Opinion
No. 14–143.
2014-06-4
Tenant appeals from a final judgment of the Civil Court of the City of New York, New York County (Andrea Masley, J.), entered August 28, 2013, which, upon an order granting landlord's motion for summary judgment, awarded landlord possession and a recovery of rent arrears in the principal sum of $234,299.97, in a nonpayment summary proceeding.
Present: SCHOENFELD, J.P., SHULMAN, LING–COHAN, JJ. PER CURIAM.
Final judgment (Andrea Masley, J.), entered August 28, 2013, affirmed, with $25 costs, for the reasons stated by Andrea Masley, J. at Civil Court.
Landlord's alleged failure to substantially complete the work set forth on the “punch list” made part of the governing commercial lease agreement is no defense to the landlord's rent claim. It is undisputed that tenant did not terminate the lease within six months of the lease date, a contingency which the parties agreed would be the “sole and exclusive remedy” in the event landlord failed to “substantially complete” the agreed upon work ( see Diplomat Props., L.P. v. Komar Five Assoc., LLC, 72 AD3d 596 [2010]; Foot Locker Stores, Inc. v. Pyramid Mgt. Group, Inc., 45 AD3d 1447 [2007] ). “Absent some violation of law or transgression of a strong public policy, the parties to a contract are basically free to make whatever agreement they wish, no matter how unwise it might appear to a third party” ( Rowe v. Great Atlantic & Pac. Tea Co., Inc., 46 N.Y.2d 62, 67–68 [1978] ).
I concur.