From Casetext: Smarter Legal Research

Matter of Solow v. Bethlehem Steel Corp.

Appellate Division of the Supreme Court of New York, First Department
Jan 26, 1978
60 A.D.2d 826 (N.Y. App. Div. 1978)

Summary

In Matter of Solow v Bethlehem Steel Corp. (60 AD2d 826 [1st Dept 1978]), the Court explained: "Section 38 of the Lien Law does not establish an absolute right to a detailed statement from a lienor as to all the items of labor and/or material and the value thereof for which he claims a lien but does require a statement from a lienor as to items in dispute" (citing Matter of 819 Sixth Ave. Corp. v T. & A. Assoc., 24 AD2d 446 [1st Dept 1965])."

Summary of this case from Melcon Gen. Contractors, L.L.C. v. ELUL 1080 Leggett LLC

Opinion

January 26, 1978


Judgment (denominated an order) of the Supreme Court, New York County, entered April 28, 1977, which granted petitioners' motion for a statement by the lienor under section 38 Lien of the Lien Law, unanimously modified, on the law and on the facts, to require lienor to supply, solely to petitioner Solow Development Corporation, an itemization only of those extras still at issue, totaling $26,531.71, the balance remaining in dispute, and otherwise affirmed, without costs and without disbursements. Section 38 Lien of the Lien Law does not establish an absolute right to a detailed statement from a lienor as to all the items of labor and/or material and the value thereof for which he claims a lien but does require a statement from a lienor as to items in dispute (see Matter of 819 Sixth Ave. Corp. v T. A. Assoc., 24 A.D.2d 446). Although the contract does not contain any agreed contract price, but rather states a formula for determining such price, nevertheless it appears from the deposition of Arthur Geller, an employee of petitioner Solow Development Corporation, that said petitioner admits the agreed price and reasonable value of the work performed under the contract is $8,831,060.66, the sum claimed by lienor therefor. In the circumstances, a statement of the details thereof is not required (Matter of 819 Sixth Ave. Corp. v T. A. Assoc., supra; see Matter of Borysko [Kabor Constr. Corp.], 2 Misc.2d 621). The only sum remaining in dispute is the difference between the lienor's claim for extras ($203,289.09) and said petitioner's acknowledgment of extras ($176,757.38). A statement of the details of said difference ($26,531.71) is required. (See Matter of 819 Sixth Ave. Corp. v T. A. Assoc., supra; see, also, Matter of Pinckney v Ocean Home Enterprises, 13 A.D.2d 806.) According to the notice of lien, said petitioner's total obligation is $9,034,349.75. This consists of lienor's claim of $8,831,060.66 for work performed under the contract and its claim of $203,289.09 for extras. As the total paid by said petitioner (admitted in the afore-mentioned deposition of its employee) is $7,910,050.40, the balance due by lienor's reckoning is $1,124,299.35, the sum stated in the notice of lien as the amount unpaid. Petitioner admits the agreed price and reasonable value of the work performed under the contract is $8,831,060.66, and concedes the sum of $176,757.38, for extras it approved, for a total sum of $9,007,818.04. Subtracting $9,007,818.04 from $9,034,349.75, the sum lienor claims in the notice of lien as petitioner's total obligation, leaves $26,531.71 as the balance remaining in dispute, for extras still at issue, to be itemized. We reject petitioners' argument that Sheldon H. Solow as an individual and owner of the premises in question is entitled to a section 38 statement in his own right because he was not personally a party to the contract. The record establishes that Diesel, in contracting with lienor, was an authorized agent acting on behalf of Solow Development Corporation and that the petition asserts that Solow Development Corporation was "the general contractor and/or agent of Sheldon H. Solow." In contracting with lienor, Diesel was thus acting as an agent of Sheldon H. Solow himself. In either case, Sheldon H. Solow must be bound by the intra vires acts of Diesel (see 2 N.Y. Jur, Agency, § 153).

Concur — Birns, J.P., Evans, Lane and Markewich, JJ.


Summaries of

Matter of Solow v. Bethlehem Steel Corp.

Appellate Division of the Supreme Court of New York, First Department
Jan 26, 1978
60 A.D.2d 826 (N.Y. App. Div. 1978)

In Matter of Solow v Bethlehem Steel Corp. (60 AD2d 826 [1st Dept 1978]), the Court explained: "Section 38 of the Lien Law does not establish an absolute right to a detailed statement from a lienor as to all the items of labor and/or material and the value thereof for which he claims a lien but does require a statement from a lienor as to items in dispute" (citing Matter of 819 Sixth Ave. Corp. v T. & A. Assoc., 24 AD2d 446 [1st Dept 1965])."

Summary of this case from Melcon Gen. Contractors, L.L.C. v. ELUL 1080 Leggett LLC
Case details for

Matter of Solow v. Bethlehem Steel Corp.

Case Details

Full title:In the Matter of SHELDON H. SOLOW et al., Respondents, v. BETHLEHEM STEEL…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jan 26, 1978

Citations

60 A.D.2d 826 (N.Y. App. Div. 1978)

Citing Cases

2269 First Ave Owner LLC v. BDM Sols. LLC

"The purpose of the itemization is to apprise the owner of the details of the lienor's claim" (F.J.C. Cavo…

York Restoration Corp. v. Pedrol Contracting Inc.

First, the Court found that Lien Law §38 did not apply to Respondent's lien. Citing Solow v Bethlehem Steel …