Opinion
Civil Action 19-4241
02-28-2022
ORDER
JOEL H. SLOMSKY, J.
AND NOW, this 28th day of February 2022, upon consideration of Plaintiff's Motion for Judgment on the Pleadings (Doc. No. 25), Defendant Connolly Contractors, Inc.'s Response (Doc. No. 29), Defendant Glenn M. White Builders, Inc.'s Response (Doc. No. 31), Plaintiff's Reply (Doc. No. 26), and in accordance with the Opinion of the Court issued this day, it is ORDERED as follows:
1. Plaintiff's Motion for Judgment on the Pleadings (Doc. No. 25) is GRANTED.
2. Main Street shall have 14 days to determine whether to pursue a claim for reimbursement of defense costs from Connelly Contractors and to file a submission with the Court documenting those costs.
BY THE COURT: