Opinion
2:21-cv-02193-CDS-EJY
08-19-2022
KERN RIVER GAS TRANSMISSION COMPANY, a Delaware corporation. Plaintiff, v. MANOR AT ALIANTE HOMEOWNERS ASSOCIATION, a Nevada nonprofit corporation; and a 50-FOOT-WIDE EASEMENT CROSS A PORTION OF THE SOUTH OF SECTION 19, TOWNSHIP OF 19 SOUTH, RANGE 61 EAST M.D.M, Defendants.
GIBBS GIDEN LOCHER TURNER, SENET & WITTBRODT LLP, Richard E. Haskin, Esq., Nevada State Bar # 11592, Attorneys for Defendant MANOR AT ALIANTE HOMED WERS ASSOCIATION. PARSONS BEHLE & LATIMER, John A. Snow, Esq. Nevada Bar #4133, PARSONS BEHLE & LATIMER, Attorneys for Plaintiff KERN RIVER GAS TRANSMISSION COMPANY.
GIBBS GIDEN LOCHER TURNER, SENET & WITTBRODT LLP, Richard E. Haskin, Esq., Nevada State Bar # 11592, Attorneys for Defendant MANOR AT ALIANTE HOMED WERS ASSOCIATION.
PARSONS BEHLE & LATIMER, John A. Snow, Esq. Nevada Bar #4133, PARSONS BEHLE & LATIMER, Attorneys for Plaintiff KERN RIVER GAS TRANSMISSION COMPANY.
STIPULATION AND ORDER TO CONTINUE OPPOSITION AND REPLY DEADLINES TO MOTION FOR SUMMARY JUDGMENT
STIPULATION AND ORDER TO CONTINUE BRIEFING DEADLINES
COMES NOW Defendant MANOR AT ALIANTE HOMEOWNERS ASSOCIATION, a Nevada nonprofit corporation (“Defendant” or the “Association”) and Plaintiff KERN RIVER GAS TRANSMISSION COMPANY, a Delaware corporation (“Kern River” or “Plaintiff') (collectively the “Parties”) by and through their undersigned counsel, and hereby stipulate and agree as follows;
That Association's deadline to file a response to the Kern River's Motion for Summary Judgment should be continued to August 24, 2022.
The deadline for the Kern River to file any reply will be August 31, 2022.
Good cause exists because the Motion for Summary Judgment because the Association requires additional time to evaluate the legal issues and respond thereto.
The continuance is only one (1) week, and no party will be prejudiced thereby.
ORDER
1. GOOD CAUSE APPEARING, AND BY STIPULATION OF THE PARTIES, IT IS HEREBY ORDERED, Defendant MANOR AT ALIANTE HOMEOWNERS ASSOCIATION's deadline to file a response to the Kern River's Motion for Summary Judgment should be continued to August 24, 2022.
2. The deadline for the Plaintiff KERN RIVER GAS TRANSMISSION COMPANY to file any reply will be August 31, 2022.
IT IS SO ORDERED.