JERSEY STEEL AND IRON COMPANY, Appellant, v . ANDREW J. ROBINSON…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jul 1, 1903

Citations

85 App. Div. 512 (N.Y. App. Div. 1903)
83 N.Y.S. 450

Citing Cases

Schwartz v. Lewis

But when it purports to state the date of furnishing the last item of work and material, if an unintentional…

Redd Bros. v. Todd

Appellant failed to file a just and true account, by intentionally omitting all credits for the purpose of…