Matter of Walsh Construction Company v. Egan

Appellate Division of the Supreme Court of New York, Third Department
Feb 28, 1991
170 A.D.2d 899 (N.Y. App. Div. 1991)

Opinion

February 28, 1991

Appeal from the Supreme Court, Albany County (Conway, J.).


In November 1987, petitioner entered into a construction contract with the State for construction of Cayuga Correctional Facility in Cayuga County. In January 1989, petitioner submitted payment application No. 20 for work performed at the facility. Payment was rejected and petitioner commenced a CPLR article 78 proceeding, the precursor to the present proceeding, seeking to compel payment. By judgment dated April 19, 1989, Supreme Court ordered respondents to pay application No. 20 with interest thereon in accordance with law. Payment was made; however, respondents refused to pay interest. Petitioner then commenced the instant article 78 proceeding to compel respondents to pay interest as previously directed, to be computed from January 27, 1989. Supreme Court directed respondents to pay interest as previously directed, but directed that interest be computed from March 10, 1989. On this appeal respondents assert that Supreme Court erred in directing the payment of interest and petitioner asserts that interest should be computed from January 27, 1989.

At the outset, it is noted that no appeal was taken from the April 19, 1989 judgment of Supreme Court and it is final and binding on the parties (see, Matter of Reilly v Reid, 45 N.Y.2d 24). The sole issue before this court, therefore, is whether Supreme Court properly determined the date from which to reckon interest. We conclude that it did. State Finance Law § 179-f (1) provides that where a State agency fails to make payment by the "required payment date", it shall be liable for interest on the amount overdue. State Finance Law § 179-f (2) defines "required payment date" as 30 days "after receipt of an invoice for the amount * * * due". Finally, State Finance Law § 179-e (6) (a) defines "receipt of an invoice" as "the date on which a proper invoice is actually received in the designated payment office". Here, the invoice was received at the Albany office of the Office of General Services, its designated payment office, on February 6, 1989. Supreme Court correctly concluded March 10, 1989 (30 days after receipt on Feb. 6, 1989) to be the date from which interest should be calculated.

Supplementary judgment affirmed, without costs. Mahoney, P.J., Casey, Weiss, Crew III, and Harvey, JJ., concur.


Summaries of

Matter of Walsh Construction Company v. Egan

Appellate Division of the Supreme Court of New York, Third Department
Feb 28, 1991
170 A.D.2d 899 (N.Y. App. Div. 1991)
Case details for

Matter of Walsh Construction Company v. Egan

Case Details

Full title:In the Matter of WALSH CONSTRUCTION COMPANY, a Division of GUY F. ATKINSON…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Feb 28, 1991

Citations

170 A.D.2d 899 (N.Y. App. Div. 1991)
566 N.Y.S.2d 728

Citing Cases

Battisti v. Battisti

92 judgment entered by plaintiff against him. By order dated September 21, 1989, Supreme Court vacated the…