From Casetext: Smarter Legal Research

Mesa Sand v. Landfill

Colorado Court of Appeals. Division II
Feb 18, 1988
759 P.2d 757 (Colo. App. 1988)

Summary

In Mesa Sand, the indemnity provision stated, "Mesa and Landfill agree to indemnify and hold the other harmless from any and all claims, damages, suits, liabilities, costs and expenses (including but not limited to attorneys fees and expenses of investigation) which the other party might suffer as a result of the activities or negligence of the other party."

Summary of this case from Arapahoe Co. Water Waste. Pub. Imp. Dist. v. HDR

Opinion

No. 84CA1387

Decided February 18, 1988. Rehearing Denied Mesa Sand March 17, 1988. Rehearing Denied Landfill April 7, 1988. Certiorari Granted Landfill August 1, 1988 (88SC190).

Appeal from the District Court of Boulder County Honorable Morris W. Sandstead, Judge

Martin, Knapple, Humphrey Tharp, Joel C. Maguire, for Plaintiff-Appellee, Cross-Appellant and Defendant on Counterclaim.

Parcel, Mauro, Hultin Spaanstra, Paul F. Hultin, Marcus L. Squarrell, for Defendant-Appellant, Cross-Appellee.


Defendant and third-party plaintiff, Landfill, Inc. (Landfill), the operator of a landfill operation, appeals the judgment of the trial court awarding damages to plaintiff, Mesa Sand and Gravel Company (Mesa). Mesa is engaged in the business of excavation and sale of earthen material. Mesa cross-appeals the judgment of the trial court. We affirm.

In September 1975, Mesa and Landfill entered into a contractual agreement whereby Landfill would excavate a landfill site and Mesa would remove the excavated material. The agreement specifically incorporated by reference a plan prepared by consulting engineers. The plan delineated procedures for conducting a cooperative, dual excavation and landfill operation. Both parties were contractually obligated to follow the plan. Pursuant to the agreement, Mesa also agreed to pay Landfill ten cents per ton for earthen material removed by Mesa.

In 1979, Mesa became aware that Landfill was not following the consulting engineer's plan and, therefore, was not complying with the terms of the 1975 agreement. After several notices from Mesa to Landfill regarding the latter's deviation from the plan, Mesa brought this action. Landfill counterclaimed, also alleging breach of contract. Both parties appeal the judgment entered.

I.

Mesa and Landfill both challenge the trial court's computation and award of damages. We find no error in the trial court's award.

The general measure of damages for breach of contract cases is that sum which places the nondefaulting party in the position the party would have enjoyed had the breach not occurred. Smith v. Hoyer, 697 P.2d 761 (Colo.App. 1984). When evidence in the record establishes values both higher and lower than that found by the trial court, the finding is presumed correct. See Denver v. Minshall, 109 Colo. 31, 121 P.2d 667 (1942); Hayden v. Board of County Commissioners, 41 Colo. App. 102, 580 P.2d 830 (1978). Conclusions drawn from the evidence will not be disturbed on appeal unless they are so erroneous as to find no support in the record. Carlson v. Garrison, 689 P.2d 735 (Colo.App. 1984).

Here, the record reflects that at least four methods of considering the complex factual issues and calculating damages were presented to the trial court, including the opinions and evaluations of several expert witnesses. The court arrived at a damage figure consistent with the report of one of the expert witnesses. Therefore, we find ample support in the record for the trial court's findings and conclusions regarding the amount of damages to be awarded Mesa.

Mesa argues, however, that the amount awarded was insufficient as a matter of law. Our examination of the record reveals that the trial court was correct in concluding that not all of Landfill's deviations from the engineering plan constituted a breach of the agreement. Therefore, Landfill's breach was designated by the court as consisting only of those "unreasonable deviations" from the plan. The trial court correctly concluded that Mesa cannot be compensated for each and every deviation.

II.

Mesa next contends that the trial court erred in failing to award interest on the judgment pursuant to § 5-12-102, C.R.S. (1987 Cum. Supp.). We disagree.

Section 5-12-102, C.R.S. (1987 Cum. Supp.) provides in pertinent part:

"[C]reditors shall receive interest as follows:

(a) When money or property has been wrongfully withheld, interest shall be an amount which fully recognizes the gain or benefit realized by the person withholding such money or property from the date of wrongful withholding to the date of payment or to the date judgment is entered, whichever first occurs . . . ." (emphasis added)

Thus, statutory interest can only be awarded when a wrongdoer benefits or realizes a gain from his actions. Here, the record shows that Mesa had a right of access to the property and to excavate it itself. Further, Landfill did not gain or benefit by failing to excavate the materials in accordance with the agreement. Landfill's benefit in the operation arose at the time it filled the excavations with refuse, and not before. Therefore, under the plain language of the statute, there was no wrongful withholding. Accordingly, Mesa is entitled only to post-judgment interest, not prejudgment interest. See Asphalt Paving Co. v. United States Fidelity Guaranty Co., 671 P.2d 1013 (Colo.App. 1983); cf. Isbill Associates, Inc. v. City County of Denver, 666 P.2d 1117 (Colo.App. 1983).

III.

Mesa's final contention is that the trial court erred in failing to award it attorney fees, costs, and expenses based on a provision in the 1975 agreement. We disagree.

Section 1-9 of the Mesa-Landfill agreement states:

"Mesa and Landfill agree to indemnify and hold the other harmless from any and all claims, damages, suits, liabilities, costs and expenses (including but not limited to attorney's fees and expenses of investigation) which the other party might suffer as a result of the activities or negligence of the other party."

If the language used in a contract is plain, its meaning clear, and no absurdity is involved, the contract must be enforced as written. Bennett v. Price, 692 P.2d 1138 (Colo.App. 1984). The intent of the parties to a contract is to be determined primarily from the language of the document itself, and if the agreement of the parties consists of a written instrument, the determination of the effect of the instrument is a matter of law. International Technical Instruments, Inc. v. Engineering Measurements Co., 678 P.2d 558 (Colo.App. 1983).

Here, the first clause of Section 1-9 serves to identify the section as a standard statement of mutual indemnification. As such, the plain language of the clause indicates that Mesa and Landfill agreed to indemnify each other from potential liabilities owed to third parties. Contrary to Mesa's position, the section does not contemplate an award of attorney fees, costs, and expenses, for suits between the parties to the contract. To allow the term "activities" to include the act of performing the contract itself is to strain the plain meaning of the agreement and distort the parties' intentions. We conclude that, as a matter of law, Section 1-9 of the contract does not permit an award of attorney fees, costs, and expenses in this breach of contract action.

IV.

On its cross-appeal, Landfill first contends that the trial court erred in interpreting the Mesa-Landfill agreement to impose duties upon Landfill that did not exist in the agreement. We disagree.

Although we are not bound by the trial court's interpretation of the contract, Gilpin Investment Co. v. Blake, 712 P.2d 1051 (Colo.App. 1985), we conclude that the trial court correctly determined the rights and duties of the parties under the agreement. Therefore, we find no merit in Landfill's arguments that Landfill was not bound by the terms set forth in the engineer's plan.

V.

Landfill next contends that the trial court erred in awarding damages to Mesa as Mesa failed to prove that it had a right to excavate and sell the materials after December 1978. We disagree.

Issues not raised in the trial court may not be raised for the first time on appeal. Matthews v. Tri-County Water Conservancy District, 200 Colo. 202, 613 P.2d 889 (1980); Mohawk Green Apartments v. Kramer, 709 P.2d 955 (Colo.App. 1985).

Although this contention goes to the issue of damages, the record shows that no attack was made on Mesa's property rights prior to appeal. We therefore decline to address it.

VI.

Landfill's final contention is that the trial court failed to consider in its damage calculations Mesa's duty to mitigate its damages. Again, we disagree.

Mitigation is an affirmative defense which defendant has the burden of establishing. Combined Communications Corp. v. Bedford Motors, Inc., 702 P.2d 281 (Colo.App. 1985). Landfill did not plead or prove Mesa's failure to mitigate its damages, and therefore, the trial court did not err in failing to consider mitigation in its award.

Judgment affirmed.

JUDGE PLANK concurs.

JUDGE TURSI concurs in part and dissents in part.


Summaries of

Mesa Sand v. Landfill

Colorado Court of Appeals. Division II
Feb 18, 1988
759 P.2d 757 (Colo. App. 1988)

In Mesa Sand, the indemnity provision stated, "Mesa and Landfill agree to indemnify and hold the other harmless from any and all claims, damages, suits, liabilities, costs and expenses (including but not limited to attorneys fees and expenses of investigation) which the other party might suffer as a result of the activities or negligence of the other party."

Summary of this case from Arapahoe Co. Water Waste. Pub. Imp. Dist. v. HDR
Case details for

Mesa Sand v. Landfill

Case Details

Full title:Mesa Sand and Gravel Co., Plaintiff-Appellee, Cross-Appellant, v…

Court:Colorado Court of Appeals. Division II

Date published: Feb 18, 1988

Citations

759 P.2d 757 (Colo. App. 1988)

Citing Cases

Mesa Sand v. Landfill

Both parties appealed. A divided panel of the court of appeals affirmed the district court on all issues in…

Arapahoe Co. Water Waste. Pub. Imp. Dist. v. HDR

Where the plain language of the contract indicates the parties intended to indemnify each other from…