Opinion
No. 217.
Argued April 10, 11, 1900. Decided May 21, 1900.
The city of Rochester invited proposals from contractors for two separate contracts for work to be done for the improvement of its water works. Among others who bid were the petitioners, the Moffett, etc. Company, who put in bids for each. Owing to causes which are set forth in full in the opinion of the court, some serious mistakes were made in the figures in their proposals, whereby the compensation that they would receive if their bids were accepted and the work performed by them would be diminished many thousand dollars. When the bids were opened by the city government their bids were the first opened, and as they were read aloud their engineer noticed the errors and called attention to them and stated what the figures were intended to be and should be. The statutes of New York provided that "neither the principal nor sureties on any bid or bond shall have the right to withdraw or cancel the same until the board shall have let the contract for which such bid is made and the same shall have been duly executed." The city government rejected one of their bids and accepted the other, and called for its performance at the prices stated in the bid. The company declined to enter into a contract for the performance of the work at that price; and, claiming that the city threatened to enforce the bond give with the proposals, brought suit praying for a reformation of the proposals to conform to the asserted intention in making them and their execution as reformed, or their rescission; and for an injunction against the officers of the city, restraining them from declaring the complainant in default, and from forfeiting or enforcing its bond. Judgment was rendered in the Circuit Court in the company's favor, which was reversed in the Circuit Court of Appeals. The case was then brought here on certiorari. Held: (1) That there was no doubt of the mistake on the part of the company; (2) That there was a prompt declaration of it as soon as it was discovered; (3) That when this was done the transaction had not reached the degree of a contract. The party alleging a mistake must show exactly in what it consists and the correction that should be made. The evidence must be such as to leave no reasonable doubt on the mind of the court as to either of these points. The mistake must be mutual and common to both parties to the instrument. It must appear that both have done what neither intended. A mistake on one side may be a ground for rescinding, but not for reforming a contract. Where the minds of the parties have not met there is no contract, and hence none to be rectified. Hearne v. Marine Ins. Co., 20 Wall. 488, cited on these points and approved.
"OFFICE OF THE EXECUTIVE BOARD, "ROCHESTER, N.Y., January 12, 1893."By Mr. Schroth:"Resolved, That the proposal of the Moffett, Hodgkins Clarke Company, of New York, N.Y., submitted on December 23, 1892, for the construction of a riveted steel pipe conduit 38 inches in diameter, and all the required appurtenances thereto, commencing at the north end of the contemplated masonry conduit near the village of Hemlock Lake, Livingston County, N.Y., and terminating at Mt. Hope reservoir, in the city of Rochester, N.Y., and by route `B' as described in the notice of letting for said work, be, and the same is hereby, accepted, and that said work be and hereby is awarded to said Moffett, Hodgkins Clarke Company."By Mr. Schroth:"Resolved, That the Moffett, Hodgkins Clarke Company, of New York, be and they are herewith required to attend at the office of this board, along with the sureties to be offered by said company, on or before Thursday, January 19, 1893, and to execute at that time the contract for the performance of the work of constructing a riveted steel pipe conduit 38 inches in diameter, and all the required appurtenances thereto, by route `B,' from the north end of the contemplated masonry conduit near the village of Hemlock Lake, Livingston County, N.Y., to Mt. Hope reservoir in the city of Rochester, N.Y., and that the failure of such attendance and execution will be regarded as an abandonment of intention on the part of said Moffett, Hodgkins Clarke Company to perform said work."By Mr. Schroth:"Resolved, That the clerk be, and he is hereby, directed to cause immediate legal service of notice of award of contract to be made on the Moffett, Hodgkins Clarke Company, of New York, N.Y., in accordance with the foregoing resolutions."The answer admitted the allegations of the bill in regard to the powers of the executive board, and that it determined to enter into a contract set forth in the bill; that it prepared specifications and gave notice as stated, and required bond to accompany proposals conditioned as alleged; that the complainant had such bond executed and annexed the same to its proposal of contract No. 2.The answer alleged that the defendants did not know and could not set forth their belief or otherwise whether complainant was a corporation or employed engineers, or what their duties were, or that the officers of the complainant had to delegate important duties to subordinates, or whether its agents could procure firms to contract and make proposals before the 15th of December, 1892; or whether its engineer was nervous or made mistakes as alleged or in the way alleged, or the prices bid were inadequate, or that complainant was led to believe by the defendants that contracts Nos. 1 and 2 would be let jointly and not separately, or its bid declared informal and cannot be received, or that its engineer when the bids were opened notified the board that the prices which had been read for item "d" of route "B" in contract No. 2 of fifty cents per cubic yard was a clerical error.The answer then proceeded in substance as follows:The notice for bids required that all bids should state the prices for every separate item of work named in the proposals, should be plainly stated and distinctly written in ink, both in words and figures, in the proposed blanks left therefor; that the complainant's engineer received all communications requested by him from the executive board and its engineer, and all the plans and specifications and information were at the complainant's command before its submission of the proposals for the contract.On account of the treacherous subsoil disclosed by borings along route "B" in contract No. 2, the latter route would be the least expensive, and the prices complained of by complainant were reasonable and fair values for the work set forth, and it was denied that clerical errors were contained in the proposals, or that they were less than the average bids by competitive bidders, and averred that the amounts were knowingly and intentionally inserted to make complainant's bid what is known as an "unbalanced bid," to wit, in which the contractor will give a "low price for one kind of work or materials in the same contract with the hope that the quantity of work and materials for which a low price is bid will be reduced, while the quality of materials or work for which a high price is bid will be increased, thus making up on the high price bid sufficient to give the contractor a large profit upon the whole work."The complainant bid upon some items in contract No. 2 in excess of a reasonable price, thus making its bid for route "B," contract No. 2, an unbalanced bid, enabling complainant to realize upon the completion of the work far in excess of the amount based upon the estimates of defendant's engineer.In pursuance of the notice to contractors the board awarded to W.H. Jones Sons contract No. 1, they being the lowest bidders, and to complainant contract No. 2, it being the lowest bidder, but this was not done to take undue and unconscionable advantage of the manner in which the proposals were made under contracts Nos. 1 and 2, and presented to the board, nor did the board act in bad faith and award the contract for the purpose of taking advantage of the alleged clerical errors.On the 12th of December, 1892, by the resolution marked schedule "B," the board duly and legally awarded to the complainant the contract for the construction of the conduit of route "B," in contract No. 2, and the complainant was notified to attend at the office of the board with its sureties to execute the proposed contract, and the complainant "without sufficient reason or excuse, and with intent to defraud said defendants, did refuse and neglect to enter into said contract, and said defendants deny that said complainant is entitled to the relief, or any part thereof, in the said complaint demanded, and they respectfully submit that the injunction awarded against them by this honorable court on the 15th day of February, 1893, ought to be dissolved, and that the said bill ought to be dismissed, with costs."Evidence was submitted on the issues, including the specifications, proposals and bond.A decree was entered adjudging the proposals of the complainant for the conduit on line or route "B" to be "rescinded, canceled and declared null, void and of no effect," and ordering an injunction to be issued restraining the city and its officers from declaring complainant in default with respect to its bids and proposals, "or from declaring forfeited the bond executed by and on behalf of said complainant, and accompanying the aforesaid bids and proposals, or from in any manner suing upon or attempting to enforce or collect the said bond."Commenting on the facts the learned trial judge said:"The question in this controversy is plain and simple: Shall the complainant be held to an erroneous bid by which it agreed to do certain work for the city of Rochester for $63,800 less than was intended? The work related to the construction of a conduit to convey the water of Hemlock Lake to the city. By a mistake of Mr. Burlingame, its engineer, the complainant bid fifty cents per cubic yard for earth excavation in open trenches when it intended to bid seventy cents, and one dollar and fifty cents for earth excavation in tunnel when it intended to bid fifteen dollars."The proof of these mistakes is clear, explicit and undisputed. As soon as the item proposing to do the work for fifty cents, as aforesaid, was read at the meeting of the executive board, and before any action was taken thereon, Mr. Burlingame stated that it was an error, and that complainant intended to bid for route B the same as for route A, viz., seventy cents."There is some testimony of a negative character that this prompt repudiation of the bid did not take place, but the great weight of testimony is in favor of the complainant. Had the errors been corrected the complainant's bid would still have been $200,000 below the next lowest bid. On route A the complainant's bid was $903,324. The mistakes all occurred on route B, and yet route A was selected, and the work awarded to other bidders for $1,123,920, or $220,596 more than the complainant's proposal."Upon the principal issue there is no disputed question of fact. Counsel for the defendants, though not admitting the mistakes, which are the basis of the action, do not dispute them. The oral argument proceeded upon the theory that the mistakes were made precisely as alleged."In order that no injustice may be done to the defendants, their position in this regard is stated in the language of their brief, as follows:"`We admit that the evidence of the complainant shows that Mr. Burlingame entered in his proposal sheets certain figures and numbers different from those which he intended to make, and that the defendants have no evidence to contradict his testimony.'" 82 F. 255.On appeal to the Circuit Court of Appeals the decree was reversed, with instructions to the Circuit Court to dismiss the bill. 33 C. C.A. 319. The case is here on writ of certiorari.Other facts are stated in the opinion.
Mr. Louis Marshall for petitioner.
Mr. Porter M. French for respondents.
Both of the lower courts agree that there was a mistake. The Circuit Court said that the proof of it was "clear, explicit and undisputed." The Circuit Court of Appeals, while expressing no dissent as to the fact, said "that one of the alleged mistakes, that in respect to the tunnel excavation, was not a mistake in any legal sense, but was a negligent omission arising from an inadequate calculation of the cost of the work."
We do not think the negligence was sufficient to preclude a claim for relief if the mistakes justified it.
This court said in Hearne v. Marine Insurance Company, 20 Wall. 488, 490, by Mr. Justice Swayne:
"The reformation of written contracts for fraud or mistake is an ordinary head of equity jurisdiction. The rules which govern the exercise of this power are founded in good sense and are well settled. Where the agreement as reduced to writing omits or contains terms or stipulations contrary to the common intention of the parties, the instrument will be corrected so as to make it conform to their real intent. The parties will be placed as they would have stood if the mistake had not occurred.
"The party alleging the mistake must show exactly in what it consists and the correction that should be made. The evidence must be such as to leave no reasonable doubt upon the mind of the court as to either of these points. The mistake must be mutual, and common to both parties to the instrument. It must appear that both have done what neither intended. A mistake on one side may be a ground for rescinding, but not for reforming, a contract. Where the minds of the parties have not met there is no contract, and hence none to be rectified."
The last two propositions may be claimed to be pertinent to the case at bar, even though the transactions between the parties be considered as a completed contract.
There was no doubt of the mistake, and there was a prompt declaration of it as soon as it was discovered and before the city had done anything to alter its condition. Indeed, according to the testimony of one witness, the clerk of the board before the mistake was declared by complainant's engineer expressed the thought that fifty cents per cubic yard for earth excavation was too low, "and there was some discussion about it at the time, but Mr. Aldridge (he was chairman of the board) said he (the clerk) might as well go on and read it, as the bid was informal." The reading proceeded, and subsequently the board let the work on contract No. 1 to Jones Son, and accepted complainant's proposals containing the mistakes for the work on line "B," contract No. 2, although complainant protested that there was a mistake in the price of earth excavation and also in tunnel excavation. This was inequitable, even though it was impelled by what was supposed to be the commands of the charter. It offered or forced complainant the alternative of taking the contract at an unremunerative price, or the payment of $90,000 as liquidated damages. We do not think such course was the command of the statute or the board's duty.
The rule between individuals is that until a proposal be accepted it may be withdrawn, and if this principle cannot be applied in the pending case, on account of the charter of the city, there is certainly nothing in the charter which forbids or excuses the existence of the necessary elements of a contract.
The charter of the city provides that "neither the principal nor sureties on any bid or bond shall have the right to withdraw or cancel the same until the board shall have let the contract for which such bid is made, and the same shall be duly executed." A perfectly proper provision, but as was said by the learned Circuit Court:
"The complainant is not endeavoring `to withdraw or cancel a bid or bond. The bill proceeds upon the theory that the bid upon which the defendants acted was not the complainant's bid; that the complainant was no more responsible for it than if it had been the result of agraphia or the mistake of a copyist or printer. In other words, that the proposal read at the meeting of the board was one which the complainant never intended to make, and that the minds of the parties never met upon a contract based thereon. If the defendants are correct in their contention there is absolutely no redress for a bidder for public work, no matter how aggravated or palpable his blunder. The moment his proposal is opened by the executive board he is held as in a grasp of steel. There is no remedy, no escape. If, through an error of his clerk, he has agreed to do work worth a million dollars for ten dollars, he must be held to the strict letter of his contract, while equity stands by with folded hands and sees him driven to bankruptcy. The defendant's position admits of no compromise, no exception, no middle ground."
These remarks are so apposite and just it is difficult to add to them. The transactions had not reached the degree of a contract — a proposal and acceptance. Nor was the bid withdrawn or cancelled against the provision of the charter. A clerical error was discovered in it and declared, and no question of the error was then made or of the good faith of complainant.
It is true it is now urged by counsel that there was no mistake, but that the prices were deliberately and consciously inserted for the purpose of making an "unbalanced bid," in which low prices in some items are compensated by high prices in others. The Circuit Court and the Circuit Court of Appeals found against this view, and this court usually accepts such concurrence as conclusive.
The Circuit Court of Appeals, however, found that while there was a clerical error for the earth excavation in contract No. 2, route "B," that the alleged mistake in tunnel excavation "was not a mistake in any legal sense, but was a negligent omission arising from an inadequate calculation of the cost of the work." Further, the court said:
"It is also manifest that the complainant did not intend to give the board an opportunity to correct the mistakes and award the contract on the corrected basis. There was no color of foundation for the assertion that the proposals were to be treated as a single bid for contracts No. 1 and No. 2, and that both contracts must be awarded to the complainant or neither. The position thus taken by the complainant was well calculated to excite distrust on the part of the board and induce its members to believe that the alleged mistakes were an afterthought, conceived when the complainant had become convinced by studying the proposals of its competitors that it could not profitably carry out the contract on the terms proposed."
We are unable to concur in either of these conclusions. The mistake in tunnel excavations arose from inadvertently making the cost of one item — mere earth digging and putting the dirt into cars — the total cost without making "any allowance for any work preparatory to it or connected with it," to quote the testimony of complainant's engineer. And it seems impossible for the error to have escaped the notice of the board. Other contractors charged for the same work $12 and $15.
The conclusion that the complainant did not intend to give the board an opportunity to correct the mistakes is based on a letter addressed to the board, in which it claimed unity in the contracts and bids, and demanding that "the contract in its entirety for both sections of the work be awarded to us at the corrected price, or that we may be allowed to withdraw our proposal and have our bid returned to us."
But before the time expressed in the resolutions of the executive board of the city for the complainant to appear and execute a contract, or it would be regarded as abandoning its intention to do so, complainant filed its bill in this case, and appealed to a court of equity to determine its rights and obligations.
On filing the bill and supporting affidavits, on the 18th of January, 1893, an order was issued temporarily restraining the officers of the city from declaring the complainant in default or from forfeiting or suing on its bond, until a motion for an injunction pendente lite could be heard. Subsequently, after hearing and argument, an injunction pendente lite was issued.
Prior to its issuing, but after the restraining order, the executive board accepted the bid of Whitmore, Rauber Vicinus, and entered into a contract with them for the construction for the riveted steel pipe conduit, thirty-eight inches in diameter, for route "A," for eight thousand feet. That is on a different route and claimed to be the subject of a different contract from that awarded to the complainant.
This action made a reformation of the proposals impossible — made any action of the Circuit Court impossible, except to annul the proposals or dismiss the bill and subject the complainant to a suit on its bond. If the decree was narrowed to this relief it was the fault of the city, not of the complainant. Whatever its prior claims and pretensions may have been, by submitting itself to a court of equity complainant submitted itself to abide by what that court should decree, and the alternative of a reformation of the proposals was certainly not their execution unreformed.
By letting the contract to Whitmore, Rauber Vicinus, the city, in effect, evaded the restraining order, forestalled the action of the Circuit Court, and prevented the reformation of the proposals; and by preventing that justified the decree which was entered.
The decree of the Circuit Court of Appeals is reversed and that of the Circuit Court is
Affirmed.