From Casetext: Smarter Legal Research

Nelson v. Mayor, Etc., of New York

Court of Appeals of the State of New York
Jan 20, 1892
131 N.Y. 4 (N.Y. 1892)

Opinion

Argued December 23, 1891

Decided January 20, 1892

Louis Marshall for appellant.

D.J. Dean for respondent.




This action was brought in October, 1873, to recover the balance claimed by the plaintiff to be due to him for vitrified salt glazed stoneware drain and sewer pipe and invert blocks, delivered by him to the city in the years 1871 and 1872, under a contract with the city made in 1871. He has been paid seventy per cent of the contract price for the materials delivered, and the claim he now makes is for the remaining thirty per cent retained by the terms of the contract, to wit, the sum of $54,550.60 and the interest thereon from December 12, 1872.

The action has been twice tried. On the first trial the complaint was dismissed on the ground that the contract under which the plaintiff claimed was, under the circumstances appearing, not authorized by law. The judgment for the defendant was affirmed at the General Term (5 Hun, 190), but upon appeal to this court it was reversed. ( 63 N.Y. 535.) Upon the second trial no question was made that the contract was legal in form and was authorized by law. Nor was any question made that all the materials for which the plaintiff claimed payment had been delivered. The only defense made to his claim was that the contract under which the materials had been delivered was procured by him through fraud and collusion with some of the officers and agents of the city, and that, therefore, it was void and not binding upon the city. All the oral evidence upon the trial was introduced upon this defense, and no other matter was submitted to the jury. Upon the defense of fraud, the jury found a verdict in favor of the defendant, upon which judgment was entered. That judgment has been assailed by the learned counsel for the plaintiff with much elaboration and ability, and yet we do not think he has been successful in pointing out any error for which it should be reversed.

The evidence of fraud and collusion in the making and execution of the contract was sufficient to sustain the verdict. The department of public works advertised for proposals to furnish the pipes and invert blocks. The advertisement was first published on the 8th day of April, 1871, and by its terms the letting of the contract took place on the eighteenth day of the same month. The advertisement specified the size, quantity and quality of the materials to be furnished, and among the specifications was the following: "The commissioner of public works reserves the right to increase or diminish the gross quantity, or the quantity of each kind, to an amount not exceeding thirty per cent of the gross amount of contract, but the time of delivery, however, to be extended or diminished in the ratio of the increase or diminution;" and this clause was embodied in the contract. If every bidder for the contract put fair, honest, bona fide prices upon each kind of pipe to be furnished, this clause could work no mischief or injustice. But it gave opportunity — just such opportunity as could be desired by a person who wished, in collusion with the officers of the department of public works, to put in what is called an unbalanced bid — to perpetrate a fraud upon the city. No one not in fraudulent complicity with the city officials could, with this clause in operation, safely put in an unbalanced bid. If he bid a very low price for some of the pipes and a very high price for others, the city officials might require him to furnish a large quantity of pipes which he had offered to furnish for much less than their value, and very little or none of those which he had offered to furnish for more than their value, and thus he might be financially ruined, unless his pecuniary resources were very great. But by increasing the quantity of pipes which the bidder had agreed to furnish for a price largely in excess of their value, the city officials could make the fortune of the bidder. It is thus clear that no man of prudence could, under such circumstances, dare to put in an unbalanced bid, and thus place his fortune at the mercy of the city officials. If this clause had simply permitted the city officials to increase or diminish any kind of pipe only thirty per cent, the facilities for fraud would not have been so great. But with rare cunning it was so framed that any one kind of pipe could be increased by thirty per cent of the gross amount of the whole contract, and thus an enormous increase of the kind of pipe most profitable to the contractor was made possible.

There was another clause in the proposals, harmless if honesty was the purpose in the making and performance of the contract, but well calculated to favor a contractor who was in complicity with city officials, and that provided that the contractor should "commence the delivery of said pipe and appurtenances at such time and in such manner and proportion as shall be designated in said agreement hereunto annexed, and complete the same within ninety days next thereafter."

Thus the way was prepared, and the fraudulent scheme, as the jury must have found, was concocted.

Now, what happened? There were two bidders for the contract, Mr. McMann and the plaintiff. The prices bid by the plaintiff on many kinds of pipe were much below, and on many kinds much above, the prices of McMann, and the result was that for the estimated quantities of pipes and invert blocks contained in the proposals at the prices bid respectively by the two bidders, the plaintiff's bid was $55,454.50 lower than his competitor's, and the contract was, therefore, awarded to him. What further happened? In the advertised proposals there were forty-three different quantities and kinds of pipes mentioned, and for each of these the bidders named a price, and under the clause above quoted twenty-six of these kinds were entirely omitted, none having been required or furnished; and in every case where none was furnished, the bid of the plaintiff was lower than that of McMann; and in no case was there an entire omission of pipe where the price of the plaintiff was greater than that of McMann; and in the remaining seventeen kinds of pipe, where plaintiff's prices were higher than those of McMann, the quantities were, in all but four trifling exceptions, largely increased. The result was that, measuring by the prices bid, the aggregate contract price of the pipes and invert blocks delivered by the plaintiff under the contract was $70,947.03 more than the same materials would have cost if the contract had been awarded to McMann upon the prices bid by him. It is difficult to account for these remarkable results by any theory of chance or accident, and it is hard to disbelieve that they were not due to a fraudulent scheme previously devised.

There is another significant fact. The specifications as advertised required two thousand invert blocks, and for these the plaintiff bid $3.50 a piece, although he was at the time offering to sell them in different parts of the country for $2.60, with at least ten per cent discount, and McMann's bid for them was only sixty cents a piece; and the quantity of these blocks required and actually delivered was 20,127, an increase of more than ten fold; and yet at the same time when the department of public works advertised for bids for the two thousand invert blocks, it advertised for proposals to construct sewers which required over 11,000, and these sewer contracts were let at the same time as the contract for materials let to the plaintiff. This evidence tended to show that when the city officials inserted in the specifications for the materials, 2,000 invert blocks, they knew the city would need much more, and thus there was a fine opportunity for the operation of plaintiff's unbalanced bid.

This is not all. The evidence tends to show that for the first payment made to the plaintiff under his contract, the city officials gave him an estimate for a much larger quantity of materials delivered under his contract than he had actually delivered, and that thus he was enabled to obtain from the city several thousand dollars more than was at that time his due. By the terms of the letting and of plaintiff's contract, he was required to deliver all the materials in about one hundred days, and yet he was permitted to take many days in excess of that number.

It cannot, we think, be said that all these facts are equally consistent with honesty as with fraud. They seem to point unmistakably to fraud and collusion. It does not seem possible that such a contract could be so made and executed with honest and fair motives. The plaintiff introduced no evidence on the trial to parry or weaken the force of this evidence. He, knowing more of the facts than any other living witness, did not even offer his own evidence to put an innocent face upon facts which bear such an ugly aspect. Fraud need not be proved by direct evidence. It is generally disguised and covered up and must be brought to light by the proof of circumstances not equally consistent with innocence. Here we cannot doubt that the evidence was sufficient to warrant the verdict of the jury. ( Matter of Anderson, 109 N.Y. 554.)

It was not incumbent upon the defendant to show precisely how or when the fraud was concocted, or what particular city officials were implicated in it. It was enough to show that the contract with whomsoever made was the creature of fraud.

Thus this contract was not in any proper sense, as required by the law, let to the lowest bidder, and being fraudulent and void, it imposed no obligation upon the city.

But the plaintiff attempts to answer the charge of fraud in three ways: (1) He says that the city waived the fraud and ratified the contract by receiving the materials delivered under the contract, and thus accepting performance thereof. As matter of law the city did none of these things. It could only act through its agents, and they could bind it only when acting for it within the boundaries prescribed by law. As they could not bind it originally by such a fraudulent contract, they could not bind it by subsequently in any manner ratifying it. They could not bind it either by making or ratifying a fraudulent contract. The city officials, in fraudulent complicity with the plaintiff, certainly could not ratify the contract; and the acts of honest officials in recognition of the contract, while ignorant of the fraud, would not ratify it. And further, no city official like the comptroller, or even the mayor, could ratify the contract who did not have power to bind the city by such a contract; and no contract could be made binding by ratification which could not at the time of the ratification be made. The law required such contracts to be let after advertisement to the lowest bidder. The letting of this contract was merely a formal, not a real, compliance with the law, and it was so affected with fraud that the city did not become bound thereby. No officer of the city could thereafter make such a contract absolutely binding upon the city by ratification or otherwise, except in the form prescribed by law. But there is a further answer to this claim of ratification, and that is that no such claim appears to have been made upon the trial, and the trial judge was not asked to rule upon such a claim or to charge the jury in reference thereto, and he did not submit and was not requested to submit the facts in reference thereto to the jury. The sole question of fact submitted to the jury was that of fraud, and the judge in substance charged the jury that if they found the alleged fraud and collusion in the origin of the contract, they must render their verdict for the defendant; but that if they found the contract was honestly made the plaintiff was entitled to recover; and to this there was no exception; and thus the plaintiff cannot now complain that the case was given to the jury upon an erroneous view of the law. (2) It is said that the city has had the benefit of these materials and, therefore, ought to pay for them. How much ought it to pay? Certainly not the contract prices placed upon them by the plaintiff in his unbalanced, fraudulent bid. If the plaintiff claims he should be paid their value, the answer is that he did not upon the trial put forward such a claim. There he claimed to recover upon his contract, and he gave no evidence whatever of the value of the materials, and he furnished no basis whatever for any recovery by him of the value. On the contrary, the evidence tended to show that he had already been paid more than a fair value for the materials delivered by him. He had received, at least, $15,000 more than the materials were fairly worth, if their value be measured by the prices named in the bid of McMann; and it further appears that he was probably paid nearly the full value of the materials delivered by him measuring their value by the prices for which he sold the same materials in the market to other purchasers. (3) He further says that the city has been deprived of the defense of fraud by the action of the board of audit, consisting of the comptroller, the commissioner of public works and the president of the department of public parks, created by the act, chapter 9, of the Laws of 1872. That board was authorized to audit claims against the city, and the plaintiff presented to them claims against the city amounting to the sum of $55,327.69, and they were audited and allowed for that sum and subsequently paid by the city. The plaintiff claims that that sum was seventy per cent of three bills, amounting to $79,039.35 for materials furnished under this contract, and that the remaining thirty per cent, $23,711.66, remains unpaid, and is part of the sum sought to be recovered in this action. It does not appear what documents, papers or proof were before the board. It is inferable that the three bills were before them. It does not appear what determination or adjudication they made. All the plaintiff claimed was $55,327.69, and that sum they audited and allowed, and so far as we know they made no other determination. The counsel for the plaintiff claims that the audit must have the same effect as a judgment rendered by a court, and hence that the contract must be deemed to be valid and free from fraud, and that the city is thereby estopped from denying its liability for plaintiff's entire claim. It is undoubtedly true that if the plaintiff had sued the city for the three bills and had recovered the amount audited in an action, there would have been a conclusive adjudication of the validity of the entire claim. But can a mere audit by a board simply clothed with the power to audit have such conclusive effect? Our attention is called to no authority giving the audit such effect, and we are confident there is none. The law of 1872 provides for nothing akin to a regular judicial proceeding. It does not provide for the examination of witnesses and there is none of the ordinary machinery of a court of justice. To give to the audit of such a board the far reaching effect of a regular judgment would be both novel and mischievous. Such an audit when the auditors are not fraudulently imposed on and act within their jurisdiction, is undoubtedly conclusive until in some way reversed as to the liability of the city for the amount audited, and it cannot be collaterally overhauled or attacked. But it is conclusive for nothing more, and this is true of every audit made by county supervisors and town boards of auditors. When the auditors honestly allow a claim, acting within their jurisdiction, and no fraud has been practiced upon them in procuring the allowance the liability of the municipality is fixed, and the claim is no longer subject to dispute. But the audit does nothing but fix the amount of the claim, simply that and nothing more. Then, too, the audit of this board may have proceeded upon the theory that there was at least the sum audited due the plaintiff for the materials delivered, and it cannot be known from this record that they meant to decide more, and they certainly had no authority to decide more, and the audit does not establish that the plaintiff is entitled to the amount claimed in this action, or even the sum of $23,711.66, the balance now claimed upon the three bills presented. So we think the trial judge did not err in his charge to the jury that they "had nothing to do with what the board of audit did."

As before stated, the defendant gave evidence tending to show that when the plaintiff received his first payment under his contract he had not furnished all the materials certified for him by the city officers, and hence that his payment was greater than he was then entitled to. The evidence on the part of the city upon this point was mainly that of two employes of the plaintiff who had charge of the deliveries of the materials to the city and who kept a record of the deliveries in books kept by them. They testified that the entries in the books were made at the time of the deliveries; that they were correct, and that they had no independent memory of the items, and thus foundation was laid for the introduction of the books. It is now claimed that the accuracy of the books was not sufficiently proved, and that it was error to receive them in evidence. They were objected to on the part of the plaintiff on the following grounds: "(1) That by the evidence of the defendant's own witness they are not the books of the plaintiff. (2) Because the books contain entries of other matters besides the deliveries to the city. (3) That the evidence is immaterial inasmuch as defendant's counsel has already admitted that the plaintiff has delivered to the defendant all the pipe for which he claims to recover." The trial judge overruled the objection and admitted so much of the books in evidence as related to deliveries to the city. No other objections were made to the books at any stage of the trial, and clearly none of these were valid.

The defendant's counsel also put in evidence statements made up from these books by one of the witnesses who had made most of the entries in them, showing the quantities of materials delivered as appeared from them, which statements also showed the quantities of materials in the bill of the plaintiff which was claimed to be overestimated. These statements were intended to show by contrast that plaintiff's first bill was inaccurate and greatly exaggerated. They were objected to by plaintiff's counsel as incompetent, immaterial and irrelevant, and on no other ground. The counsel has made a most elaborate argument to show that it was error to receive these statements. It may be that when all the evidence is carefully analyzed they appear to be less weighty as evidence than claimed by the defendant, and probably they may be entitled to but little weight. But they were evidence for what they were worth. No defect in the proof relative to them was pointed out. Their accuracy seems to have been assumed. They had some tendency to sustain the allegation of the defendant that the first bill presented by the plaintiff under his contract was fraudulent, collusive or very carelessly and recklessly made. The judge submitted this evidence to the jury with some very pertinent and significant remarks, to which no exception was taken on the part of the plaintiff. No claim whatever was made that there was not sufficient evidence upon this point for submission to the jury. There was, therefore, no error in the reception of these books and statements, and there is now certainly no valid ground of complaint as to them on the part of the plaintiff.

No other exceptions require attention, and our conclusion is that the judgment should be affirmed.

All concur.

Judgment affirmed.


Summaries of

Nelson v. Mayor, Etc., of New York

Court of Appeals of the State of New York
Jan 20, 1892
131 N.Y. 4 (N.Y. 1892)
Case details for

Nelson v. Mayor, Etc., of New York

Case Details

Full title:WILLIAM NELSON, JR., Appellant, v . THE MAYOR, ALDERMEN AND COMMONALTY OF…

Court:Court of Appeals of the State of New York

Date published: Jan 20, 1892

Citations

131 N.Y. 4 (N.Y. 1892)
42 N.Y. St. Rptr. 492
29 N.E. 814

Citing Cases

Bone v. Hayes

562; Ernst v. Crosby, 140 N.Y. 364, [ 35 N.E. 603].) This principle applies with, perhaps, greater force…

Wilmerding v. O'Brien

It is "enough to show that the contract with whomsoever made was the creature of fraud." ( Nelson v. Mayor,…