From Casetext: Smarter Legal Research

LR School Dist. v. Celotex Corp.

Supreme Court of Arkansas (En Banc)
Feb 19, 1979
264 Ark. 757 (Ark. 1979)

Summary

noting that if the parties involved have assumed conflicting postures regarding the facts and circumstances, the issue or question is generally a question of fact; however, if there is no conflict in the evidence and only one reasonable inference can be drawn from the evidence, the issue becomes one of law

Summary of this case from Greenway Equip., Inc. v. Johnson

Opinion


576 S.W.2d 709 (Ark. 1979) 264 Ark. 757 The LITTLE ROCK SCHOOL DISTRICT OF PULASKI COUNTY, Arkansas, Appellant, v. MATSON, INC., et al., Appellees. No. 78-137. Supreme Court of Arkansas. February 19, 1979.

        [264 Ark. 768-A] Supplemental Order on Petitions for Rehearing.

        The petition for rehearing filed by the architects, Cromwell, Neyland, Truemper, Levy and Gatchell, Inc., is granted, for the reason that the only cause of action asserted against them is based upon negligent design, not breach of warranty, and that action is barred by the statute of limitations. The other petitions for rehearing are denied.

        HARRIS, C. J., dissents.

        BYRD, J., dissents.

        GEORGE ROSE SMITH and FOGLEMAN, JJ., would grant rehearing as to all appellants.

        [264 Ark. 768-B] BYRD, Justice, dissenting.

        One of the troubles with per curiam orders is that like Mother Hubbard's dress, they cover everything and tell you nothing. The per curiam by the majority in holding that the statute, Ark.Stat.Ann. § 37-237 (Acts 1967, No. 42), has run against the architect, neglect to state that although the architect certified the building as complete in 1968 he continued to act on the roofing matter on the following dates, to-wit:

2-11-69

7-28-69

11-09-69

11-17-70

12-23-70

12-29-70

2-01-71

2-09-71

2-18-71

3-04-71

3-23-71

4-27-71

6-04-71

6-24-71

8-10-71

8-30-71

10-01-71

2-18-72

[264 Ark. 768-C] 11-02-73

12-15-73

1-04-74

1-08-74

1-18-74

2-22-74

2-27-75

3-18-75

3-26-75

        As late as 11-2-73 the architect was "pleased with the general appearance of the roof and (Knox Gill's) concern for keeping the building watertight." It was not until 3-26-75 that the architect concluded that the roof had failed. It was only when the school board made demand upon Celotex that they learned of the fact that the roof may have been negligently designed.

        Since the architect remained in the same fiduciary capacity to the school board at all times and consistently pointed the finger at Celotex and Knox Gill for the trouble with the leaks, I submit that such conduct in law amounts to concealment of the fact that there was anything wrong with the design. In such situations the courts of this nation almost universally hold that such conduct tolls the running of the statute of limitations. The reason for so holding is stated in 51 Am.Jur.2d Limitation of Actions § 147 as follows:

"The reasoning adopted in support of the general rule is that to hold that the statute of limitations ran in favor of a person who had concealed the cause of action under such circumstances would be to permit the defendant to take advantage of his own wrong and to sustain [264 Ark. 768-D] a defense of which in good conscience he ought not to be permitted to avail himself . . .."

        With reference to whether or not there was a concealment, 51 Am.Jur.2d Limitation of Actions § 149 points out that where " . . . there are fiduciary or confidential relations between the parties, there needs to be no evidence of a fraudulent concealment other than that implied from the transaction itself."

        For the reasons herein stated, I respectfully dissent from the majority's per curiam order stating that the statute had run against the architect.


Summaries of

LR School Dist. v. Celotex Corp.

Supreme Court of Arkansas (En Banc)
Feb 19, 1979
264 Ark. 757 (Ark. 1979)

noting that if the parties involved have assumed conflicting postures regarding the facts and circumstances, the issue or question is generally a question of fact; however, if there is no conflict in the evidence and only one reasonable inference can be drawn from the evidence, the issue becomes one of law

Summary of this case from Greenway Equip., Inc. v. Johnson

In Little Rock School District v. Celotex Corp., 264 Ark. 757, 574 S.W.2d 669 (1979), the court considered the vendor's attempts to repair a leaking roof as conduct that might have tolled the statute of limitations, and therefore held that the attempts raised a factual question for resolution by the jury, stating that a statute of limitations "`is tolled so long as the vendor insists that the defect can be repaired and is attempting to do so.'"

Summary of this case from A. J. Aberman, Inc. v. Funk Building Corp.
Case details for

LR School Dist. v. Celotex Corp.

Case Details

Full title:THE LITTLE ROCK SCHOOL DISTRICT of Pulaski County, Arkansas v. CELOTEX…

Court:Supreme Court of Arkansas (En Banc)

Date published: Feb 19, 1979

Citations

264 Ark. 757 (Ark. 1979)
264 Ark. 757
574 S.W.2d 669

Citing Cases

Safeway Stores, Inc. v. Certainteed Corp.

Thus, it is not conclusively established that Certainteed's express warranty meant only that the roofing…

Haase v. Starnes, M.D

The General Assembly was no doubt aware of this rule of law when it included breach of warranty and contract…