Judgment affirmed, with costs. Held, that the parties contemplated the execution of a formal contract which was not done; no opinion.

Concur: HISCOCK, Ch. J., CARDOZO, POUND, McLAUGHLIN, CRANE, ANDREWS and LEHMAN, JJ.


Summaries of

Moody Engineering Co. v. Board of Education of Union Free School District No. 1

Court of Appeals of the State of New York
Jul 5, 1924
144 N.E. 920 (N.Y. 1924)
Case details for

Moody Engineering Co. v. Board of Education of Union Free School District No. 1

Case Details

Full title:MOODY ENGINEERING COMPANY, Appellant, v . BOARD OF EDUCATION OF UNION FREE…

Court:Court of Appeals of the State of New York

Date published: Jul 5, 1924

Citations

144 N.E. 920 (N.Y. 1924)
144 N.E. 920

Citing Cases

Hughes v. City of Buffalo

This position is supported by well-considered legal authorities. (Page Cont. p. 72; Clark New York Law of…

Harvey v. General Cable Corp.

(2 Clark on New York Law of Contracts, § 1029, p. 1605; Miller v. Schloss, 218 N.Y. 400, 406.) The evidence…