From Casetext: Smarter Legal Research

Kiewit Infrastructure W. Co. v. L.L.O., Inc.

United States District Court, District of Nevada
Dec 20, 2021
2:20-cv-00493-RFB-DJA (D. Nev. Dec. 20, 2021)

Opinion

2:20-cv-00493-RFB-DJA

12-20-2021

KIEWIT INFRASTRUCTURE WEST CO., a Delaware corporation, Plaintiff, v. L.L.O., INC. dba ACME ELECTRIC, a Nevada corporation; TAB CONTRACTORS, INC., a Nevada corporation; LIBERTY MUTUAL INSURANCE COMPANY, a Massachusetts corporation, Defendants. AND RELATED COUNTER-CLAIM AND THIRD-PARTY CLAIM

Justin C. Jones, Esq. Nicole E. Lovelock, Esq. Stephen A. Davis, Esq. JONES LOVELOCK Attorneys for L.L.O., Inc. dba ACME Electric, TAB Contractors, Inc., and Liberty Mutual Insurance Company WATT, TIEDER, HOFFAR & FITZGERALD, L.L.P. David F. McPherson (admitted pro hac vice) Rebecca S. Glos (admitted pro hac vice) Attorneys for Kiewit Infrastructure West Co. and Travelers Casualty and Surety Company of America


Justin C. Jones, Esq. Nicole E. Lovelock, Esq. Stephen A. Davis, Esq. JONES LOVELOCK Attorneys for L.L.O., Inc. dba ACME Electric, TAB Contractors, Inc., and Liberty Mutual Insurance Company

WATT, TIEDER, HOFFAR & FITZGERALD, L.L.P. David F. McPherson (admitted pro hac vice) Rebecca S. Glos (admitted pro hac vice) Attorneys for Kiewit Infrastructure West Co. and Travelers Casualty and Surety Company of America

STIPULATION TO EXTEND DISCOVERY DEADLINES (FOURTH REQUEST)

It is hereby stipulated by and between Plaintiff / Counterdefendant / Third-Party Defendant Kiewit Infrastructure West Co. (“Kiewit”), Third-Party Defendant Travelers Casualty and Surety Company of America (“Travelers”), Defendants / Counterclaimants / Third-Party Plaintiffs L.L.O. Inc. dba Acme Electric (“ACME”) and TAB Contractors, Inc. (“TAB”), and Defendant Liberty Mutual Insurance Co. (“Liberty”, together with ACME and TAB, the “Subcontractors”), by and through their respective counsel of record, to extend discovery deadlines from May 17, 2022 to September 14, 2022 (the “Stipulation”), for the reasons stated herein.

A. Discovery completed to date.

ITEM

DATE

Rule 26(f) Conference

June 17, 2020

Subcontractors' Initial FRCP Rule 26(a) Disclosure

July 8, 2020

Kiewit's Initial FRCP Rule 26(a) Disclosure

July 8, 2020

Subcontractors' First Supplemental Disclosure

July 31, 2020

Kiewit's First Supplemental Initial Disclosure

August 3, 2020

Subcontractors' Second Supplemental Disclosure

August 5, 2020

Subcontractors' First Requests for Production of Documents to Kiewit

August 10, 2020

Kiewit's Initial Production of Documents

August 24, 2020

Kiewit's First Requests for Production of Documents to ACME

August 31, 2020

Kiewit's First Requests for Production of Documents to TAB

August 31, 2020

Kiewit's First Interrogatories to ACME

August 31, 2020

Kiewit's First Requests for Admission to ACME

August 31, 2020

Kiewit's Amended First Requests for Admissions to ACME

September 1, 2020

Kiewit's First Interrogatories to TAB

September 1, 2020

Kiewit's Responses to the Subcontractors' First Requests for Production of Documents to Kiewit

September 16, 2020

Kiewit's First Production of Documents

September 24, 2020

Kiewit's Second Supplemental Initial Disclosures

September 30, 2020

ACME's Responses to Kiewit's Amended Requests for Admissions

October 27, 2020

ACME's Responses to Kiewit's Request for Production of Documents

October 27, 2020

ACME's Responses to Kiewit's Interrogatories

October 27, 2020

TAB's Responses to Kiewit's Interrogatories

October 27, 2020

Subcontractors' Third Supplemental Disclosure

October 27, 2020

Kiewit's Second Set of Interrogatories to ACME

October 29, 2020

ITEM

DATE

ACME's Responses to Kiewit's Second Set of Interrogatories

December 7, 2020

ACME's First Set of Interrogatories to Kiewit

February 11, 2021

ACME's First Set of Requests for Admission to Kiewit

February 11, 2021

Subcontractors' Second Set of Requests for Production of Documents to Kiewit

February 11, 2021

TAB's First Set of Interrogatories to Kiewit

February 11, 2021

Subcontractors' Fourth Supplemental Disclosure

February 12, 2021

Kiewit's Third Supplemental Initial Disclosure

February 17, 2021

Subcontractors' Fifth Supplemental Disclosure

March 1, 2021

Kiewit's Supplemental Disclosure of Schedules in Native Form

March 9, 2021

Kiewit's Fourth Supplemental Initial Disclosure

March 15, 2021

Kiewit's Fifth Supplemental Initial Disclosure

March 29, 2021

Kiewit's Supplemental Disclosure of Documents

March 30, 2021

Kiewit's Supplemental Disclosure of Documents

April 14, 2021

Kiewit's Supplemental Disclosure of Documents

April 15, 2021

Kiewit's Sixth Supplemental Initial Disclosure

April 15, 2021

Kiewit's Supplemental Disclosure of Documents

April 16, 2021

Kiewit's Seventh Supplemental Initial Disclosure

April 16, 2021

Kiewit's Eighth Supplemental Initial Disclosure

April 29, 2021

Subcontractors' Subpoena Duces Tecum issued to Clark County Public Works

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to the Narwhal Group

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to the Nevada Department of Transportation

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to CH2M Hill

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to NVEnergy

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to Clark County Public Works

May 7, 2021

Subcontractors' Subpoena Duces Tecum issued to Atkins North America

May 7, 2021

ITEM

DATE

Kiewit's Supplemental Disclosure of Documents

May 17, 2021

Kiewit's Ninth Supplemental Initial Disclosure

May 19, 2021

Subcontractors' Public Records Request to the Nevada Department of Transportation

May 25, 2021

Subcontractors' Seventh Supplement to Initial Disclosure

June 15, 2021

Kiewit's Tenth Supplemental Initial Disclosure

June 25, 2021

Kiewit's Supplemental Production of Documents

June 25, 2021

Kiewit's Notice of Errata to Tenth Supplemental Initial Disclosures

June 28, 2021

Subcontractors' Eighth Supplement to Initial Disclosure

July 1, 2021

Kiewit's Eleventh Supplemental Initial Disclosure

July 6, 2021

Kiewit's Supplemental Production of Documents

July 6, 2021

Kiewit's Supplemental Production of Documents

July 7, 2021

Kiewit's Twelfth Supplemental Initial Disclosure

July 8, 2021

Kiewit's Supplemental Production of Documents

July 16, 2021

Kiewit's Supplemental Production of Documents

July 18, 2021

Kiewit's Thirteenth Supplemental Initial Disclosure

July 20, 2021

Kiewit's Supplemental Production of Documents

July 22, 2021

Kiewit's Fourteenth Supplemental Initial Disclosure

July 23, 2021

Kiewit's Fifteenth Supplemental Initial Disclosure

July 28, 2021

Kiewit's Supplemental Production of Documents

July 28, 2021

Subcontractors' Ninth Supplement to Initial Disclosure

August 26, 2021

Kiewit's Interrogatories to ACME, Set 3

September 28, 2021

Kiewit's Interrogatories to TAB, Set 2

September 28, 2021

Kiewit's Requests for Production of Documents to ACME, Set

September 28, 2021 2

Kiewit's Requests for Production of Documents to TAB, Set 2

September 28, 2021

Kiewit's Supplemental Production of Documents

October 8, 2021

ITEM

DATE

Subcontractors' Tenth Supplement to Initial Disclosure

October 21, 2021

Subcontractors' Eleventh Supplement to Initial Disclosure

November 16, 2021

Kiewit's Interrogatories to ACME, Set 3

November 16, 2021

Kiewit's Interrogatories to TAB, Set 2

November 16, 2021

Kiewit's Requests for Production of Documents to ACME, Set

November 16, 2021 2

Kiewit's Requests for Production of Documents to TAB, Set 2

November 16, 2021

First Amended Stipulation Regarding Interrogatories and Deposition of 30(b)(6) Witnesses [Dkt. 94]

November 18, 2021

B. Discovery to be completed.

The parties are continuing to conduct discovery. Third party subpoenas have been issued and served by the Subcontractors, and further third-party subpoenas may be necessary. The Parties need to conduct numerous depositions and serve their expert reports upon each other.

C. Reasons why discovery has not or will not be completed by the current deadline.

This litigation pertains to a dispute between the parties for construction work performed on Project Neon, the largest public works project in Nevada history, with competing claims and counterclaims seeking millions of dollars in damages. Kiewit and the Subcontractors worked on Project Neon for several years, generating and accumulating hundreds of thousands of documents and electronically stored information (“ESI”) during the project, involving numerous personnel and entities.

Kiewit and Subcontractors are working through discovery issues related to ESI disclosures and discovery responses. These discovery issues have impacted the parties' ability to notice depositions of fact witnesses and impacted Subcontractors' experts' ability to form expert opinion regarding the claims, defenses, and damages at issue in this action. Based upon such issues, the Parties are unable to conduct depositions of project personnel and the parties' Rule 30(b)(6) designees or have their expert witnesses complete their reports. / /

The parties are currently contemplating mediation to resolve their differences before this action goes to trial. However, to have a meaningful mediation session, the parties need additional time in discovery.

Given the sheer amount of documents produced to date, the remaining documents that need to be produced by both parties, the expert reports that need to be prepared and disclosed, and the depositions that need to be taken, there is good cause to extend the discovery deadlines as set forth below.

D. Proposed schedule for completing discovery.

DEADLINE

CURRENT

PROPOSED

Discovery Cutoff

May 17, 2022

September 14, 2022

Amend Pleadings and Add Parties

February 16, 2022

May 17, 2022

Expert Disclosures

March 18, 2022

June 16, 2022

Rebuttal Expert Disclosures

April 19, 2022

August 15, 2022

Dispositive Motions

June 16, 2022

October 17, 2022

Joint Pretrial Order

July 19, 2022

November 16, 2022

E. Good cause exists to extend the discovery deadline.

LR 26-3 requires that any stipulation made to extend discovery be made before 21 days of the discovery deadline and be supported by good cause and satisfy the requirements of LR IA 6-1. The good cause standard under LR 26-3 is the same as the good cause standard under Fed.R.Civ.P. 16(b)(4). Winfeld v. Wal-mart Stores, Inc., 2:14-cv-01034-MMD-CWH, 2016 WL 3360658, at *1 (D. Nev. Jun. 9, 2016). “Good cause to extend a discovery deadline exists ‘if it cannot reasonably be met despite the diligence of the part[ies] seeking extension.'” Nunez v. Harper, 2:13-cv-0392-GMN-NJK, 2014 WL 2808985, at *2 (D. Nev. June 20, 2014) (quoting Johnson v. Mammoth Recs., Inc., 975 F.2d 604, 609 (9th Cir. 2002)). / /

Good cause exists to extend the discovery deadlines. The parties still have a significant amount of discovery to complete and are contemplating non-binding mediation. Thus, a discovery extension is warranted under these circumstances, and good cause exists to grant this Stipulation.

ORDER

Dated: December 17, 2021.

IT IS SO ORDERED.


Summaries of

Kiewit Infrastructure W. Co. v. L.L.O., Inc.

United States District Court, District of Nevada
Dec 20, 2021
2:20-cv-00493-RFB-DJA (D. Nev. Dec. 20, 2021)
Case details for

Kiewit Infrastructure W. Co. v. L.L.O., Inc.

Case Details

Full title:KIEWIT INFRASTRUCTURE WEST CO., a Delaware corporation, Plaintiff, v…

Court:United States District Court, District of Nevada

Date published: Dec 20, 2021

Citations

2:20-cv-00493-RFB-DJA (D. Nev. Dec. 20, 2021)