Knab v. Robertson

Supreme Court, Appellate Division, Fourth Department, New York.
Nov 9, 2017
155 A.D.3d 1565 (N.Y. App. Div. 2017)

Opinion

1172 CA 17-00724.

11-09-2017

Robert M. KNAB, Jr., Plaintiff–Respondent, v. Drew ROBERTSON, et al., Defendants, and Oakgrove Construction, Inc., Defendant–Appellant.

Law Offices of John Wallace, Buffalo (Nancy A. Long of Counsel), for Defendant–Appellant. Lipsitz Green Scime Cambria LLP, Buffalo (John A. Collins of Counsel), for Plaintiff–Respondent.


Law Offices of John Wallace, Buffalo (Nancy A. Long of Counsel), for Defendant–Appellant.

Lipsitz Green Scime Cambria LLP, Buffalo (John A. Collins of Counsel), for Plaintiff–Respondent.

PRESENT: WHALEN, P.J., CENTRA, LINDLEY, TROUTMAN, AND WINSLOW, JJ.

MEMORANDUM:Plaintiff commenced this Labor Law and common-law negligence action seeking damages for injuries he sustained while working in the median of the New York State Thruway. The New York State Thruway Authority (Authority) hired defendant Oakgrove Construction, Inc. (Oakgrove) to work on the thruway, including repaving a section thereof, and the Authority hired defendant Foit–Albert Associates, Architecture, Engineering and Surveying, P.C. (Foit–Albert) to inspect Oakgrove's work. Foit–Albert subcontracted some of that work to plaintiff's employer. Oakgrove began to perform drainage and clearing work in August 2010, but suspended the work in late November for the winter shutdown period. Oakgrove removed all of its equipment and employees from the work site, and all lanes of the thruway in the area of the proposed construction were opened. Before suspending its work, Oakgrove noted that some of the elevation measurements provided by the Authority were incorrect. Foit–Albert, whose contract with the Authority stated that its inspection responsibilities also included surveying, assigned plaintiff to take new measurements, including during Oakgrove's winter construction hiatus. In December, plaintiff was taking those measurements when a vehicle operated by defendant Drew Robertson left the roadway and struck him. Plaintiff commenced this action, asserting claims under Labor Law §§ 200 and 241(6) as well as a common-law negligence cause of action against Oakgrove.

Supreme Court erred in denying Oakgrove's motion seeking summary judgment dismissing the complaint against it. Addressing first the claim under Labor Law § 241, we note that, while under that statute "owners and general contractors are generally absolutely liable for statutory violations ..., other parties may be liable under th[at] statute[ ] only if they are acting as the ‘agents' of the owner or general contractor by virtue of the fact that they had been given the authority to supervise and control the work being performed at the time of the injury" ( Walsh v. Sweet Assoc., 172 A.D.2d 111, 113, 577 N.Y.S.2d 324 [3d Dept.1991], lv. denied 79 N.Y.2d 755, 581 N.Y.S.2d 666, 590 N.E.2d 251 [1992] ; see Russin v. Louis N. Picciano & Son, 54 N.Y.2d 311, 318, 445 N.Y.S.2d 127, 429 N.E.2d 805 [1981] ; Giovanniello v. E.W. Howell, Co., LLC, 104 A.D.3d 812, 813, 961 N.Y.S.2d 513 [2d Dept.2013] ). "The owner or general contractor is not synonymous with the prime contractor ... Generally speaking, the prime contractor for general construction (especially in State construction projects) has no authority over the other prime contractors ... unless the prime contractor is delegated work in such a manner that it stands in the shoes of the owner or general contractor with the authority to supervise and control the work" ( Walsh, 172 A.D.2d at 113, 577 N.Y.S.2d 324 ; see Kulaszewski v. Clinton Disposal Servs., 272 A.D.2d 855, 856, 707 N.Y.S.2d 558 [4th Dept. 2000] ).

Here, Oakgrove and Foit–Albert were both prime contractors, and plaintiff's employer contracted only with Foit–Albert. Oakgrove did not supervise or instruct plaintiff. Rather, plaintiff reported to a supervisor at Foit–Albert. Oakgrove established as a matter of law that it had no control over plaintiff or the work he was performing, and plaintiff failed to raise a triable issue of fact (see Kulaszewski, 272 A.D.2d at 856, 707 N.Y.S.2d 558 ; Greenleaf v. Bristol–Myers Squibb Co., 231 A.D.2d 902, 903, 648 N.Y.S.2d 407 [4th Dept.1996] ). Plaintiff's reliance on the fact that Oakgrove provided GPS units for plaintiff to use is misplaced inasmuch as "[t]he determinative factor on the issue of control is not whether a [contractor] furnishes equipment but[, rather, is] whether [it] has control of the work being done and the authority to insist that proper safety practices be followed" ( Everitt v. Nozkowski, 285 A.D.2d 442, 443–444, 728 N.Y.S.2d 58 [2d Dept.2001] ; see Grimes v. Pyramid Cos. of Onondaga, 237 A.D.2d 940, 940–941, 655 N.Y.S.2d 206 [4th Dept.1997] ). Here, there is nothing in the record to indicate that Oakgrove had such control over plaintiff's work, and the court therefore should have dismissed the Labor Law § 241(6) claim against Oakgrove.

We further agree with Oakgrove that it established that it did not have control over the work site at the time of plaintiff's accident, and plaintiff failed to raise a triable issue of fact. Thus, the court should have dismissed the Labor Law § 200 claim and common-law negligence cause of action against Oakgrove (see Miano v. State Univ. Constr. Fund, 291 A.D.2d 830, 830–831, 736 N.Y.S.2d 556 [4th Dept.2002] ; Fenton v. Monotype Sys., 289 A.D.2d 194, 194, 733 N.Y.S.2d 696 [2d Dept.2001] ; see generally Steiger v. LPCiminelli, Inc., 104 A.D.3d 1246, 1248, 961 N.Y.S.2d 634 [4th Dept.2013] ). Furthermore, Oakgrove also established that it did not create or have actual or constructive notice of the dangerous condition of the work site, thereby establishing an additional ground for dismissal of that claim and cause of action against it (see generally Piacquadio v. Recine Realty Corp., 84 N.Y.2d 967, 969, 622 N.Y.S.2d 493, 646 N.E.2d 795 [1994] ; Gloria v. MGM Emerald Enters., 298 A.D.2d 355, 356, 751 N.Y.S.2d 213 [2d Dept.2002] ), and plaintiff failed to raise a triable issue of fact (see generally Zuckerman v. City of New York, 49 N.Y.2d 557, 562, 427 N.Y.S.2d 595, 404 N.E.2d 718 [1980] ).

In light of our determination, we do not address Oakgrove's remaining contentions on appeal.

It is hereby ORDERED that the order so appealed from is unanimously reversed on the law without costs, the motion is granted and the complaint against defendant Oakgrove Construction, Inc. is dismissed.


Summaries of

Knab v. Robertson

Supreme Court, Appellate Division, Fourth Department, New York.
Nov 9, 2017
155 A.D.3d 1565 (N.Y. App. Div. 2017)
Case details for

Knab v. Robertson

Case Details

Full title:Robert M. KNAB, Jr., Plaintiff–Respondent, v. Drew ROBERTSON, et al.…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Nov 9, 2017

Citations

155 A.D.3d 1565 (N.Y. App. Div. 2017)
63 N.Y.S.3d 781
2017 N.Y. Slip Op. 7822

Citing Cases

Volgassov v. Silverstein Props.

Tishman seeks summary judgment dismissing plaintiff's causes of action premised on Labor Law §§ 200, 240 (1)…

Verdugo v. Fox Bldg. Grp.

Furthermore, we agree with CNY that the court should have granted its motion with respect to the Labor Law §…