Order, Supreme Court, New York County (Shirley Fingerhood, J.), entered March 6, 1990, which denied defendant's motion to dismiss the complaint on the ground that plaintiff failed to comply with alternative dispute resolution in the underlying contract, unanimously reversed, on the law, without costs, motion to dismiss granted. The Clerk is directed to enter judgment in favor of defendant dismissing the complaint.

Howard Burger, for Plaintiff-Respondent.

Ira Lipton, for Defendant-Appellant.

Before: Williams, J.P., Mazzarelli, Wallach, Buckley, Friedman, JJ.


Plaintiff was a contractor engaged by defendant Transit Authority to excavate for new subway facilities in lower Manhattan. The contract provided that disputes were to be resolved by defendant's Chief Engineer with subsequent judicial review limited in scope to whether or not any determination by the Chief Engineer is "arbitrary, capricious or so grossly erroneous to evidence bad faith." Such a dispute arose, was submitted by plaintiff to the Chief Engineer and was resolved against plaintiff. Instead of seeking review as provided by CPLR Article 78, plaintiff commenced this plenary action which pleaded causes of action for breach of contract and quantum meruit. Defendant moved to dismiss for plaintiff's failure to comply with the alternative dispute resolution provision of the contract. While the IAS court's decade-old decision to deny defendant's motion is understandable in terms of the then-controlling precedent, it has been clear since at least 1993 that the contract clause providing for dispute resolution by defendant's Chief Engineer is not against public policy, is enforceable and requires dismissal of this complaint (compare Cross Brown v. Nelson, 4 A.D.2d 501, 503 [party to contract cannot be arbitrator to resolve contract disputes]with Westinghouse Elec. Corp. v. New York City Transit Auth., 82 N.Y.2d 47 [engineer review of contract disputes with circumscribed judicial review consistent with public policy]. While plaintiff argues that Westinghouse was a narrow ruling, there is utterly no support for such a position; subsequent decisions have reflected no hesitation to enforce non-judicial resolution of contract disputes when the contracting parties have clearly agreed to do so (see Yonkers Contr. Co. v. Port Autho. Trans-Hudson Corp., 87 N.Y.2d 927, 930; Ferguson Elec. Co. v. Kendal at Ithaca, 274 A.D.2d 890; and, Skanska Tunneling v. City of New York, 247 A.D.2d 344,appeal dismissed 92 N.Y.2d 844). We have reviewed plaintiff's other contentions and find them to be without merit.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

Laquila Construction v. N.Y.C. Transit Auth

Appellate Division of the Supreme Court of New York, First Department
Apr 19, 2001
282 A.D.2d 331 (N.Y. App. Div. 2001)
Case details for

Laquila Construction v. N.Y.C. Transit Auth

Case Details

Full title:LAQUILA CONSTRUCTION, INC., PLAINTIFF-RESPONDENT v. NEW YORK CITY TRANSIT…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Apr 19, 2001

Citations

282 A.D.2d 331 (N.Y. App. Div. 2001)
723 N.Y.S.2d 464

Citing Cases

Greenwald v. Weisbaum

The First Department has relied upon the Westinghouse decision in recent cases and upheld ADR provisions,…

Greenwald v. Weisbaum

The First Department has relied upon the Westinghouse decision in recent cases and upheld ADR provisions,…