JM Holdings 1 LLC (“JM”) and Cedar Holdings, LLC (“Cedar”), brought this action against Quarters Holding GmbH (“Quarters”), alleging breach of contract and other related claims. Now, JM and Cedar (together, “Plaintiffs”) move for entry of a final default judgment against Quarters in the amount of $8,783,337.58 [post-judgment interest is automatic, so no need to say anything about it; pre-judgment interest is not automatic]. For the reasons that follow, the motion is granted.
I. Background
The following background facts are taken from the amended complaint. (See Dkt. No. 16 (“Compl.”).) For a more detailed recitation of the relevant facts, see the Court's prior opinion and order denying Quarters' motions to dismiss and to impose sanctions. (See Dkt. No. 38.)
This case concerns a multifamily property located at 251 DeKalb Avenue in Brooklyn, New York, which Plaintiffs own and manage. (Compl. ¶¶ 1,7-9, 18.) In July of 2019, Plaintiffs agreed to lease the property to a shell company controlled by Quarters. (Compl. ¶¶ 11-13, 21.) As part of the agreement, Plaintiffs agreed to renovate the property. (Compl. ¶¶ 21, 22.) These renovations were originally to have been completed by the end of November 2019, but construction delays pushed them into early 2020. (Compl. ¶¶ 22, 24.) Through these delays, Quarters represented that it still intended to occupy the property and encouraged Plaintiffs to continue investing in renovations. (Compl. ¶¶ 26, 27.)
The shell company is Medici 251 DeKalb LLC (“Medici”). Because Medici is a shell company, Plaintiffs in fact dealt solely with agents of Quarters. For the sake of simplicity, the Court here uses “Quarters” to refer to both Quarters and Medici. (See Dkt. No. 22 at 9).
Then, COVID-19 hit New York City and Quarters reversed course. Quarters refused to sign a certificate that Plaintiffs needed to obtain financing unless Plaintiffs stipulated that they were in default for failing to complete renovations by the originally projected date of November 30, 2019, or they signed a “side-letter” to that effect. (Compl. ¶¶ 32, 38-40.) When Plaintiffs refused, Quarters informed them it would be terminating the lease. (Compl. ¶ 41.)
Plaintiffs brought this action on May 4, 2020, alleging that Quarters breached its guaranty of the lease and acted in bad faith. (See Dkt. No. 1.) Quarters appeared and moved to dismiss on May 22, 2020, after which Plaintiffs filed an amended complaint on June 12, 2020. (See Dkt. Nos. 7-12, 16.) Quarters again moved to dismiss and for sanctions. (See Dkt. Nos. 17, 25.) This Court denied both of Quarters' motions on March 8, 2021, and directed Quarters to answer, which Quarters did on March 29, 2021. (See Dkt. Nos. 38, 43.) Though Quarters had waived challenge to service of process by appearing in the action, Plaintiffs served Quarters under the Hague Convention on September 16, 2021, and filed proof of this service on the docket on September 30, 2020. (See Dkt. No. 59-1.)
On April 21, 2021, the Court granted the request of Quarters' counsel, Akerman LLP, to withdraw as counsel and ordered Quarters to have new counsel appear within 30 days or risk default. (See Dkt. 48.) Akerman served this order on a Quarters representative on August 22, 2021. (See Dkt. No. 49.) Yet no new counsel appeared, and Quarters ceased its defense in this action. On October 10, 2021, the Clerk of Court entered a certificate of default. (See Dkt. No. 60.) Plaintiffs moved for a default judgment against Quarters on October 15, 2021 and served the default judgment papers on Quarters by mail on October 18, 2021. (See Dkt. Nos. 61, 64.)
II. Discussion
A party “against whom a judgment for affirmative relief is sought” is in default when it “has failed to plead or otherwise defend.” Fed.R.Civ.P. 55(a). As a “default is an admission of all well-pleaded allegations against the defaulting party . . . a district court must accept as true all of the factual allegations of the non-defaulting party and draw all reasonable inferences in its favor.” Belizaire v. RAV Investigative and Sec. Servs. Ltd., 61 F.Supp.3d 336, 344 (S.D.N.Y. 2014) (quotation marks omitted). Nonetheless, a district court must “determine whether the [plaintiff's] allegations establish [the defendant's] liability as a matter of law.” Id. (quoting Finkel v. Romanowicz, 577 F.3d 79, 84 (2d Cir. 2009)). “[A] default judgment entered on well-pleaded allegations in a complaint establishes a defendant's liability.” Id. (quoting Trans World Airlines, Inc. v. Hughes, 449 F.2d 51, 69 (2d Cir. 1971), rev'd on other grounds, 409 U.S. 363 (1973)).
Notably, this Court has already concluded that Plaintiffs adequately pleaded their allegations in the Complaint. (See Dkt. No. 38 at 11-13, denying Quarters' Motion to Dismiss the Complaint.) “To determine whether the plaintiff's allegations are well pleaded [for purposes of a default judgment], the Court applies the same standards that govern a motion to dismiss under [Rule] 12(b)(6).” Conan Props. Int'l LLC v. Sanchez, 2018 WL 3869894, at *2 (E.D.N.Y. Aug. 15, 2018) (citing Steginsky v. Xclera Inc., 741 F.3d 365, 368 (2d Cir. 2014)). Therefore, the Court concludes that Quarters' liability has been established as a matter of law and Plaintiffs are entitled to the relief they seek. Plaintiffs seek $8,783,337.58 in monetary relief, which is the amount of the base rent for the duration of Quarters' aborted lease, less the amount Quarters had already paid as a security deposit. (See Dkt. No. 62-5.)
III. Conclusion
For the foregoing reasons, Plaintiffs' motion for default judgment is GRANTED. Plaintiffs are awarded judgment against Quarters in the amount of $8,783,337.58, plus post-judgment interest at the statutory rate. The Clerk of Court is directed to enter judgment accordingly.
The Clerk is respectfully directed to close the motion at Docket Number 61, to enter final judgment, and to close this case. Plaintiffs are directed to serve a copy of this Order on Quarters.
SO ORDERED.