Opinion
6:21-cv-200-JA-EJK
07-10-2024
JOHNSON BROS. CORP., Plaintiff, v. WSP USA, INC. and CDM SMITH, INC., Defendants.
ORDER
JOHN ANTOON II UNITED STATES DISTRICT JUDGE
This case is before the Court on Defendant CDM Smith, Inc.'s motion in limine (Doc. 183) and Plaintiffs response (Doc. 197). Having reviewed the parties' submissions, the Court will grant the motion in part, deny it in part, and reserve ruling in part.
I. BACKGROUND
This dispute stems from problems encountered during the design and construction of the Veterans Memorial Bridge in Volusia County, Florida. (Doc. 140 ¶ 1; Doc. 143 ¶ 1; Doc. 153 at 2). In February 2013, the County contracted with Defendant WSP USA, Inc. for design and engineering services on the bridge project. (Doc. 76-1 at 39; Doc. 140 ¶ 3; Doc. 143 ¶ 3; Doc. 153 at 2). Three years later, in February 2016, the County entered into a contract with Plaintiff whereby Plaintiff became the general contractor for construction of the bridge. (Doc. 76-3 at 64; Doc. 140 ¶ 4; Doc. 143 ¶ 2; Doc. 153 at 5). Shortly thereafter, in March 2016, the County contracted with Defendant CDM Smith, Inc. for Construction, Engineering, and Inspection (CEI) services on the project. (Doc. 76-2 at 34; Doc. 140 ¶ 5; Doc. 143 ¶ 7; Doc. 153 at 3).
Whenever Plaintiff encountered a problem during the project that affected Plaintiffs work to the point that Plaintiff wanted reimbursement from the County, Plaintiff submitted an official Notice of Intent to File Claim (NOI) to the County regarding the problem. (See, e.g., Doc. 76-4 at 2). Over the course of the project, Plaintiff submitted multiple NOIs. (Doc. 76 ¶ 23; Doc. 140 ¶ 7; Doc. 143 ¶¶ 13-15; see Doc. 153 at 9).
Initially in this lawsuit, Plaintiff sued only the County, (see Docs. 1, 9, 13, 36, & 70), alleging that the County “rejected or failed to respond to” claims raised in various NOIs, (Doc. 13 ¶¶ 10-11; Doc. 36 ¶¶ 10-11; Doc. 70 ¶¶ 10-11). The County filed a third-party complaint against WSP foi- indemnification, breach of contract, and negligence. (See Doc. 45). Eventually, Plaintiff settled with the County, and under the settlement agreement, the County assigned to Plaintiff rights to sue WSP and CDM for damages related to the project. (Doc. 76-49 §§ 2.1, 8.1). Plaintiff then sued WSP and CDM in Plaintiff s own right and as the County's assignee. (See Doc. 76). Recently, Plaintiff settled with WSP, (see Doc. 208), and in settling, Plaintiff “resolved in their entirety” some of the claims against CDM, (Doc. 209 at 1-2).
Plaintiff now asserts claims against CDM in connection with nine NOIs:; NOIs 3, 8, 13, 18, 20, 26, 35, 44, and 47. (Id. at 2). NOI 3 involves a prohibition on jetting, (Doc. 76 ¶ 23a)-a method of installing piling (structural support for bridges) that uses pressurized jets of water to loosen soil, (Doc. 137-4 at 4-5). NOI 8 involves broken piling. (Doc. 76 ¶ 23b). NOIs 13, 18, and 44 involve cracking in four piers. (Id. ¶¶ 23c-d, 23m). NOI 20 involves delays related to the i project's erection plan, (id. ¶ 23e)-a plan that sets out the sequence of construction operations for a project while accounting for safety and structural stability during construction, (see Doc. 156-1 at 1.5-16, 22; see also Doc. 137-4 at 19-22). NOIs 26 and 35 involve problems with the construction of pier caps and a fishing pier, respectively. (Doc. 76 ¶¶ 23g, 23j). And NOI 47 seeks interest due under the Local Government Prompt Payment Act (the Act), (id. ¶ 23p). See Fla. Stat. § 218.735.
For each NOI, Plaintiff brings breach-of-contract and contractual-indemnification claims as the County's assignee and a negligence claim in its own right under Florida common law. (See Doc. 76 ¶ 26; see, e.g., id. ¶¶ 56-76 i (the three counts against CDM related to NOI 3)). As the County's assignee, Plaintiff also asserts general-indemnification claims. (Id. ¶¶ 694-706). Among the damages that Plaintiff seeks are lost opportunity costs, which represent the investment loss that Plaintiff allegedly suffered when, instead of investing money “in its corporate business,” it spent that money on the project because of delays, inefficiencies, and extra work caused by Defendants' conduct. (Doc. 1709 at 48). Plaintiff also seeks to recover-through its indemnification claims- the attorney fees that the County incurred in defending against Plaintiffs claims. (See, e.g., Doc. 76 ¶ 670). CDM now moves to exclude several categories of evidence.
II. LEGAL STANDARD
CDM mainly brings its motion pursuant to Federal Rule of Evidence 403. (See Docs. 181 & 183). This rule allows a court to “exclude relevant evidence if [the] probative value [of the evidence] is substantially outweighed by a danger of. . . unfair prejudice, confusing the issues, misleading the jury, undue delay, wasting time, or needlessly presenting cumulative evidence.” Fed.R.Evid. 403. “Because it allows a trial court to exclude evidence that is probative, Rule 403 is ‘an extraordinary remedy which should be used sparingly.'” Aycock v. R.J. Reynolds Tobacco Co., 769 F.3d 1063, 1069 (11th Cir. 2014) (quoting United States v. King, 713 F.2d 627, 631 (11th Cir. 1983)). “Accordingly, the balance [under the rule] should be struck in favor of admissibility.” Id. Courts "look at the [challenged] evidence in [the] light most favorable to its admission, maximizing its probative value and minimizing its undue prejudicial impact.” United States v. Elkins, 885 F.2d 775, 784 (11th Cir. 1989). A “court's discretion to exclude evidence under Rule 403 is narrowly circumscribed.” United States v. Norton, 867 F.2d 1354, 1361 (11th Cir. 1989).
III. DISCUSSION
The motion addresses eight topics: (1) Plaintiff's claims as the County's assignee, (2) lost opportunity cost damages, (3) certification of foundations, (4) Plaintiff s arbitration with a nonparty subcontractor, (5) the County's attorney fees, (6) CDM's purported contractual obligation to detect errors in WSP's deliverables, (7) CDM's purported contractual obligation to act as a neutral judge of Plaintiffs claims, and (8) a prior dispute between Plaintiff and CDM's predecessor company. (See Doc. 183). The Court discusses these topics in turn.
A. Plaintiffs Claims as the County's Assignee
CDM seeks to exclude any reference to Plaintiffs County-assigned claims and to any “damages purportedly sustained by [the] County that were not allocated in” Plaintiffs settlement agreement with the County. (Id. at 4-5 (emphasis omitted); see Doc. 181 at 3-8). CDM argues-based on the settlement agreement-that because the County never incurred damages related to the NOIs at issue in this case, Plaintiff cannot bring claims as the County's assignee. (See Doc. 181 at 3-8; Doc. 183 at 4; see also Doc. 197 at 2-6). CDM made the same argument in its motion for summary judgment. (See Doc. 139 at 25). The Court rejected that argument then for multiple reasons-including that under the settlement agreement, the County “gave Plaintiff valuable consideration in the form of an assignment of rights” so Plaintiff could sue CDM for damages “stem[ming] from the NOIs now at issue in this case,” (Doc. 212 at 14-17)- and rejects it now for the same reasons.
B. Lost Opportunity Cost Damages
CDM seeks to prohibit Plaintiff from presenting lost opportunity cost damages to the jury, contending that such damages are speculative and unreliable. (Doc. 183 at 4-6; see Doc. 181 at 8-11). CDM made this argument in its motion for summary judgment. (Doc. 139 at 22), and the Court rejected it, (Doc. 212 at 25-26). The Court explained that “the record reflect[ed] that [the] calculation of Plaintiffs lost opportunity costs” made by Plaintiffs damages expert was properly “based on Plaintiffs financial data,” that “[t]here [wa]s evidence that CDM's negligent conduct caused Plaintiff damage,” and that the damages expert provided a standard by which the amount of damages could be properly determined. (Id. at 25). See W. W. Gay Meeh. Contractor, Inc. v. Wharfside Two, Ltd., 545 So.2d 1348, 1351 (Fla. 1989). The Court will deny CDM's motion in limine as to lost opportunity cost damages for the same reasons.
C. Certification of Foundations
CDM seeks to exclude any reference to certification of foundations related to resolution of a sign convention error encountered during the project. (Doc. 183 at 4, 10; see Doc. 181 at 15-17). Focusing on its contract with the County, CDM maintains that there is no “evidence that CDM had any obligation to certify foundations.” (Doc. 183 at 10). In response, Plaintiff points to an e-mail from WSP to CDM that contemplates certification of foundations and argues that the e-mail is evidence that “a reasonable, prudent professional” in CDM's position “would have sought certification from [a] geotechnical engineer as part of an independent, peer review to resolve the sign convention error.” (Doc, 197 at 1516). The Court agrees with Plaintiff. CDM's contract required CDM to “adhere to the standard of care applicable to a consultant with the degree of skills and diligence normally employed by a licensed professional in his field or practice performing the same or similar services or [w]ork.” (Doc. 76-2 at 16). The issue of certification of foundations is probative given CDM's duty to adhere to that standard of care. The Court will thus deny CDM's motion in limine on this issue.
D. Plaintiffs Arbitration with the Nonparty Subcontractor
CDM seeks to exclude any evidence of Plaintiffs arbitration with a nonparty subcontractor, as well as any reference to the arbitration award, the attorney fees and costs that Plaintiff incurred in connection with the arbitration, and Florida's wrongful act doctrine, which Plaintiff asserts as the basis for its entitlement to the fees. (Doc. 183 at 4, 6-7; see Doc. 181 at 17-20). In addition to arguing under Rule 403, CDM contends that the arbitration “award is inadmissible hearsay not subject to any exception.” (Doc. 183 at 6). Since settling with WSP, Plaintiff is no longer invoking the wrongful act doctrine or pursuing the attorney fees that Plaintiff incurred in the arbitration. (Doc. 209 at 1-2). Accordingly, the Court will grant CDM's motion in limine as to the arbitration with the nonparty subcontractor.
E. The County's Attorney Fees
CDM seeks to exclude any reference to the County's attorney fees. (Doc. 183 at 7-8). The Court will reserve ruling on this issue and allow the parties to present further argument on it at the pretrial conference.
F. CDM's Purported Contractual Obligation to Detect Errors in WSP's Deliverables
CDM seeks to prohibit Plaintiff from arguing to the jury that CDM's contract with the County required CDM to “detect material errors and omissions in WSP's deliverables.” (Doc. 183 at 8-9). CDM asserts that this issue is for the judge rather than the jury because the “language of CDM's contract ... is not reasonably susceptible to more than one interpretation” given the contract's definition of “deliverable.” (See id.). In response, Plaintiff contends that a "plain and ordinary reading” of CDM's contract with the County “reflects that CDM agreed to recognize material errors and/or omissions in the drawings and specifications prepared by WSP and to identify those errors to [the] County to prevent a failure in the deliverables on the [p]roject.” (Doc. 197 at 23-24). Because the contract's definition of “deliverable” is not a model of clarity and resolving this issue requires the Court to consider the interplay of different provisions in the contract, the Court will reserve ruling on the issue and allow the parties to present further argument on it at the pretrial conference.
G. CDM's Purported Contractual Obligation to Act as a Neutral Judge of Plaintiffs Claims
CDM seeks to prohibit Plaintiff from arguing to the jury that CDM was required under its CEI contract to act as a “neutral” or “impartial” judge of Plaintiffs claims or of NOIs. (Doc. 183 at 10-12). To be clear, earlier in this action, when the Court ruled on CDM's Daubert motion (Doc. 137), the Court held that one of Plaintiffs engineering experts could opine on “the purported expectation that a CEI act as an impartial honest broker on a project.” (Doc. 204 at 9-10). And that ruling still stands. However, the instant dispute about referring to CDM as an impartial judge concerns contractual language requiring CDM to “judge” Plaintiffs performance under the construction contract. (See Doc. 197 at 25-27). Plaintiff maintains that CDM's contractual duty to judge its performance carried a “duty of impartiality.” (Id. at 26). But that reading cannot be squared with the plain meaning of the contract's language. See Corp. Creations Int'l, Inc. v. Marriott Int'l, Inc., 276 So.3d 36, 38 (Fla. 4th DCA 2019) (applying the language of a contract “as written” when that language was “clear and unambiguous”). Accordingly, the Court will grant CDM's motion as to this issue.
Daubert v. Merrell Dow Pharms., Inc., 509 U.S. 579 (1993).
H. Prior Dispute Between Plaintiff and CDM's Predecessor
CDM seeks to exclude any reference to a prior dispute between Plaintiff and CDM's predecessor company related to a different bridge construction project, including any reference to the arbitration award associated with that dispute, which was entered in Plaintiffs favor against CDM. (Doc. 183 at 12- 13; see Doc. 197-21). The Court will reserve ruling on the issue and allow the j parties to present further argument on it at the pretrial conference.
IV. CONCLUSION
Accordingly, it is ORDERED that CDM's motion in limine (Doc. 183) is GRANTED in part and DENIED in part, and the Court reserves ruling in part.