Laborers Dist. Council v. McDowell Contractors

United States Court of Appeals, Eleventh Circuit
Jul 6, 1982
680 F.2d 94 (11th Cir. 1982)

Summary

In McDowell, the Eleventh Circuit affirmed a district court's holding that in the absence of a showing of union majority at a specific project, the terms of an area-wide pre-hire agreement are not enforceable against the employer with respect to the project in question; if the union cannot enforce the terms of the pre-hire agreement, neither can its pension fund.

Summary of this case from Trustees of Atlanta v. So. Stress Wire Corp.

Opinion

No. 81-7765. Non-Argument Calendar.

July 6, 1982.

Jerome A. Cooper, Birmingham, Ala., for plaintiffs-appellants.

Chris Mitchell, Birmingham, Ala., for defendants-appellees.

Appeal from the United States District Court for the Northern District of Alabama.

Before GOLDBERG, HILL and HATCHETT, Circuit Judges.

Honorable Irving L. Goldberg, U.S. Circuit Judge for the Fifth Circuit, sitting by designation.


In this appeal, we are asked whether a union or its pension fund may enforce the provisions of an area-wide "prehire" labor agreement against a construction contractor building a project within the covered area, when the union has not shown that it represents a majority of those working on the project in question.

§ 8(f) of the Labor Management Relations Act, 29 U.S.C. § 158(f) (1976), provides for prehire agreements such as the one here in question.

In proceedings below, the district court held: (1) that in the absence of a showing of a union majority at a given project, the terms of an area-wide prehire labor agreement would not be enforceable against the employer with respect to that project; and (2) that if the union could not enforce the terms of the prehire agreement, neither could its pension fund. Dissatisfied with the district court's ruling, the plaintiff union and pension fund trustees brought this appeal.

We find that the issues presented herein are controlled by clear precedent. On the basis of the Supreme Court's recent opinion in Kaiser Steel Corporation v. Mullins, et al., ___ U.S. ___, 102 S.Ct. 851, 70 L.Ed.2d 833 (1982) and the Fifth Circuit's en banc decision set forth in N.L.R.B. v. Haberman Construction Company, 641 F.2d 351 (5th Cir. 1981), the decision of the district court is

In Kaiser Steel Corporation v. Mullins, supra, the Supreme Court held that an employer's obligation to contribute to a union pension fund is unenforceable if the underlying labor-management agreement is itself unenforceable.

As a decision of the "old" Fifth Circuit, N.L.R.B. v. Haberman, supra serves as binding precedent for this panel unless or until overruled by a decision of the Supreme Court or the Eleventh Circuit sitting en banc. See, Bonner v. City of Prichard, Alabama, 661 F.2d 1206 (11th Cir. 1981).

AFFIRMED.


As a senior member of the "born-again" Fifth Circuit, I sit with my friends and former colleagues on this court as a visitor, a judicial interloper. As a guest, I am naturally reluctant to burden my hosts with torrid tales of bygone battles, for there is no surer way to wear out one's welcome. However, a good guest should not sit in stony silence when the conversation turns to matters of great moment. Thus, I feel that I must add a personal note of reluctant concurrence.

As the author of the panel opinion in N.L.R.B. v. Haberman Construction Company, 618 F.2d 288 (5th Cir. 1980), my views on the issues presented in this case are a matter of record. It is my position that the rule set forth by the en banc court in Haberman leaves those in the construction trades without the effective protections of collective bargaining, nomadic orphans in labor's maelstrom.

The rule adopted by the en banc court in Haberman forces unions to demonstrate majority support at each construction project before they can enforce an area-wide prehire agreement at that project. I believe that this rule imposes an impossible burden upon the exercise of important rights secured by the National Labor Relations Act. However, my views in this matter have been rejected. This panel is bound to follow the rule set forth in the 5th Circuit's en banc opinion in Haberman. Only en banc reconsideration by the Eleventh Circuit can change this result.

Thus, while I adhere to the views expressed in the panel opinion in Haberman, I recognize that well established principles of stare decisis require this panel to affirm the decision of the district court. Having duly noted my reservations, I concur.


Summaries of

Laborers Dist. Council v. McDowell Contractors

United States Court of Appeals, Eleventh Circuit
Jul 6, 1982
680 F.2d 94 (11th Cir. 1982)

In McDowell, the Eleventh Circuit affirmed a district court's holding that in the absence of a showing of union majority at a specific project, the terms of an area-wide pre-hire agreement are not enforceable against the employer with respect to the project in question; if the union cannot enforce the terms of the pre-hire agreement, neither can its pension fund.

Summary of this case from Trustees of Atlanta v. So. Stress Wire Corp.
Case details for

Laborers Dist. Council v. McDowell Contractors

Case Details

Full title:LABORERS DISTRICT COUNCIL OF ALABAMA, ON BEHALF OF LABORERS INTERNATIONAL…

Court:United States Court of Appeals, Eleventh Circuit

Date published: Jul 6, 1982

Citations

680 F.2d 94 (11th Cir. 1982)

Citing Cases

Trustees of Iron Workers Fund v. a P Steel

The Trustees in the case before us contend that Schafer's rationale concerning the appropriate unit for…

Trustees of Atlanta v. So. Stress Wire Corp.

On August 5, 1982, the court noted McDowell, a newly issued decision dealing with the majority requirement.…