From Casetext: Smarter Legal Research

Mendelsohn v. City of New York

Supreme Court, Appellate Division, First Department, New York.
Nov 17, 2011
89 A.D.3d 569 (N.Y. App. Div. 2011)

Opinion

2011-11-17

Allan B. MENDELSOHN, etc., Plaintiff–Appellant, v. CITY OF NEW YORK (19th Precinct), Defendant–Respondent.

The McDonough Law Firm, LLP, New Rochelle (Howard S. Jacobowitz of counsel), for appellant. Michael A. Cardozo, Corporation Counsel, New York (Jane L. Gordon of counsel), for respondent.


The McDonough Law Firm, LLP, New Rochelle (Howard S. Jacobowitz of counsel), for appellant. Michael A. Cardozo, Corporation Counsel, New York (Jane L. Gordon of counsel), for respondent.

TOM, J.P., SAXE, MOSKOWITZ, DeGRASSE, ABDUS–SALAAM, JJ.

Order, Supreme Court, New York County (Geoffrey D. Wright, J.), entered on or about February 9, 2011, which, to the extent appealed from, granted defendant City of New York's cross motion for summary judgment dismissing the complaint as time-barred, unanimously affirmed, without costs.

The court correctly determined that, pursuant to CPLR 213(2), this action for breach of a construction contract had to be commenced within six years of substantial completion of the work and was time-barred ( see Phillips Constr. Co. v. City of New York, 61 N.Y.2d 949, 951, 475 N.Y.S.2d 244, 463 N.E.2d 585 [1984]; 645 First Ave. Manhattan Co. v. Silhouette Drywall Sys., 212 A.D.2d 394, 622 N.Y.S.2d 46 [1995] ). The City submitted a letter dated May 21, 1992 showing that the work was substantially complete on April 9, 1992, more than six years before plaintiff commenced this action.

Plaintiff failed to raise an issue of fact as to when the work was substantially complete. To the contrary, plaintiff's own document, a contractor's certificate seeking partial payment dated May 7, 1992, indicates that 98% of the work was complete as of that date. The June 29, 1992 and August 5, 1992 memoranda, and the October 1, 1993 and November 22, 1993 letters, merely show that work incidental to the electrical work on the building, namely a fire alarm system and items on a punch list, was incomplete ( see Phillips Constr., 61 N.Y.2d at 951, 475 N.Y.S.2d 244, 463 N.E.2d 585).

Additionally, plaintiff's purported claim to recover its guarantee monies pursuant to Article 24 of the contract has not been considered here, as it was not raised below, either in the pleadings or the motion papers and thus, was not preserved for appellate review.

We have considered plaintiff's remaining contentions and find them unavailing.


Summaries of

Mendelsohn v. City of New York

Supreme Court, Appellate Division, First Department, New York.
Nov 17, 2011
89 A.D.3d 569 (N.Y. App. Div. 2011)
Case details for

Mendelsohn v. City of New York

Case Details

Full title:Allan B. MENDELSOHN, etc., Plaintiff–Appellant, v. CITY OF NEW YORK (19th…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Nov 17, 2011

Citations

89 A.D.3d 569 (N.Y. App. Div. 2011)
934 N.Y.S.2d 3
2011 N.Y. Slip Op. 8291

Citing Cases

Rad & D'Aprile Inc. v. Arnell Constr. Corp.

“[I]n construction cases a contractor's claim accrues upon the substantial completion of its work” ( 645…

NexBank, SSB v. Soffer

This argument is akin to trying to recall a bullet fired from a gun because it missed its mark. Plaintiff…