From Casetext: Smarter Legal Research

MCI CONSTRUCTORS, INC. v. HAZEN SAWYER, P.C.

United States District Court, M.D. North Carolina
Mar 9, 2009
1:99CV2, 1:02CV396 (M.D.N.C. Mar. 9, 2009)

Opinion

1:99CV2, 1:02CV396.

March 9, 2009


MEMORANDUM OPINION AND ORDER


On June 17, 2008, Plaintiff, MCI Constructors LLC, moved to vacate, and, in the alternative, remand an arbitration award in which Plaintiff was ordered to pay Defendant, the City of Greensboro, North Carolina, in the amount of $14,939,004. (1:99-cv-2, Docs. 535, 541); (1:02-cv-396, Docs. 68, 70.) On July 10, 2008, Plaintiff's performance bond guarantor, Counter Defendant, National Union Fire Insurance Company of Pittsburgh, also moved to vacate the award. (Doc. 548.) For the reasons set forth herein, Plaintiff and Counter Defendant's motions to vacate are DENIED and Plaintiff's motion to remand is DENIED.

The docket numbers noted in the remainder of this memorandum opinion refer to documents associated with case number 1:99-cv-2, not case number 1:02-cv-396, although the same pleadings were filed in both cases.

I. Facts

The general background of this case has been set forth in the previous memorandum opinions associated with this matter dated March 24, 2000, October 6, 2000, January 18, 2001, September 6, 2001, and November 1, 2002.

The Honorable William L. Osteen, Sr. presided over this case until September, 2007. Subsequently, Judge Osteen, Sr. retired and the case was ultimately assigned to the undersigned court.

On November 25, 2005, the court denied Plaintiff, MCI Constructors LLC (hereinafter "Plaintiff" or "MCI") and Defendant's, the City of Greensboro, North Carolina (hereinafter "Defendant" or "City"), cross-motions for summary judgment. (Doc. 462.) On December 5, 2005, a pretrial conference was held in preparation for a trial date of February 6, 2006.

On January 26, 2006, City, MCI, and MCI's performance bond guarantor, National Union Fire Insurance Company of Pittsburgh (hereinafter "Counter Defendant" or "National Union"), advised the court that they had entered a binding arbitration agreement (hereinafter the "Arbitration Agreement") to resolve all outstanding issues between them arising from a construction contract (hereinafter the "Contract") dispute. (Doc. 490.) The Arbitration Agreement entered by the parties provided, in pertinent part, as follows:

1. The "[a]rbitration will be final and binding," and "will be pursuant to the Federal Arbitration Act" (hereinafter the "FAA"). (Pl.'s Mot. to Vacate (Liability Award) Ex. A (Doc. 497-2) at 1.)
2. "Except as provided herein or otherwise agreed, the rules would be standard AAA Complex Commercial or JAMS rules." (Id.)
3. The proceeding "would be bifurcated between liability and damages." (Id. at 1-2.)
4. With regard to the liability phase, "[t]he parties have agreed to substitute you[, the arbitrators,] in the place of Edward Kitchen, who was then City Manager and acted as Referee pursuant to Article 16, and resubmit the Liability Phase issue: was the termination of MCI's performance for cause or convenience?" (Id. at "STIPULATED SUBMISSION TO PANEL OF ARBITRATORS" ¶ 9.)
5. Concerning the damages phase, "[r]egardless of which party wins at the [Liability] Phase, there would be a separate hearing on damages. . . . If the City has prevailed at the [Liability] Phase, the second issue will be what amount should either partly [sic] recover under Articles 15.2.4, 17.5 and 18 of the Contract."

(Id. at 2-3.)

The parties subsequently filed a joint motion to stay the matter pending the conclusion of the arbitration proceeding for which they intended to participate. (Doc. 490.) The court granted the parties' motion on February 7, 2006. (Order dated 2/7/2006 (Doc. 494).)

After the court stayed the action, the arbitration proceeding was conducted before a three-member panel of arbitrators (hereinafter the "Panel"). Following a finding of liability in favor of City (hereinafter the "Liability Award"), the Panel considered the issue of damages. During the course of the damages phase, both parties presented their arguments and theories to the Panel. MCI argued that, taking into consideration the balance of $9,667,357 it was due under the Contract, it was entitled to recover approximately $450,000 from City. (See Decl. of William Cary Ex. 57 (Doc. 525-6) at 103.) City, on the other hand, contended that it was entitled to a recovery of approximately $17,000,000 from MCI. (See Decl. of William Cary Ex. 56 (Doc. 525-5) at Tab 17.) In light of the evidence and arguments presented by the parties, the Panel found that City was entitled to recover $14,939,004 in damages from MCI (hereinafter the "Damages Award"). (Def.'s Notice of Arbitration Award Ex. A (Doc. 503-2) at 2.)

Several documents referred to throughout this opinion are before the court as attachments to a declaration submitted by William Cary, one of City's attorneys. National Union has neither objected to Mr. Cary's declaration nor the exhibits that accompany it. Although MCI has objected to Mr. Cary's declaration, it does not object to the court's consideration of the exhibits attached thereto. (Pl.'s Mot. to Strike Declaration of William Cary (Doc. 533) at 1 n. 1 ("[T]he documents themselves need not be stricken at this time. . . .").) Accordingly, the court has relied on Exhibits 50, 56, 57 and 61 of Mr. Cary's declaration, as the parties do not object to the introduction of these documents and the documents do not appear elsewhere in the record.

Plus interest at the federal judgment rate from the date of the City Manager's damages decision. (Def.'s Notice of Arbitration Award Ex. A (Doc. 503-2) at 2.)

Neither the Liability Award nor the Damages Award outlined the Panel's reasoning in coming to its conclusions on the liability and damages issues. The Damages Award did however state that "[a]ny claims or issues of either party not expressly awarded herein, are hereby denied." (Id.)

On April 24, 2008, MCI sent an electronic message to the Panel. (Decl. of William Cary Ex. 50 (Doc. 525-8).) MCI requested that the Panel modify the Damages Award. (Id.) MCI contended that the Panel failed to deduct the Contract balance from the amount the Panel awarded to City. (Id.) Further, MCI objected to the form of the Damages Award. (Id.) MCI maintained that the Panel was required to provide a reasoned award that addressed the disposition of all the claims submitted by the parties to the Panel. (Id.)

On May 7, 2008, the Panel responded to MCI's electronic message. (Decl. of William Cary Ex. 61 (Doc. 525-10).) The Panel denied MCI's request for the Panel to modify the Damages Award due to a purported computational error. (Id. at 2.) The Panel stated that "[t]he Damages Award did not contain any errors and the arbiters have already decided all claims submitted to them." (Id.)

Similarly, the Panel "denied" MCI's objection to the form of the Damages Award. (Id.) The Panel stated that pursuant to the term in the Arbitration Agreement that provided that the arbitration would be governed by "standard AAA Complex Commercial or JAMS rules," it opted to proceed under the Commercial Rules. (Id.) The Panel noted that the Commercial Rules do not require arbitrators to provide reasoned awards unless the parties make a written request for a reasoned award prior to the appointment of the arbitrators. (Id.) The Panel reasoned that since none of the parties requested a reasoned award prior to its appointment, it was not obligated to provide a reasoned award and the form of the Damages Award was not erroneous. (Id.)

The Panel also noted that the (unreasoned) form of the Damages Award mirrored the form of the Liability Award, to which MCI did not object. (Decl. of William Cary Ex. 61 (Doc. 525-10) at 2.)

II. Legal Standard

III. Discussion

Patten v. Signator Ins. Agency441 F.3d 230234 Genus Credit Mgmt. Corp. v. Jones citing Upshur Coals Corp. v. United Mine Workers of Am., Dist. 31933 F.2d 225229Choice Hotels Int'l, Inc. v. S.M. Prop. Mgmt., LLC519 F.3d 200207 A. Motions to Vacate

The FAA provides that:

(a) In any of the following cases the United States court in and for the district wherein the award was made may make an order vacating the award upon the application of any party to the arbitration —
(1) where the award was procured by corruption, fraud, or undue means;
(2) where there was evident partiality or corruption in the arbitrators, or either of them;
(3) where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced; or
(4) where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.
9 U.S.C. § 10.

MCI and National Union have moved to vacate the Damages Award on the grounds that (1) the Panel applied the wrong body of procedural rules in selecting the form of the Damages Award, (2) the Damages Award did not draw its essence from the Arbitration Agreement and the Contract, (3) the Panel did not make a mutual, final, and definitive award based on the subject matter submitted to them, (4) the Damages Award is unenforceable, and (5) City materially breached the Arbitration Agreement. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 4-20); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).)

1. Procedural Rules and the Form of the Award

Three bodies of procedural rules are referred to in the Arbitration Agreement entered by the parties. The Arbitration Agreement provides that "[e]xcept as provided herein or otherwise agreed," the arbitration "would be [conducted pursuant to] standard AAA Complex Commercial or JAMS rules." (Pl.'s Mot. to Vacate (Liability Award) Ex. A (Doc. 497-2) at 1.) Another provision in the agreement states that "[i]f MCI prevails at the [Liability] Phase. . . . [t]here will be a complete arbitration utilizing the AAA Rules and Procedures for Large, Complex Construction Disputes on MCI's damages. . . ." (Id. at 3.)

The three potentially applicable sources of procedural rules contained in the Arbitration Agreement have different requirements with regard to whether arbitrators must provide a breakdown of the computations that underlie their awards or must outline the reasoning upon which their awards are based. Under the JAMS Comprehensive Arbitration Rules and Procedures arbitration awards must be reasoned. JAMS Rule 24(h) states that "[t]he Award will consist of a written statement signed by the Arbitrator regarding the disposition of each claim and the relief, if any, as to each claim. Unless all Parties agree otherwise, the Award shall also contain a concise written statement of the reasons for the Award." JAMS Engineering and Construction Arbitration Rules and Procedures, http://www.jamsadr.com/images/PDF/JAMS-comprehensive_arbitration_rules.PDF at 20.

Under the AAA Rules and Procedures for Large, Complex Construction Disputes, awards must be broken down, but generally do not have to be reasoned absent a request from the parties. Construction Rule R-43(b) states that "[t]he arbitrator shall provide a concise, written breakdown of the award. If requested in writing by all parties prior to the appointment of the arbitrator, or if the arbitrator believes it is appropriate to do so, the arbitrator shall provide a written explanation of the award." Construction Industry Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Construction Disputes), http://www.adr.org/sp.asp?id=22004#R43.

In contrast to the JAMS and Construction rules, awards issued pursuant to the AAA Commercial Arbitration Rules do not need to be broken down and are not required to be reasoned unless the parties request a reasoned award before the arbitration proceeding commences. Commercial Rule R-42 states that "[t]he arbitrator need not render a reasoned award unless the parties request such an award in writing prior to appointment of the arbitrator or unless the arbitrator determines that a reasoned award is appropriate." American Arbitration Association Commercial Arbitration Rules and Mediation, http://www.adr.org/sp.asp?id=22440#R42.

In the instant case, City prevailed at the liability phase and none of the parties requested a reasoned Damages Award before the Panel rendered its damages decision. Pursuant to the applicable procedural provision in the Arbitration Agreement, the Panel elected to proceed under the Commercial Rules, rather than the JAMS Rules, and declined to provide its reasoning for the Damages Award. (Decl. of William Cary Ex. 61 (Doc. 525-10) at 2.) On review, MCI and National Union contend that the Damages Award should be vacated because the Panel should have applied the Construction Rules, not the Commercial Rules. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 2-3); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).) In the alternative, MCI argues that the parties did not intend to be bound by the generally applicable procedural rules provision, as evidenced by the provision's inclusion of the words "would be." MCI maintains that in the absence of such an intent to be bound, the Panel was not authorized to select the procedural rules that would apply if City prevailed at the liability phase.

MCI raised this argument for the first time during an oral argument hearing on pending motions held on January 26, 2009.

The court finds that MCI and National Union's arguments are without merit. The Panel's use of the Commercial Rules does not constitute a legal or factual error, let alone a basis for vacatur.

The plain language of the applicable procedural rules provision in the Arbitration Agreement is clear and unambiguous. The Panel could apply one of two bodies of procedural rules, the JAMS Rules or the Commercial Rules, unless MCI prevailed at the liability phase. (See Pl.'s Mot. to Vacate (Liability Award) Ex. A (Doc. 497-2) at 1 ("Except as provided herein or otherwise agreed, the rules would be standard AAA Complex Commercial or JAMS rules." (emphasis added)).) Although the Arbitration Agreement states that the Construction Rules are to be applied if MCI prevails at the liability phase, MCI did not prevail at the liability phase. (See Pl.'s Mot. to Vacate (Liability Award) Ex. A (Doc. 497-2) at 2-3 ("If MCI prevails at the [Liability] Phase . . . [t]here will be a complete arbitration utilizing the AAA Rules and Procedures for Large, Complex Construction Disputes on MCI's damages. . . .") (emphasis added)); (Def.'s Notice of Arbitration Award Ex. A (Doc. 503-2) at 2 (finding that City's termination of MCI's performance was "for cause").) Since there is no "special rules" clause under the provision in the agreement discussing how the arbitration should proceed if City prevailed at the liability phase, as City did, the Panel was correct to rely on the umbrella procedural rules provision in the agreement. In sum, the Panel validly exercised their discretion and did not err in doing exactly what the parties authorized it to do, apply the Commercial Rules.

Moreover, even if the court accepted MCI's factual contentions, vacatur is not appropriate. Even assuming, arguendo, that the Panel misread the Arbitration Agreement and consequently erred in applying the Commercial Rules, an award may not be vacated merely because an arbitrator misread the arbitration agreement. See Patten, 441 F.3d at 235 ("An arbitration award does not fail to draw its essence from the agreement merely because a court concludes that an arbitrator has `misread the contract.'" (internal citations omitted)). Further, even if the court agreed with MCI's argument that there was no binding agreement between the parties as to the procedural rules that were to be applied if City prevailed at the liability phase, contrary to MCI's assertion, the Panel had the authority to select the applicable procedural rules in the absence of an agreement by the parties. Where a "clear and unambiguous" procedural standard has not been set forth in the arbitration agreement, the "arbitrator has the authority and the discretion to follow procedures that he or she deems to be appropriate."Int'l Bhd. of Elec. Workers, AFL-CIO, Local No. 1434 v. E. I. DuPont de Nemours Co., 420 F.Supp. 208, 211 (E.D. Va. 1976);see also Int'l Union, United Mine Workers of Am. v. Marrowbone Dev. Co., 232 F.3d 383, 389 (4th Cir. 2000) ("An arbitrator typically retains broad discretion over procedural matters . . .").

2. Award Drawing Its Essence From the Agreement

At common law, an arbitration agreement may be vacated if it fails to "draw its essence from the contract." Patten, 441 F.3d at 234. However, "[a]n arbitration award does not fail to draw its essence from the agreement merely because a court concludes that an arbitrator has `misread the contract.'" Id. at 235 (quoting Upshur, 933 F.2d at 229). "An arbitration award fails to draw its essence from the agreement only when the result is not rationally inferable from the contract" or "[the] arbitrator based his award on his own personal notions of right and wrong."Id. (internal quotation marks and citations omitted).

In the present case, MCI and National Union argue that the Damages Award does not draw its essence from the Arbitration Agreement and Contract (hereinafter collectively referred to as the "Agreement") because the award did not discuss whether arguments offered by MCI regarding articles nine and eleven of the Contract defeated City's damages claims. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 6-8); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).) In support of this argument, MCI and National Union rely on the Fourth Circuit's holding in Clinchfield Coal Co. v. District 28, United Mine Workers of America that `where the . . . arbitrator fails to discuss critical contract terminology, which terminology might reasonably require an opposite result, the award cannot be considered to draw its essence from the contract.' (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 6-8) (quoting Clinchfield Coal Co. v. District 28, United Mine Workers of Am., 720 F.2d 1365, 1369 (4th Cir. 1983)); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).)

In Hall Street Assoc., L.L.C. v. Mattel, Inc., ___ U.S. ___, 128 S.Ct. 1396, 1403 (2008), the Supreme Court recently held that "§§ 10 and 11 respectively provide the FAA's exclusive grounds for expedited vacatur and modification [of arbitration awards]." (Emphasis added). The Hall Street Court did not however determine whether common law grounds for vacatur, including "manifest disregard" and "essence of the agreement," are permissible bases for vacatur independent of, or as a shorthand for, the grounds for vacating awards that are specified in the FAA. Id. at 1404, 1406 ("parties wanting review of arbitration awards . . . may contemplate enforcement under state statutory law or common law. . . . [H]ere we speak only to the scope of expeditious judicial review under §§ 9, 10, and 11 [of the FAA], deciding nothing about other possible avenues of judicial enforcement of arbitration awards." (emphasis added)). Therefore, assuming, without deciding, that this court could vacate or remand the Damages Award for "failing to draw its essence" from the Agreement, the court finds that MCI has failed to carry its burden of proof.

The court rejects MCI and National Union's "failure to discuss" argument. MCI and National Union's argument rests on the faulty premise that arbitrators are required to provide reasoned awards. Contrary to MCI and National Union's suggestion,

courts generally have held that arbitrators are not required to give their reasons for an award or that the proceedings and record be as complete as a court trial. Arbitrators are not required to disclose the basis upon which the awards are made and courts will not look behind a lump-sum award in an attempt to analyze their reasoning process.
Atlanta-Tomberlin, Inc. v. E. Band of Cherokee Indians, 672 F. Supp. 887, 889 (W.D.N.C. 1987); see also Remmey v. PaineWebber, Inc., 32 F.3d 143, 150-51 (4th Cir. 1994) ("That the arbitrators' accompanying "Case Summary" did not mention all of [the movant's] claims is of no moment here. After all, the Supreme Court has held that arbitrators need not state reasons for reaching a particular result."); United Steelworkers of Am. v. Enter. Wheel Car Corp., 363 U.S. 593, 598 (1960) ("Arbitrators have no obligation to the court to give their reasons for an award."). MCI and National Union could have contracted for reasoned arbitration awards, but they did not. See First Options of Chi. Inc. v. Kaplan, 514 U.S. 983, 943 (1995) ("[A]rbitration is simply a matter of contract between the parties."); United Paperworkers Int'l Union, AFL-CIO v. Misco, Inc., 484 U.S. 29, 39 (1987) ("The parties bargained for arbitration to settle disputes and were free to set the procedural rules for arbitration to follow if they chose."). Furthermore, under the applicable AAA rules, MCI and National Union could have, but did not, request a reasoned award before the arbiters were appointed or contend to the Panel during the arbitration proceeding that the Panel should find that a reasoned award was necessary. MCI and National Union's argument on review, in essence, asks this court to rewrite the Contract. The court declines MCI and National Union's invitation. "[T]he parties [had] a right to make their own contract and it is not the function of this Court to rewrite it or torture the meaning [of the agreement the parties willingly entered]." See Torrington Co. v. Aetna Casualty Sur. Co., 264 S.C. 636, 643, 216 S.E.2d 547, 550 (1975); see also Penn v. Standard Life Ins. Co., 160 N.C. 399, 76 S.E. 262, 263 (1912) ("Courts are not at liberty to rewrite contracts for the parties.").

Additionally, the proposition for which MCI and National Union cite Clinchfield is not persuasive on the facts of this case. The problem that the Fourth Circuit encountered in Clinchfield is not present here. "In Clinchfield, the underlying problem with the arbitrator's decision was that the result seemed impossible to square with certain provisions of the contract; without some discussion of the provisions by the arbitrator, the court was forced to conclude that the arbitral award did not draw its essence from the contract." Keebler Co. v. Truck Drivers, Local 170, 247 F.3d 8, 12-13 (1st Cir. 2001). By contrast, in this case, the Panel's Damages Award can be squared with the Agreement. Just as the court previously found that a reasonable jury could find in favor of City, the Panel's award could plausibly be understood to rest on the reasonable view that MCI and National Union's article nine and eleven arguments did not defeat City's damages claims. (See Mem. Op. Order dated 11/25/2005 (Doc. 462).)

Moreover, the Arbitration Agreement states that "[i]f the City has prevailed at the [Liability] Phase, the second issue will be what amount should either [party] recover under Articles 15.24, 17.5 and 18 of the Contract." (Pl.'s Mot. to Vacate (Liability Award) Ex. A (Doc. 497-2) at 2-3.) Presumably, if the parties intended for the Panel to specify how it arrived at its final damages determination the agreement would state that the issue the Panel must address is what amounts the parties are due under each provision of the contract from which the parties contend they are entitled to relief. Since all the parties asked for was a singular "amount," the court finds, based on a plain reading of the unambiguous language in the agreement, the parties did not intend for the Panel to provide a reasoned Damages Award. The parties received exactly what they contracted for, a single numerical figure specifying the amount of recovery to which City is entitled.

In light of case law stating that reasoned awards are not required and the dissimilarities between the facts in Clinchfield and this case, the court concludes that where an arbitrator was under no obligation to provide a reasoned award, the mere fact that the award does not discuss allegedly critical contract terminology does not by itself constitute a failure of the award to draw its essence from the agreement. See supra Part III.A.2.

The court notes that its interpretation of Clinchfield is consistent with the understanding of the First Circuit Court of Appeals and another district court in the Fourth Circuit. See Keebler Co. v. Truck Drivers, Local 170, 247 F.3d 8, 12-13 (1st Cir. 2001) (distinguishing Clinchfiled in its decision to uphold an arbitration award on a ground not stated by the arbitrator himself); Van Pelt v. UBS Fin. Servs., Inc., No. 3:05cv477, 2007 U.S. Dist. WL 2997598, at *4 (W.D.N.C. Oct. 12, 2007) ("The panel was silent concerning the basis for its monetary award, which is not a basis for vacating the award. Arbitrators need not state reasons for reaching a particular result. . . . [T]here is nothing on the face of the award that can show that the panel failed to address critical contract terminology.").

A party cannot satisfy its burden of proof with mere conjecture that the arbiters failed in their duties or engaged in misconduct. See Jeffress v. Reddy, No. 98-2613, 2003 WL 22293579, at *4 (4th Cir. Oct. 7, 2003) ("Conjecture, speculation, and mere possibilities will not sustain the plaintiff's burden of proof on the proximate cause element." (citing Fitzgerald v. Manning, 679 F.2d, 341, 349 (4th Cir. 1982))). The only evidence that MCI and National Union presented in support of its claim that the Damages Award did not draw its essence from the Agreement was the fact that the award was not reasoned. Accordingly, the court finds that MCI and National Union have not carried their burden of proving that the Damages Award should be vacated because it failed to draw its essence from the Agreement.

3. Award Based on the Subject Matter Submitted to the Arbitrators

Section 10(a)(4) of the FAA provides that an arbitration award may be vacated "where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made." 9 U.S.C. § 10(a)(4). Nevertheless, "[t]he Supreme Court has held that a contention that `the arbitrators misconstrued a contract is not open to judicial review' under § 10(a)(4) of the FAA." Int'l Longshoremen's Assoc. v. Hampton Rds. Shipping Assoc., No. 94-1838, 1995 U.S. App. WL 19321, at *6 (4th Cir. Jan. 19, 1995) (quoting Bernhardt v. Polygraphic Co. of Am., Inc., 350 U.S. 198, 203 n. 4 (1956)). "Prior cases addressing this provision have vacated arbitration awards on this ground only when the arbitrator either failed to resolve an issue presented to him or issued an award that was so unclear and ambiguous that the reviewing court could not engage in meaningful review." Id.

Here, MCI and National Union argue that the Damages Award must be vacated under § 10(a)(4) because the Panel did not provide a reasoned award. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 10-12); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).)

The court rejects MCI and National Union's § 10(a)(4) argument. An award being unreasoned is not a basis for vacatur under § 10(a)(4). As noted, awards are generally vacated under § 10(a)(4) only where the arbitrators failed to resolve an issue presented to them or the award is ambiguous or unclear. Int'l Longshoremen's Assoc., 1995 U.S. App. WL at *6.

Once again, the Panel was under no obligation to provide a reasoned Damages Award and MCI and National Union have not proven that the Panel did not resolve the issues presented to them by the parties. Supra Part III.A.2. The mere fact that the Panel did not rule in MCI and National Union's favor does not indicate that the Panel did not resolve the issues presented to them.

A significant record exists from which this court can review the Damages Award. The Arbitration Agreement was entered into and arbitration was conducted after significant and lengthy proceedings in this court and the Fourth Circuit Court of Appeals. MCI and City's cross-motions for summary judgment (which involved, in part, the parties' claims concerning the amount of damages the parties contended they were entitled) were denied because a reasonable jury could find in favor of either party based on the evidence in the record. From this court's review of the order denying the parties' cross-motions for summary judgment and the Panel serving as finder of fact during the arbitration, it follows that the Damages Award can reasonably be understood to flow from the evidence contained in the record and the claims submitted by the parties. See Hatfield v. Johnson Controls, Inc., 791 F. Supp. 1243, 1251 n. 5 (E.D. Mich. 1992) (noting that arbitrators and jurors both serve the function of fact finder).

Further, MCI and National Union have not proven that the Damages Award is unclear or ambiguous so as to warrant vacatur under § 10(a)(4). It is not apparent from the face of the Damages Award that the Panel did not consider the language of the Agreement and all of the parties' claims and arguments. To the contrary, because of the extensive record available from all of the related proceedings, it is clear the Panel did consider the parties' claims and arguments. Additionally, the Damages Award states that "[a]ny claims or issues of either party not expressly awarded herein, are hereby denied." (Def.'s Notice of Arbitration Award Ex. A (Doc. 503-2) at 2.) Considering the multiple number of claims and counterclaims submitted to the Panel, "[t]his statement of an arbitral decision could hardly be more definite," clear and unambiguous. See Remmey, 32 F.3d at 150 (holding that an unreasoned award with similar language (to the effect that all claims of the claimant against the respondent are dismissed in all respects) should not be vacated under § 10(a)(4)). Accordingly, the court finds that MCI and National Union have failed to meet their burden of showing that the Damages Award should be vacated under § 10(a)(4) of the FAA.

4. Enforceability of the Damages Award

MCI and National Union argue that the Damages Award is unenforceable on two grounds: (1) the Damages Award is based on an invalid agreement to arbitrate, as the parties did not mutually assent to the terms of the Arbitration Agreement, and (2) the award violates public policy.

a. Mutual Assent

MCI and National Union argue that disagreements between the parties as to whether they were permitted to submit additional briefs and documents to the Panel evince a lack of mutual assent to the terms of the Arbitration Agreement, thus the Arbitration Agreement is unenforceable. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 12-13); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542))). MCI and National Union assert this argument only after having received the benefits of the Arbitration Agreement and after the Damages Award was entered by the Panel. Nevertheless, the court examines whether MCI and National Union have established that the Arbitration Agreement is invalid for want of mutual assent.

"To determine whether the parties agreed to arbitrate, [and thus whether the arbitration agreement at issue is enforceable,] courts apply state law principles governing contract formation." Hightower v. GMRI, Inc., 272 F.3d 239, 242 (4th Cir. 2001). Under North Carolina law, a valid contract requires mutual assent of the parties to the terms of the agreement so as to establish a "meeting of the minds." Creech v. Melnick, 347 N.C. 520, 527, 495 S.E.2d 907, 911-12 (N.C. 1998). An agreement lacks mutual assent, and thus may be avoided, where the movant establishes by "clear, strong, and convincing" evidence, Speas v. Merch.'s Bank Trust Co. of Winston-Salem, 188 N.C. 524, 125 S.E. 398, 401 (1924), that the parties made a "mutual mistake" "as to an existing or past fact that is material and enters into and forms the basis of the contract or is the `essence of the agreement,'" Creech, 495 at 912 (citation omitted). Further, a contract lacks mutual assent, and thus may be avoided, where a party's unilateral mistake as to a term in the agreement is accompanied by "fraud, imposition, undue influence, or like oppressive circumstances." Marriott Fin. Servs., Inc. v. Capitol Funds, Inc., 288 N.C. 122, 136, 217 S.E.2d 551, 560 (1975).

In the case at bar, none of the parties have disputed that North Carolina law applies to the issue of whether the Arbitration Agreement is enforceable. With regard to the validity of the Arbitration Agreement, the parties exclusively discussed North Carolina contract law in their briefs. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 12-13); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542))); (Def.'s Mem. in Support of Resp. to Motion to Vacate Damages Award (Doc. 553) at 16-17.) The court thus looks to North Carolina law in determining the validity of, and the parties obligations under, the Arbitration Agreement.
Under North Carolina law, agreements to arbitrate are generally valid pursuant to N.C. GEN. STAT. § 1-569.6. Additionally, "the law of contracts governs the issue of whether there exists an agreement to arbitrate." Routh v. Snap-On Tools Corp., 108 N.C.App. 268, 271, 423 S.E.2d 791, 794 (Ct.App. 1992).

The court notes that "North Carolina has a strong public policy favoring the settlement of disputes by arbitration."Johnston County v. R.N. Rouse Co., 331 N.C. 88, 91, 414 S.E.2d 30, 32 (1992). Pursuant to this public policy, "any doubt concerning the existence of [an arbitration agreement] must . . . be resolved in favor of arbitration." Id. (emphasis added).

The court finds that MCI and National Union have not established that the Arbitration Agreement is unenforceable for want of mutual assent by any standard. With regard to MCI and National Union's mutual mistake argument, the parties have failed to meet their heightened burden of proving that the disagreements at issue concerned a material matter. On the "materiality" point, MCI and National Union offered no evidence. Instead, they merely relied on two unsupported assertions: "[t]his issue goes to the heart of the dispute between City and MCI" and "it is a material term. . . ." (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 12-13); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).) Two bare assertions do not constitute "clear, strong, and convincing" evidence. See Gardner v. May, 172 N.C. 192, 194-95, 89 S.E. 955, 956 (1916) (stating that a consent judgment could be set aside for mutual mistake, though "the burden [is] on the party attacking the judgment to show facts which will entitle him to relief" (emphasis added)). Similarly, MCI and National Union have not proven the existence of a unilateral mistake. MCI and National Union offered no evidence tending to show that the purported mistakes at issue were induced by any misrepresentations or deceitful conduct on part of City or that the circumstances surrounding their entering the Arbitration Agreement were oppressive.

The Panel's decision concerning the types of evidence they would consider is procedural in nature. See Int'l Union, United Mine Workers of Am. v. Marrowbone Dev. Co., 232 F.3d 383, 389 (4th Cir. 2000) ("An arbitrator typically retains broad discretion over procedural matters and does not have to hear every piece of evidence that the parties wish to present."). The court notes that neither MCI nor National Union presented evidence tending to show that any of the Panel's procedural rulings "were in bad faith or so gross as to amount to affirmative misconduct." See id. at 389 (noting the standard for vacating an arbitral award because of an arbitrator's procedural ruling).

b. Public Policy

Pursuant to the Supreme Court's decision in Misco, an arbitration award may be vacated if the award violates "some explicit public policy that is well defined and dominant, and is to be ascertained by reference to the laws and legal precedents and not from general considerations of supposed public interests." Misco, 484 U.S. at 42-45 (internal citations and quotations omitted).

In the present matter, MCI and National Union argue that the Damages Award violates North Carolina public policy because City purportedly received both actual and liquidated damages for the same breach and did not allocate its costs. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 8-10); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).)

The court finds MCI and National Union's public policy argument unpersuasive. As stated, in reviewing arbitration awards "courts will not look behind a lump-sum award in an attempt to analyze [an arbitrator's] reasoning process." Atlanta-Tomberlin, 672 F. Supp. at 889. MCI and National Union are not able to point to anything in the Damages Award itself that indicates that the Panel's ruling violated public policy.

Nevertheless, even looking behind the lump-sum Damages Award, MCI and National Union have not proven that the Damages Award violates public policy. Both MCI and City have submitted reasonable possible calculations of the amount City is owed and their arguments as to these amounts is clearly set forth in the record of the arbitration proceeding. (See, e.g., Decl. of William Cary Exs. 56-57 (Docs. 525-5, 525-6).) The specific numbers offered by the parties are speculative at best. What is clear from the record is that MCI submitted and argued its damages calculation (i.e., City owes it approximately $450,000) and City argued its calculation (i.e., MCI owes it approximately $17,000,000). The Panel had the benefit of significant evidence and argument presented by both MCI and City and the Panel's award appears reasonable under the circumstances. The court is unable to find, from the record, that the Panel necessarily erred in the manner MCI and National Union contend, thus the court is unable to conclude that the award is void as against public policy.

Furthermore, while North Carolina courts prohibit parties from recovering twice for the same harm and require litigants to allocate their costs, "misapplication of [state] law by the arbitrators is simply an error of law. Errors of law are not the grounds on which a court can overturn an arbitration award." See Arrowhead Global Solutions, Inc. v. Datapath, Inc., No. 04-2000, 2006 WL 278393, at *5 (4th Cir. Feb. 3, 2006). Nothing in North Carolina law clearly indicates that prohibitions on receiving actual and liquidated damages from the same breach and failing to allocate costs constitute well defined and dominant public policies. In sum, the court finds that MCI and National Union have not met their burden of proof in establishing that the Damages Award should be vacated as being violative of public policy.

5. Breach of the Arbitration Agreement

Section two of the FAA provides that an arbitration agreement is enforceable unless legal or equitable grounds for its revocation are established. 9 U.S.C. § 2. Pursuant to section two of the FAA, MCI and National Union argue that the Damages Award should be vacated because City breached its implied covenant of good faith and fair dealing under the Arbitration Agreement. (Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542) at 13-20); (National Union's Mot. to Vacate and/or Remand the Arbitration Award as to MCI (Doc. 548) at 1 (incorporating Pl.'s Mem. in Support of Mot. to Vacate Damages Award (Doc. 542)).) MCI and National Union contend that City breached the Arbitration Agreement by submitting claims to the Panel for which City was not entitled to recover and attempting to prevent MCI from presenting its case. (Id.)

The court rejects MCI and National Union's final proposed basis for vacatur of the Damages Award. As stated, the Fourth Circuit has held that "[i]n order for a reviewing court to vacate an arbitration award, the moving party must sustain the heavy burden of showing one of the grounds specified in the Federal Arbitration Act or one of certain limited common law grounds."Choice Hotels, 519 F.3d at 207 (4th Cir. 2008) (citation and quotation marks omitted); supra Part II. The court finds that neither the FAA nor the Fourth Circuit provide that the breach of an arbitration agreement is a ground for vacatur of an arbitral award.

Although the Fourth Circuit in Hooters of America, Inc. v. Phillips, 173 F.3d 933 (4th Cir. 1999) held that breach of a party's duty to perform in good faith may be a basis forrevocation of an arbitration agreement, application of the principles espoused in Hooters is not warranted in this case. In Hooters, the Fourth Circuit emphasized that reviewing courts should generally refrain from disrupting arbitration awards on fairness grounds. Id. at 941 ("fairness objections should generally be made to the arbitrator, subject only to limited post-arbitration judicial review as set forth in section 10 of the FAA."). Moreover, the Hooters court specifically limited its holding to the facts present in that case. Id. at 940-41. The court noted that the procedural rules at issue in Hooters were "so one-sided that their only possible purpose is to undermine the neutrality of the proceeding" and that the court "only reach[ed] the content of the arbitration rules because their promulgation was the duty of one party." Id. at 938, 941.

The facts in the present case are not analogous to the facts inHooters. There is no evidence that the Panel did not apply the procedural rules in a neutral manner. Further, unlike in Hooters, nothing suggests that one party (i.e., City) was solely responsible for the selection of the arbitral rules.

In Hooters, a contract of adhesion gave one party unfettered discretion in selecting the procedural rules that governed the arbitration. Hooters of Am., Inc. v. Phillips, 173 F.3d 933, 936 (4th Cir. 1999). By contrast, the Arbitration Agreement in this case was drafted during the course of litigation. In light of this fact and the fact that MCI and National Union have offered no evidence to the contrary, the court finds that City, MCI, and National Union selected the procedural rules governing the arbitration proceeding.

B. Motion to Remand

In addition to moving for the vacatur of the Damages Award, MCI has moved, in the alternative, to remand the Damages Award back to the Panel for clarification as to the bases for the Panel's decision. (Doc. 535.) Although the FAA does not specifically empower courts to remand arbitration awards for clarification, in Cannelton Industries, Inc. v. District 17, United Mine Workers of America the Fourth Circuit held that "[w]hen an arbitrator does provide reasons for a decision and when those reasons are so ambiguous so as to make it impossible for a reviewing court to decide whether an award draws its essence from the agreement, the court may remand the case to the arbitrator." 951 F.2d 591, 594 (4th Cir. 1992) (emphasis added).

The FAA does however state that awards may be modified or corrected. 9 U.S.C. § 11.

Here, MCI argues that the Damages Award must be remanded for the same reasons the court should vacate the award; the award is ambiguous and the Panel failed to address critical contract terminology. (Pl.'s Mem. in Support Mot. to Remand Awards to Arbitration Panel for Clarification (Doc. 536) at 10-17.) Once more, this court disagrees.

The court finds that, even assuming, arguendo, that the Fourth Circuit would extend its holding in Cannelton to cases such as this one, where the arbitrators did not provide a reasoned award and were not required to do so, remand of the Damages Award is not proper. As stated, the Damages Award is not ambiguous, it is possible for the court to conclude that the award drew its essence from the Agreement, and there is no evidence that the Panel failed to discuss critical contract terminology. See supra Parts III.A.2, III.A.3.

The court also notes that the Fourth Circuit's remittitur language in Cannelton is permissive, not obligatory. See Cannelton Indus., Inc. v. Dist. 17, United Mine Workers of Am., 951 F.2d 591, 594 (4th Cir. 1992) ("[T]he court may remand the case to the arbitrator." (emphasis added)).

IV. Conclusion

For the reasons set forth above, Plaintiff and Counter Defendant's motions to vacate (Docs. 541, 548) are DENIED and Plaintiff's motion to remand (Doc. 535) is DENIED.


Summaries of

MCI CONSTRUCTORS, INC. v. HAZEN SAWYER, P.C.

United States District Court, M.D. North Carolina
Mar 9, 2009
1:99CV2, 1:02CV396 (M.D.N.C. Mar. 9, 2009)
Case details for

MCI CONSTRUCTORS, INC. v. HAZEN SAWYER, P.C.

Case Details

Full title:MCI CONSTRUCTORS, INC. Plaintiff, v. HAZEN AND SAWYER, P.C. Defendant. MCI…

Court:United States District Court, M.D. North Carolina

Date published: Mar 9, 2009

Citations

1:99CV2, 1:02CV396 (M.D.N.C. Mar. 9, 2009)

Citing Cases

U.S. for Use Ben. of Coastal Roof. v. P. Browne Assn

Finally, even if the court were to find that the arbitrator was required to issue a reasoned award, courts…

Covis Pharma S.A.R.L. v. Hospira Woldwide, Inc.

Where, as here, arbitrators do not explain the reasons for their decisions, "it is nearly impossible for the…